FMSHRC ALJ decision Docket SE 2016-0218 RM, SE 2016-2019 RM, SE 2016-0246 Decided April 15, 2021 Citations affirmed Judge Priscilla M. Rae

Jones Brothers, Inc. v Secretary of Labor and Secretary of Labor v. Jones Brothers, Inc.

Jones Brothers, Inc. v. Secretary of Labor (FMSHRC SE 2016-0218 RM): Road-project excavation held to be a mine

Apply this to your situation

This order from 2021 bound only the parties to this case; it isn't precedent. Ezel answers your situation under the current MSHA standards and Commission precedent, with citations.

Final order, not Commission precedent
This decision by a FMSHRC Administrative Law Judge became the final decision of the Commission 40 days after issuance because the Commission did not direct review (30 U.S.C. § 823(d)(1)). It binds the parties but is not binding on the Commission in other cases. The full text below is from the official FMSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official FMSHRC release. The full text is the Commission's own document.
Read the official release (fmshrc.gov)

Plain-English summary

Jones Brothers excavated limestone for a Tennessee highway repair project by drilling, blasting, breaking oversized rock, separating dirt, and selecting rock that met state size and drainage specifications. The company argued that the site was a borrow pit outside MSHA jurisdiction. After a new hearing ordered by the Sixth Circuit, Judge Priscilla M. Rae held that the operation extracted, milled, and prepared minerals and did not meet the borrow-pit exception because work was frequent and the rock was processed for its intrinsic properties. She upheld two withdrawal orders and seven citations covering mine notification, legal identity and quarterly reporting, miner training, an unlabeled fuel can, a defective backup alarm, and the absence of a stand-off tire-inflation device. The assessed negligence levels were sustained, and Jones Brothers was ordered to pay $2,940.

Decision snapshot

  • Cited standards: 30 C.F.R. §§ 41.11, 46.5(a), 46.8(a)(1), 50.30(a), 56.1000, 56.4402, 56.14104(b)(2), and 56.14132(a)
  • Outcome: All two orders and seven citations were upheld, with a total civil penalty of $2,940.
  • Key point: Repeated extraction and processing of rock to meet highway specifications was mining, not an exempt borrow-pit operation.

Full text (FMSHRC public release)

FEDERAL MINE SAFETY AND HEALTH
REVIEW COMMISSION

OFFICE OF ADMINISTRATIVE
LAW JUDGES

1331 PENNSYLVANIA AVE.,
N.W., SUITE 520N

WASHINGTON, DC
20004-1710

TELEPHONE: 202-434-9956
/ FAX: 202-434-9949

April 15, 2021

JONES
BROTHERS INC.,

Contestant,

v.

SECRETARY
OF LABOR

MINE
SAFETY AND HEALTH      

ADMINISTRATION
(MSHA),

Respondent.

SECRETARY
OF LABOR

MINE
SAFETY AND HEALTH      

ADMINISTRATION
(MSHA),

Petitioner,

v.

JONES
BROTHERS INC.,

Respondent.

CONTEST
PROCEEDINGS

Docket
No. SE 2016-0218-RM

Citation
No. 8817595; 04/06/2016

Docket
No. SE 2016-0219-RM

Citation
No. 8817596; 04/06/2016

Mine:
Jones Brothers Mine

Mine
ID: 40-03454

CIVIL PENALTY PROCEEDING

Docket
No. SE 2016-0246

A.C.
No. 40-03454-410595

Mine:
Jones Brothers Mine

DECISION AND ORDER

Appearances:              Willow
E. Fort, Esq., Office of the Solicitor, U.S. Department of Labor, Arlington,
Virginia, for the Petitioner

Douglas
R. Pierce, Esq. and Michael D. Oesterle, Esq., King & Ballow, Nashville,
Tennessee, for the Respondent

Before:                        Judge
Rae

This case is before me upon a
petition for assessment of civil penalty filed by the Secretary of Labor (“Secretary”)
pursuant to Section 105(d) of the Federal Mine Safety and Health Act of 1977,
as amended, (“Mine Act” or “Act”), 30 U.S.C. § 815(d). At issue are two orders under
section 104(g) of the Mine Act and seven citations under section 104(a), issued
to Respondent Jones Brothers, Inc. (“Respondent”).

Respondent contested the citations
and orders, arguing that the excavation site was not a “mine” subject to MSHA
jurisdiction. Answer at 1. Previously, Federal Mine Safety and Health Review
Commission Administrative Law Judge Margaret Miller ruled that Respondent’s
operation was subject to the Mine Act. 39 FMSHRC 399 (Feb. 2017) (ALJ). On
April 13, 2017, the Commission denied Respondent’s Petition for Discretionary
Review. Respondent then successfully appealed to the United States Court of
Appeals for the Sixth Circuit. Jones Bros. Inc. v. Sec’y of Labor , 898
F.3d 669 (6th Cir. 2018) (holding that ALJ Miller was not constitutionally
appointed and that Respondent was entitled to a new hearing before a
constitutionally appointed ALJ).

