Drummond Company, Incorporated (ALJ decision, May 19, 1999)

Drummond Company, Incorporated (FMSHRC SE 99-39): Settlement approved and penalties modified

Decision type
ALJ decision
Docket
SE 99-39
Decided
May 19, 1999
Presiding judge
Outcome
Settled
Precedential status
Final order, not precedent
Checked against source
2026-08-11

Apply this to your situation

This order from 1999 bound only the parties to this case; it isn't precedent. Ask about your situation and see what the current MSHA standards and Commission precedent say, with citations.

Currency note: this decision dates from 1999
The MSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Final order, not Commission precedent
This decision by a FMSHRC Administrative Law Judge became the final decision of the Commission 40 days after issuance because the Commission did not direct review (30 U.S.C. § 823(d)(1)). It binds the parties but is not binding on the Commission in other cases. The full text below is from the official FMSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official FMSHRC release. The full text is the agency's own release.
Read the official release (fmshrc.gov)

Plain-English summary

Drummond Company and the Secretary jointly asked the Judge to approve settlements involving coal and coal-dust accumulations and underground diesel-fuel storage at the Shoal Creek Mine. The proposed total penalty was reduced from $6,000 to $2,950, with the parties also seeking to change two 104(d)(1) matters to 104(a) citations, remove unwarrantable-failure findings, and reduce negligence findings. The parties explained that one accumulation resulted from water on a slope belt and that the operator had invested in repairs and additional cleanup. The Judge found the settlements appropriate under the statutory penalty criteria, approved them, modified the matters identified in the operative order, and ordered payment of $2,950 within 30 days.

Decision snapshot

  • Cited standards: 30 C.F.R. §§ 75.400 and 75.1903(a)(2)
  • Outcome: The settlement was approved, specified enforcement findings were modified, and a $2,950 penalty was ordered.
  • Key point: A settlement may modify violation classifications, negligence findings, and penalties when supported by the statutory penalty criteria.

Full text (FMSHRC public release)

FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION

1730 K STREET, N.W., 6TH FLOOR

WASHINGTON, D. C. 20006-3868

May 19, 1999

SECRETARY OF LABOR
: CIVIL PENALTY PROCEEDING
MINE SAFETY AND HEALTH :
ADMINISTRATION (MSHA), : Docket No. SE 99-39 Petitioner : A. C. No. 01-02901-03658 :
v. :
:
DRUMMOND COMPANY,
: Shoal Creek Mine
INCORPORATED,
:
Respondent :

DECISION APPROVING SETTLEMENT
ORDER TO MODIFY
ORDER TO PAY

Before: Judge Merlin

This case is before me upon a petition for assessment of the civil penalties filed under section 105(d) of the Federal Mine Safety and Health Act of 1977. The parties have filed a joint motion to approve settlements. A reduction in the penalties from $6,000 to $2,950 is proposed.

Order No. 4477477 was issued under section 104(d)(1) of the Mine Act for a violation of 30 C.F.R. § 75.400 because loose coal and coal dust accumulated at various locations in the bleeder roadway. The originally assessed penalty was $1,000 and the proposed settlement is $100. The parties advise that MSHA modified the violation from a 104(d)(1) order to a 104(a) citation, deleted the unwarrantable failure finding and reduced negligence from high to low prior to the assessment of a penalty. However, these modifications were not considered when the penalty was calculated by MSHA. Therefore, the reduction reflects the penalty that would have been assessed had MSHA considered the changes to the violation.

Order No. 4477476 was issued under section 104(d)(1) of the Mine Act for a violation of 30 C.F.R. § 75.1903(a)(2) because the underground diesel fuel storage facilities were not provided with self-closing doors. The violation was designation non-significant and substantial and resulted from the operator's unwarrantable failure. The originally assessed penalty was $1,000 and the proposed settlement is $100. In their joint motion the parties request that the violation be modified from a 104(d)(1) order to a 104(a) citation, that the unwarrantable failure finding be deleted and that negligence be reduce from high to moderate. The parties advise that there is no evidence that the operator was aware or should have been aware of this condition nor is there evidence indicating how long this condition existed. Finally, the parties state that the area was inspected daily by the operator and there is no record that the doors were inoperative or in need of repair.

