Burgess Mining and Construction Corporation (Commission decision, March 18, 1980)

Burgess Mining and Construction Corporation (FMSHRC SE 79-42-R): Motion to vacate review denied

Decision type
Commission decision
Docket
SE 79-42-R
Decided
March 18, 1980
Outcome
Procedural
Precedential status
Citable Commission precedent
Checked against source
2026-10-23

Apply this precedent to your situation

This is citable Commission precedent from 1980, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.

Currency note: this decision dates from 1980
The MSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Decision of the Commission on a pending review, not a final decision on the citation
The Commission denied Burgess's motion to vacate its direction for review because the Secretary's brief was timely. Review continued, and the Commission later decided the citation in `se-79-42-r-commission`. The full text below is from the official FMSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official FMSHRC release. The full text is the agency's own release.
Read the official release (fmshrc.gov)

Plain-English summary

Burgess Mining and Construction asked the Commission to cancel its direction for review after the Secretary mailed a brief 25 days after that direction. Burgess relied on a rule requiring a petitioner to file a brief within 20 days. The Commission held that another rule added five days because the Secretary had been served by mail, making the brief timely. It denied Burgess's motion and continued its review; this order did not decide the underlying citation or assess a penalty.

Decision snapshot

  • Governing provisions: 29 C.F.R. §§ 2700.72, 2700.8(b), and 2700.1(c).
  • Outcome: Motion to vacate the direction for review denied; the underlying citation remained for later decision.
  • Key point: Five days were added to the briefing period when the direction for review was served by mail.

Full text (FMSHRC public release)

CCASE:
SOL V. BURGESS MINING & CONSTRUCTION
DDATE:
19800218
TTEXT:

FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION WASHINGTON, DC
March 18, 1980

RAY MARSHALL. SECRETARY OF LABOR
UNITED STATES DEPARTMENT OF
LABOR

v. Docket No. SE 79-42-R

BURGESS MINING AND CONSTRUCTION
CORPORATION

ORDER

Burgess Mining and Construction Corporation has moved to vacate the direction for review. Burgess asserts that the Secretary's failure to file his brief within 20 days after our granting of his Petition for discretionary review is governed by 29 CFR 2700.72. That rule requires the petitioner to file its brief within 20 days of the granting of a direction for review and provides that if the Petitioner fails to do so, the direction for review may be vacated.

The Secretary filed his brief by mail 25 days after our order directing review. The Secretary argues that his brief was timely filed and cites 29 CFR 2700.8(b), which provides:

when service of a document is by mail, 5 days shall be added to the time allowed by these rules for the filing of a response or other document.

While we are concerned with any undue delay in the proceedings before us and construe our rules so as to expedite matters wherever possible, we also are bound to interpret our rules so as to secure just determinations. 29 CFR 2700.1(c). Rule 8(b) was promulgated to ensure, as far as possible, that Parties served by mail not be deprived, through the vagaries of the post, of time elsewhere allowed in our rules for the preparation and filing of responses.
~777
The Secretary was served by mail with our direction for review. Under Rule 8(b), 5 days may properly be added to the 20 days allowed under Rule 72 within which to file his brief in response to our direction. 1/ His brief, which was filed by mail on the 25th day, was therefore timely.

Accordingly, the motion to vacate is denied.

1/ Rule 8(b) does not, however, apply to the 30 day statutory period for filing a PDR after issuance of a judge's decision. See our order dismissing the PDR in Sunbeam Coal, PITT 79-210 thru 214 (March 10, 1980).

Does this precedent still control your case?

Ezel checks whether it still stands, including any court review since, and applies it to your situation with citations.

Opens in Ezel Pro.

  • Checks the law as it stands today, not only this page
  • Cites every source it relies on, so you can verify it
  • Chat, drafting and research in one workspace