After this matter was remanded to me,
a hearing was held via Zoom for Government videoconferencing on January 26 and
27, 2021, at which time testimony was taken and documentary evidence was
submitted. Additionally, the parties submitted post-hearing briefs. Tr. II at

  1. [1]
    I have reviewed all the evidence at length and have cited to the testimony,
    exhibits, and arguments I found critical to my analysis and ruling herein
    without including a detailed summary of the testimony given.

After consideration of the evidence,
and observation of the witnesses and assessment of their credibility, I find
that I have jurisdiction over this matter because it involves a “mine” under
the Mine Act, and I uphold the citations and orders for the reasons set forth
below.

I.                
FINDINGS
OF FACT

A.     Background

This matter concerns Respondent’s
open-pit excavation site in DeKalb County, Tennessee. Tr. I at 84–85, 89–90. Respondent’s
employees worked at the site up to six days a week from August 2015 to August
2016. Tr. I at 94, 230, 291; Ex. S-25. Respondent was excavating at the site in
support of its contract with the Tennessee Department of Transportation (“TDOT”)
to repair “slide” damage [2]
to nearby State Route 141. Tr. I at 26; Ex. S-26; Ex. S-27. The contract
required Respondent to obtain approximately 68,615 tons of “graded solid rock”
to complete the road repair. Ex. S-26 at 59; Ex. S-27 at 4. TDOT’s Standard
Specifications for Road and Bridge Construction (“Standard Specifications”) define
graded solid rock as “sound,
non-degradable rock having the following characteristics”: (1) “[m]aximum
particle size of 3 feet in any direction”; (2) “[p]article size distribution in
which at least 50% of the rock is uniformly distributed between 1 foot and 3
feet in diameter, and no more than 10% is less than 2 inches in diameter”; (3)
“[r]oughly equi-dimensional in shape”; and (4) “[n]o thin, slabby material.” Ex.
S-28 at 10–11. Further, the Standard Specifications require that graded solid
rock be processed “using an acceptable method that produces the required
gradation” and that “the weighted percentage of loss shall not be more than 12”
when “subjected to five alterations of the sodium sulfate soundness test.” Ex.
S-28 at 11. Finally, the Standard Specifications require “the [e]ngineer’s approval
before using the material.” Id.

Respondent contracted with a nearby
property owner to obtain graded solid rock by excavating on his property. Tr. I
at 214; Ex. S-3 at 8–9. The property was less than one mile from the road
repair site. Tr. I at 103–04, 220, 239, 258, 307, 366. Respondent used core
drilling [3]
to obtain a rock sample and then submitted the sample to TDOT, who confirmed
that the sample qualified as graded solid rock. Tr. I at 227–28. After the rock
sample was approved, Respondent began preparing the excavation site on or about
August 10, 2015. Tr. I at 93–94, 279–80; Ex. S-3 at 14. Respondent cleared the
overburden—the timber, dirt, and rock above the graded solid rock—and then created
roadways and benches. Tr. I at 254–55, 281–84.

After preparation, Respondent started
the extraction process by drilling blast holes and “shooting” the blast holes with
explosives to expose the underlying material. Tr. I at 282–84. The underlying
material consisted of limestone rock, as well as mud and dirt seams. Tr. I at
84, 108–09, 218, 225, 256, 302, 304–06, 310, 317; Tr. II at 50–52. During extraction,
oversized rocks that were “as large as a pickup truck” were blasted loose. Tr.
I at 260, 306; Tr. II at 54. After blasting, Respondent used an excavator-mounted
piece of hydraulic equipment known as a hoe ram to break up some of the larger rocks.
Tr. I at 100, 230, 241–42, 259. Respondent then used excavators to load the material
onto dump trucks, using either a slotted [4]
or standard (solid) excavator bucket. Tr. I at 185, 220, 264. The slotted
bucket allowed undersized material to fall through the slots, leaving
appropriately sized rocks and limiting the presence of dirt. Tr. I at 102–03,
117–18, 220–21, 229–30, 271–72, 308, 333; Tr. II at 16–17, 31–32, 37–40, 53–54.
Respondent used the slotted bucket to remove dirt because TDOT did not permit
the presence of dirt in graded solid rock. Tr. I at 225–26, 271–72, 304–06. After
being loaded, the dump trucks transported the graded solid rock to the road
repair site, where it was deposited and compacted by a bulldozer. Tr. I at
239–40, 258, 316, 319.