Citation No. 4480767 was issued under section 104(d)(1) of the Mine Act for a violation of 30 C.F.R. § 75.400 because coal and coal dust accumulated along both sides of the slope belt for approximately 4,500 feet. The citation further notes that the fire boss book contained notes that the slope belt needed cleaning on each shift for the two weeks prior to the issuance of the citation. The violation was designated significant and substantial and that it resulted from the operator's unwarrantable failure. The originally assessed penalty was $4,000 and the proposed settlement is $2,750. The parties request in their motion that the violation be modified from a 104(d)(1) citation to a 104(a) citation, that the unwarrantable failure finding be deleted and that negligence be reduced from high to moderate. The parties advise that the accumulations were caused when the longwall sections encountered water problems resulting in water being transported along with the coal on the conveyor system. While traveling up the incline of the slope belt, coal and water would frequently wash off the conveyor onto the mine floor.

The parties advise in their joint motion that at the time of the violation the operator was in the process of addressing the problems with the slope belt. According to the motion, the operator had committed to spending $217,000 for the repair of the surge bin which is used to maintain an even distribution of coal throughout the length of the slope belt. The operator also purchased and installed a mini-conveyor system at the bottom of the slope to return coal fines and spillage back onto the slope belt. (It subsequently ordered a second mini-conveyor). Finally, the operator had attended to the accumulations along the slope belt by assigning additional personnel to keep the area clean. The motion states that these facts were unknown to MSHA when the citation was issued.

I have considered the representations and documentation submitted in this case, and I conclude that the proffered settlements are appropriate under the criteria set forth in section 110(i) of the Act.

In light of the foregoing, the motion for approval of settlements is GRANTED.

It is ORDERED that Order No. 4477476 be MODIFIED from a 104(d)(1) order, to delete the unwarrantable failure finding and to reduce negligence from high to moderate.

It is further ORDERED that Citation No. 4480767 be MODIFIED from a 104(d)(1) citation, to delete the unwarrantable failure finding and to reduce negligence from high to moderate.

It is further ORDERED that the operator pay a penalty of $2,950 within 30 days of this decision.

Paul Merlin
Chief Administrative Law Judge

Distribution:

William Lawson, Esq., Office of the Solicitor, U. S. Department
of Labor, Suite 150, Chambers Building, Highpoint Office Center, 100 Centerview Drive, Birmingham, AL 35216

David M. Smith, Esq., Maynard, Cooper & Gale, P.C., 1901 Sixth Avenue North, 2400 Am South/Harbert Plaza, Birmingham, AL 35203-2618

Mr. Sammy O. Key, UMWA, 986 Underwood Ferry Road, Cordova, AL 35550

/gl

FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION 1730 K STREET NW, 6TH FLOOR WASHINGTON, D.C. 20006-3868

William Lawson, Esq.
Office of the Solicitor
U. S. Department of Labor
Suite 150, Chambers Building
Highpoint Office Center
100 Centerview Drive
Birmingham, AL 35216

FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION 1730 K STREET NW, 6TH FLOOR WASHINGTON, D.C. 20006-3868

David M. Smith, Esq.
Maynard, Cooper & Gale, P.C.
1901 Sixth Avenue North
2400 Am South/Harbert Plaza
Birmingham, AL 35203-2618

FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION 1730 K STREET NW, 6TH FLOOR WASHINGTON, D.C. 20006-3868

Mr. Sammy O. Key, UMWA
986 Underwood Ferry Road
Cordova, AL 35550

What applies to your situation today?

This order bound one employer. Ezel checks the current MSHA standards and Commission precedent against your facts, with citations.

Opens in Ezel Pro.

  • Checks the law as it stands today, not only this page
  • Cites every source it relies on, so you can verify it
  • Chat, drafting and research in one workspace