On April 5, 2016, MSHA Inspector Danny
Williams [5]
inspected Respondent’s excavation site after witnessing it from a nearby road. Tr.
I at 88–89. During
the inspection, Inspector Williams spoke with Respondent’s employees. Tr. I at 121.
One employee allegedly told Inspector Williams of a discussion the employee had
with Respondent’s management regarding the possibility that the operation would
be subject to MSHA jurisdiction. Tr. I at 121–22. The employee also allegedly stated
that Respondent’s management dismissed the employee’s concerns by stating
something to the effect of “we’re going to call it a borrow pit.” [6]
Id. After
observing and photographing Respondent’s operations, Inspector Williams
returned on April 6, 2016 and issued the nine citations and orders at issue in
this matter. See infra Section III.B; Ex. S-4, S-6, S-9, S-11, S-13,
S-15, S-17, S-20, S-22.

B.     Credibility
Findings

Reviewing the record of these proceedings
compels me to address and make findings on the credibility of certain witnesses.
I find that the
testimony of Kevin Hinson, Anthony Williams, Kevin Williams, and Jimmy Givens tended
to be contradictory and not credible in several respects. Further, I credit the
testimony of Inspector Williams and Stephen Wright.

i.          
Testimony
of Kevin Hinson

On direct examination, project
manager Kevin Hinson [7]
stated that he picked up a piece of rock at the excavation site to have it
tested by TDOT to determine whether it qualified as graded solid rock. Tr. I at
215, 217. Hinson also agreed with Respondent’s counsel that every time Hinson
was required to obtain rock at other job sites for TDOT to test, Hinson was
able to find suitable rock. Tr. I at 217. However, Hinson also admitted on
cross-examination that Respondent performed core drilling “to ensure that the
rock would meet TDOT requirements,” and that TDOT performed a visual test of
the rock to ensure that it was not “thin or slabby” and “up to the inspector’s
preference.” Tr. I at 227–29.

Regarding Respondent’s use of the
hoe ram, Hinson first agreed on cross-examination that Respondent used the hoe
ram to break rock. Tr. I at 230. Then, on redirect, Hinson stated that Respondent
used the hoe ram “to break the larger rock that we could not move . . . to get
it out of the way and load the other material that we wanted.” Tr. I at 232. Hinson
later stated on recross-examination that if rock broken up by the hoe ram was
“small enough, then yes, it could have been” loaded up and taken to the road
site. Tr. I at 233. Hinson then contradicted himself again on redirect by
stating that Respondent “couldn’t afford to break rock with a hoe ram and make
it cost efficient.” Tr. I at 234. I find that Hinson’s contradictions—coupled
with his answers to Respondent’s counsel’s leading questions—make his testimony
not credible.

ii.          
Testimony
of Anthony Williams

The testimony of Foreman Anthony
Williams [8]
contained many contradictions. First, with respect to the hoe ram, Anthony
Williams testified that Respondent used the hoe ram “just to break the bigger
rocks that we couldn’t handle to move them out of the way” and to break large
rocks that were too big for the bulldozer to move. Tr. I at 259–61. This
testimony conflicts with the testimony of bulldozer operator Jimmy Givens—who stated
that he used the bulldozer to move large rocks—and excavator operator Kevin
Williams—who stated that he pushed large rocks out of the way. Tr. I at 306,

  1. Anthony Williams also stated “it would have to be me” when asked “who
    would be operating the hoe ram?” Tr. I at 261. However, Anthony Williams later
    agreed that “[a]t least one other person . . . did operate the hoe ram.” Tr. I
    at 272.

Second, Anthony Williams testified
that the only purpose of the slotted bucket was to remove dirt from the blasted
material. Id. Several other witnesses testified that the slotted bucket
not only removes dirt but is also a form of selecting appropriately sized
material. Tr. I at 102–03, 117; Tr. II at 14–15, 53–54.

Third, Anthony Williams stated that
despite the quality of the excavated material being “not good” and comparable
to waste at a quarry, the excavated material was used as graded solid rock for
the road repair project. Tr. I at 256–57. This testimony is in conflict with
that of Hinson, who mentioned core drilling and TDOT’s visual inspection to
ensure that the material met the specifications of graded solid rock. Anthony
Williams also admitted on cross-examination that employees of TDOT were on site
“every day” to ensure that the material Respondent was using at for the road
repair qualified as graded solid rock. Tr. I at 275.

Finally, Anthony Williams testified
that Ben Coleman—who served as Respondent’s superintendent of drilling and
blasting—could not control whether the blasted material was too large or too small
and that Coleman could not “help when a big rock falls off.” Tr. I at 260. However,
Coleman himself testified that “to some extent” he had “control over the size
of the rock” that was blasted off and that, depending on the hardness of the
rock and its intended application, the blaster typically develops a drilling
pattern and uses a specific type of explosive charge. Tr. II at 48–50.

In additional to the factual
contradictions above, Anthony Williams was evasive throughout cross-examination
by the Secretary, further diminishing his credibility. E.g. Tr. I at
269–74; Tr. I at 282 (Anthony Williams replied “[i]t drills” in response to
counsel’s question “[a]nd the drill does what?”). Consequently, I find Anthony
Williams’ testimony not credible.

iii.          
Testimony
of Kevin Williams

Comparing the testimony of excavator
operator Kevin Williams [9]
with the testimony of other witnesses reveals contradictions in his testimony. For
example, Kevin Williams stated that “[a]ll the rock was put on the truck if it
fit on the truck.” Tr. I at 309. Additionally, Kevin Williams stated that “if
he couldn’t load” the rocks that were “as big as a pickup truck,” then he would
“just push it to the side.” Tr. I at 306. This contradicts the testimony of other
witnesses who stated that equipment could not move the large rocks, that the
hoe ram was necessary to break the rocks so that they could be moved, and that
rocks broken up by the hoe ram were not loaded onto the trucks. Furthermore, Respondent’s
counsel’s leading questions make Kevin Williams’ testimony less credible. The
following exchange is one example:

Counsel:                      Okay.
Did you ever use a hoe ram to break up those big rock[s] so that you could load
the rock onto the trucks?

Kevin Williams:         No.

Counsel:                      Did
anybody at the S.R. 141 job use the hoe ram to break up the very big rock to
load it onto the truck?

Kevin Williams:         No.

Counsel:                      Now,
when you work at the S.R 141 job, did you load up rock for any other purpose other
than going down to the road that was next to the Caney Fork River?

Kevin Williams:         No.

Tr. I at 306–07.

iv.          
Testimony
of Jimmy Givens

Bulldozer operator Jimmy Givens [10]
agreed with counsel for Respondent’s comparison that “what the quarries considered
trash is what you guys were using . . . as the bulk fill material.” Tr. I at

  1. However, on cross-examination, Givens stated that graded solid rock “is
    usually anything over [two feet] in diameter,” which highlights his lack of
    knowledge regarding TDOT’s requirements for graded solid rock. Tr. I at 321. Further,
    Givens agreed that he was “not someone who was spending much time” at the
    excavation site. Tr. I at 317.

v.          
Testimony
of Stephen Wright

Further, the testimony of Givens
and the testimony of Anthony Williams regarding the properties of graded solid
rock are also at odds with Respondent’s witness Stephen Wright. [11]
Wright testified that TDOT developed the graded solid rock standard in response
to a “massive failure” of Interstate 40 that was “caused by water seeping out
of the ground and undermining the roadway foundation.” Tr. II at 11. Wright
further explained the importance of TDOT’s graded solid rock specification:

Tennessee
developed this graded solid rock spec, which is why you have to take the fines
out of it. They want a rock that is from a 3-foot in diameter maximum down to
about a 6-inch rock is what they would consider perfect because that gives you—and
you put that in and it’s free draining. They basically, in areas where they
believe there are potential for water to—the damage—the interface between the
field material you place and the natural ground, they will put this product in.
And to their credit, it’s expensive, they do it more than most other states,
but their roads stay there when they do that. They had a couple of high-profile
failures and this was determined to be the best method. So when you take those
big rocks and lay them down and they have a higher interlocking angle, a phi
angle it’s called, and it makes it much stronger and the water can free—flow
freely . . . through it and that gives just a tremendously stable base for the
rock.

Tr.
II at 11–12. I find Wright’s testimony regarding the properties of graded solid
rock to be credible. Wright’s testimony underscores the fact that Respondent
was required to use graded solid rock for the road repair due to its intrinsic
value—namely, for building a strong foundation and for allowing water to flow
freely through it—which was important where the road had previously become
unstable due to water damage. It is unlikely that the low quality material mentioned
by Anthony Williams and Jimmy Givens would suffice for such a project. [12]

In sum, I find that the contradictions by several
of Respondent’s witnesses—within their own testimony and when compared to the
testimony of other witnesses—makes them less credible. It is not credible that Respondent
only used the hoe ram to break up rocks for the purpose of moving them out of
the way.
I find that the hoe ram was used to reduce excavated material in size for the
purpose of using at least some of that material as graded solid rock. Despite
Respondent’s contentions and Hinson’s testimony, it would not be
profitable to not utilize the rocks crushed with the hoe ram as graded
solid rock. Resp’t Br. at 18, 21. This finding comports with the testimony
of Inspector Williams, who stated that he observed Respondent’s excavator “picking
up rocks that looked like they had been crushed with a hoe ram[] . . . and . .
. loading them onto the Mack dump truck.” Tr. I at 108. The observations
of Inspector Williams are entitled to significant weight. Harlan Cumberland
Coal Co .,
20 FMSHRC 1275, 1278-79 (Dec. 1998).

Further, I find that the slotted bucket
was used not only to remove dirt and contaminants but also to select
appropriately sized material. Although the slotted bucket may not be the most practical
or efficient way to remove dirt and small rock from excavated material, Wright
confirmed that it is possible to use a slotted bucket to create graded solid
rock and that Wright Brothers had done so in the past. Tr. II at 15, 31–32, 42.
Inspector Williams also testified that the slotted bucket is typically “used
for screening and sizing rocks.” Tr. I at 102–03.

II.             
LEGAL
PRINCIPLES

A.     Jurisdiction Under
the Mine Act

Mine Act jurisdiction applies to “[e]ach
coal or other mine, the products of which enter commerce, or the operations or
products of which affect commerce, and each operator of such mine, and every
miner in such mine.” 30 U.S.C. § 803. The term “coal or other mine” is defined
as:

(A) an area of
land from which minerals are extracted in nonliquid form or, if in liquid form,
are extracted with workers underground, (B) private ways and roads appurtenant
to such area, and (C) lands, excavations, underground passageways, shafts,
slopes, tunnels and workings, structures, facilities, equipment, machines,
tools, or other property including impoundments, retention dams, and tailings
ponds, on the surface or underground, used in, or to be used in, or resulting
from, the work of extracting such minerals from their natural deposits in
nonliquid form, or if in liquid form, with workers underground, or used in, or
to be used in, the milling of such minerals, or the work of preparing coal or
other minerals, and includes custom coal preparation facilities.

Id.
§
802(h)(1). Although the Act does not define “extracted” or “milling” with
respect to the term “minerals,” the Commission has held that the former means
“the separation of a mineral from its natural deposit in the earth,” and the
latter includes “processes by which minerals are made ready for use.” Drillex,
Inc. , 16 FMSHRC 2391, 2395 (Dec. 1994) (citations omitted) (holding that
separating rock from its deposit in the earth was mineral extraction and that the
crushing and separation of rock constituted milling).

Furthermore, the functional nature of the
operator’s activities is an important factor to consider when determining
whether an operation is a “coal or other mine” under the Act. Oliver M.
Elam, Jr. , 4 FMSHRC 5, 7 (1982). This functional analysis is a two-part
inquiry that asks: (1) whether the party engaged in activities normally
performed by a mine operator, and (2) whether the party performed these
activities to make the extracted material suitable for a particular use or to
meet market specifications. Id. at 8.

With
respect to the “affect[ing] commerce” requirement, the Act defines “commerce”
as “trade, traffic, commerce, transportation, or communication among the
several States, or between a place in a State and any place outside thereof, or
within the District of Columbia or a possession of the United States, or
between points in the same State but through a point outside thereof.” 30
U.S.C. § 802(b). The Commission reads this provision broadly and has held that
“any mining or milling that an entity engages in for its own use constitutes
‘commerce’ under . . . the Mine Act.” Alaska, Dep’t of Trans. , 36 FMSHRC
2642, 2645 (Oct. 2014) (discussing the Second Circuit’s decision in D.A.S.
Sand & Gravel, Inc. v. Chao , 386 F.3d 460 (2d Cir. 2004)).

An
exception to MSHA jurisdiction exists if an operation is classified as a
“borrow pit,” which is subject to the sole jurisdiction of the Occupational
Safety and Health Administration (“OSHA”) per an interagency agreement between MSHA
and OSHA. See MSHA-OSHA Interagency Agreement, 44 Fed. Reg. 22,827 (Apr.
17, 1979), amended by 48 Fed. Reg. 7521 (Feb. 22, 1983) (“Interagency
Agreement”). According to the Interagency Agreement, a borrow pit is defined
as:

[A]n area of land
where the overburden, consisting of unconsolidated rock, glacial debris, or
other earth material overlying bedrock is extracted from the surface. Extraction
occurs on a one-time only basis or only intermittently as need occurs, for use
as fill materials by the extracting party in the form in which it is extracted.
No milling is involved, except for the use of a scalping screen to remove large
rocks, wood and trash. The material is used by the extracting party more for
its bulk than its intrinsic qualities on land which is relatively near the
borrow pit.

Id. at 22,828. “Milling”
is further defined by the Interagency Agreement as “the art of treating the
crude crust of the earth to produce therefrom the primary consumer derivatives,”
and “the essential operation in all such processes is separation of one or more
valuable desired constituents of the crude from the undesired contaminants with
which it is associated.” Id . at 22,829. The Interagency Agreement
provides examples of milling processes, including “crushing” and “sizing.” Id.
“Crushing” is defined in part as “the process used to reduce the

size
of mined materials into smaller, relatively coarse particles,” and “sizing” is
defined as “the process of separating particles of mixed sizes into groups of
particles of all the same size, or into groups in which particles range between
maximum and minimum sizes.” Id. at 22,829–30.

When determining whether a facility
is a “mine” under the Act, “Congress clearly intended that any jurisdictional
doubts be resolved in favor of coverage by the Mine Act.” Watkins Eng’rs
& Constructors, 24 FMSHRC 669, 675–76 (July 2002) (citing S. Rep. No.
181, 95th Cong., 1st Sess. 14 (1977), reprinted in Senate Subcomm. on
Labor, Comm. on Human Res., 95th Cong., 2nd Sess., Legislative History of
the Federal Mine Safety and Health Act of 1977 at 602 (1978)). The Interagency
Agreement references this legislative history, and makes clear that questions
of jurisdiction between MSHA and OSHA should be resolved in favor of coverage
by the Mine Act. 44
Fed. Reg. at 22,828.

B.     Gravity

The Commission generally expresses gravity
as the degree of seriousness of the violation. Hubb Corp ., 22 FMSHRC
606, 609 (May 2000); Consolidation Coal Co ., 18 FMSHRC 1541, 1549 (Sept.
1996). The Commission has pointed out that the focus of the gravity inquiry “is
not necessarily on the reasonable likelihood of serious injury, which is the
focus of the [significant and substantial] inquiry, but rather on the effect of
the hazard if it occurs.” Consolidation ,

18 FMSHRC at 1550; cf. Harlan Cumberland Coal Co ., 12 FMSHRC 134, 140-41
(Jan. 1990) (ALJ) (explaining that some violations are serious notwithstanding
the likelihood of injury, such as a violation of an important safety standard,
a violation demonstrating recidivism or defiance by the operator, or a
violation that could compound the effects of other conditions).

C.     Negligence

Negligence is conduct that falls
below the standard of care established under the Mine Act. Under the
Secretary’s regulations, an operator is held to a high standard of care. 30
C.F.R. § 100.3(d). Operators must be wary of conditions and practices that could
cause injuries, and are required to take the necessary precautions to prevent
or correct those conditions or practices. Id . The Secretary defines
moderate negligence as having occurred in connection with a violation when
“[t]he operator knew or should have known of the violative condition or practice,
but there are mitigating circumstances.” Id. § 100.3(d), Table X. The
Commission generally assesses negligence by considering what actions a reasonably
prudent person familiar with the mining industry, the relevant facts, and the
protective purpose of the cited regulation would have taken under the
circumstances. Leeco, Inc ., 38 FMSHRC 1634, 1637 (July 2016); see
also Brody Mining, LLC , 37 FMSHRC 1687, 1702 (Aug. 2015) (explaining
that Commission ALJs “may evaluate negligence from the starting point of a
traditional negligence analysis” rather than adhering to the Secretary’s Part
100 definitions); accord Mach Mining, LLC v. Sec’y of Labor , 809 F.3d
1259, 1263-64 (D.C. Cir. 2016).

III.           
ANALYSIS

Respondent is contesting MSHA’s
jurisdiction as well as Inspector Williams’ negligence determinations with
respect to each of the citations and orders. Resp’t Br. at 8, 32. For the
reasons set forth below, I conclude that Respondent’s excavation site is a
“mine” under the Mine Act and is subject to MSHA jurisdiction. My negligence
determination for each citation and order is also set forth below.

A.     Whether Jones
Brothers Operates a “Mine” under the Mine Act

i.          
The
Excavation Site is a “Coal or Other Mine” Affecting Commerce

The Secretary argued that
Respondent’s excavation site is a “coal or other mine” under the Mine Act
because Respondent extracted, milled, and prepared graded solid rock—a mineral—and
that Respondent’s operations affected commerce. Sec’y Br. at 7–16. Respondent
failed to offer any argument that the excavation site was not a “coal or other
mine,” or that Respondent’s operations did not affect commerce, and instead,
solely chose to argue that it was operating a borrow pit under the Interagency
Agreement. Resp’t Br. at 7 (“[T]he Interagency Agreement establishes the issues
in this case.”).

I find that Respondent’s operation
falls within the definition of a “coal or other mine” under the Mine Act and
that Respondent’s operation affected commerce. 30 U.S.C. § 803. The Mine Act defines
“coal or other mine” as “an area of land from which minerals are extracted . .
. and . . . lands, excavations, . . . facilities, [and] equipment . . . used
in, or to be used in, the milling of such minerals, or the work of preparing .
. . other minerals.” 30 U.S.C.

§ 802(h)(1)(A), (C). Respondent separated minerals including limestone and
rocks from the earth through drilling, blasting, and excavating, which constitutes
mineral extraction and makes Respondent’s operation a “coal or other mine”
under the Act. 30 C.F.R. § 802(h)(1)(A); Drillex, Inc. , 16 FMSHRC at
2395.

Although Respondent’s extraction of
minerals is enough to make its operation a “coal or other mine” under the Act,
I also find that Respondent engaged in milling and preparation of the extracted
minerals. 30
C.F.R. § 802(h)(1)(C); Drillex, Inc. , 16 FMSHRC at 2395 (holding that the
operator “engaged in both mineral extraction and milling, either of which
independently qualifies its operation as a ‘mine’ within the meaning of the Act”).
Respondent engaged in mineral milling and preparation by using the hoe ram and
slotted bucket to size and remove dirt from the extracted material—processes by
which Respondent made the extracted material “ready for use” as graded solid
rock. See Drillex, Inc. , 16 FMSHRC at 2395; see also Marshall v.
Stoudt’s Ferry Preparation Co. , 602 F.2d 589, 592 (3d Cir. 1979)
(separation of gravel from dredged material was mineral preparation).

With respect to the requirement
that Respondent’s operation affect commerce, there is no dispute that Respondent
operated the excavation site to fulfill its obligation to produce graded solid
rock for the road repair. Because “any mining or milling that an entity engages
in for its own use constitutes ‘commerce’ under . . . the Mine Act,” and
because Respondent extracted, milled, and prepared graded solid rock to fulfill
a contractual obligation, Respondent’s operation affected commerce. See Alaska,
Dep’t of Trans. , 36 FMSHRC at 2645.

Further, under the Commission’s
functional Elam test, Oliver M. Elam, Jr. , 4 FMSHRC at 7, Mine Act
jurisdiction over Respondent is appropriate. With respect to the first prong,
Respondent engaged in activities
normally performed by a mine operator, such as: core drilling and sample testing;
the creation of roads, benches, and a highwall; removal of overburden; drilling
and blasting; excavating material using mechanized equipment; the processing of
the excavated material using the hoe ram and slotted bucket; and loading the
excavated material onto trucks for transportation. Regarding the second prong, Respondent
engaged in activities to make the extracted material suitable for a particular
use or to meet market specifications by blasting in a pattern, using the hoe
ram to break down large rocks, and using the slotted bucket to select clean
rock that was within the size requirements and phi angle dimensions for graded
solid rock.

Finally, although Respondent argued
that subjecting its operation to Mine Act jurisdiction “would represent a
drastic deviation from prior MSHA enforcement practices,” this argument is not
persuasive. Resp’t Br. at 8. The Commission has found Mine Act jurisdiction
over entities engaged in excavation for purposes of road construction,
maintenance, and repair. See Alaska, Dep’t of Trans. , 36 FMSHRC at
2642 (excavated material used to maintain road); see also Drillex, Inc. , 16 FMSHRC at 2396
(“extraction and processing of minerals were not merely incidental to road
construction”); Ammon Enter. , 30 FMSHRC 799 (July 2008) (ALJ) (excavated
material used for road construction); N.Y. State Dep’t of Transp., 2 FMSHRC 1749
(July 1980) (ALJ) (excavated material used for permanent repair of roads). Respondent’s
contention that MSHA has not treated similar operations as mines is irrelevant;
“allegations of selective enforcement cannot provide a basis for exemptions
from Mine Act coverage” because MSHA is statutorily required to exercise
jurisdiction over all mines. Kerr Enter., Inc. , 26 FMSHRC 953, 957 (Dec.
2004) (ALJ) (citing Air Prods. and Chems., Inc. , 15 FMSHRC 2428, 2435
n.2 (Dec. 1993) (concurring opinion)); 30 U.S.C. § 813(a) (“[T]he Secretary
shall make inspections of . . . each surface coal or other mine in its entirety
at least two times a year.”). Ultimately, Deference is owed to the Secretary’s
reasonable interpretation of the jurisdictional terms of the Mine Act. Alaska, Dep’t of
Trans. ,
36 FMSHRC at 2648 (citing City of Arlington v. FCC , 133 S. Ct. 1863,
1868–73 (2013)).

ii.          
The
Excavation Site Fails to Meet the “Borrow Pit” Criteria

Respondent’s primary contention is
that the excavation site is a borrow pit under the Interagency Agreement. Respondent
set forth a host of arguments in its post-hearing brief, including that: (1)
Respondent only removed unconsolidated rock, not bedrock; (2) Respondent’s
extraction activities were “only on a one-time basis or intermittently as need
occurred”; (3) the extracted material was “fill” that was used in the form in
which it was extracted and used more for its bulk than its intrinsic qualities;
(4) Respondent did not engage in milling; and (5) the extracted material was
used on land relatively near the site of extraction. Resp’t Br. at 8–25. The
Secretary argued that Respondent’s operation was not a borrow pit because: (1) Respondent
was not extracting overburden; and (2) Respondent was not extracting material
on a one-time or intermittent basis. Sec’y Br. at 16–18.

Respondent’s operation fails to meet the borrow
pit criteria set forth by the Interagency Agreement. I mportantly, the
Commission has treated the criteria for a borrow pit as necessary elements and not
as factors to be considered. Drillex, Inc. , 16 FMSHRC at 2391 (material
was used on land “relatively near” the extraction site, but operation failed to
meet other borrow pit requirements); Jermyn Supply Co., LLC , 39 FMSHRC
1472 (July 2017) (ALJ) (extraction operation was active only “sporadically,” but
the operator milled the material and the material was not being used for bulk
fill); State of Alaska, Dep’t of Trans. , 33 FMSHRC 1550 (June 2011) (ALJ)
(screening operation was active for three or four weeks per year, but the
operation was “sizing” aggregate and used specific aggregate for its “intrinsic
qualities”); Island Constr. Co, Inc. , 11 FMSHRC 2448 (Dec. 1989) (ALJ) (material
was used “in the form in which it [wa]s extracted as fill,” but operation
failed to meet other borrow pit requirements).

I find that extraction—which
occurred up to six days per week over a period of at least several months—was
not “on a one-time basis or only intermittently as need occurred,” as required
by the Interagency Agreement. Further, Respondent engaged in “milling” by “sizing”
and “crushing” through use of the calculated blasting pattern, hoe ram, and slotted
bucket. Under the Interagency Agreement, MSHA exercises jurisdiction where
there is milling, except for the use of a scalping screen—which Respondent did
not utilize—“to remove large rocks, wood and trash.” 44 Fed. Reg. at 22,828. Respondent
argued that it could not have engaged in “sizing” because TDOT’s graded solid
rock specification imposes no minimum size requirement. Resp’t Br. at 22. I
find that argument to be unpersuasive. The Standard Specifications plainly
state that graded
solid rock must have a “[m]aximum particle size of 3 feet in any direction” and
“[p]article size distribution in which at least 50% of the rock is uniformly
distributed between 1 foot and 3 feet in diameter, and no more than 10% is less
than 2 inches in diameter.” Ex. S-28 at 10–11 . Also, Wright’s testimony made clear that
graded solid rock should be composed of rocks between 3 feet and 6 inches in
diameter to achieve the optimal phi angle and to achieve a free-draining and
stable base for the roadway. Tr. II at 12. I find that in order to meet TDOT’s
graded solid rock specification, Respondent separated the extracted material into
groups in which particles ranged between maximum and minimum sizes—i.e. rocks
that were compliant with TDOT’s size requirement and rocks that were
noncompliant. Further,
the graded solid rock was not used solely as bulk, but was instead used more
for its intrinsic drainage properties—which were essential for the road repair
project Respondent was engaged in. The free-draining and free-flowing nature
of graded solid rock is why TDOT created the specification for that material. I
find that although Respondent used the graded solid rock in bulk to fill in the
roadway, it was selected and used more for its intrinsic properties than as
plain bulk fill. It is true that Respondent used the graded solid rock “on land
which [wa]s relatively near” the excavation site. However, Respondent’s failure
to meet the other borrow pit requirements is fatal to its argument.

The legislative history of the Mine
Act is unequivocal that jurisdictional doubts should be resolved in favor of
coverage by the Mine Act, and the Interagency Agreement makes this overtly
clear. 44
Fed. Reg. at 22,828 (mentioning “Congress’ intention that doubts be resolved in
favor of inclusion of a facility within the coverage of the Mine Act”). Whether a facility
is subject to MSHA or OSHA jurisdiction is significant because of the different
inspection practices between the agencies. Inspector Williams testified that MSHA
inspects open-pit quarries twice per year in unannounced visits. Tr. I at 124–25;
see also 30 U.S.C. § 813(a) (“Authorized representatives of the
Secretary . . . shall make frequent inspections and investigations in coal or
other mines each year.”). This is quite different than the circumstances under
which OSHA conducts inspections, often after an accident occurs or a complaint
is lodged. Cf. Donovan v. Dewey , 452 U.S. 594, 603–04 n.9 (1981) (contrasting
the “certainty and regularity” of the Mine Act’s inspection scheme with the discretionary
inspection scheme of the Occupational Safety and Health Act).

Commission precedent supports the
conclusion that Respondent’s operation is not a borrow pit. The Commission’s
decision in Drillex, Incorporated , 16 FMSHRC 2391 (Dec. 1994), contains
similar facts to the instant matter, and in that case, the Commission held that
the borrow pit exception did not apply. Drillex concerned a project
where the operator was contracted to perform “drilling, blasting, rock
excavation and crushing” of 20,000 cubic meters of stone “to be used as fill
for embankment and road base.” Id. at 2392. The operator excavated and processed
material approximately three times per week and reduced the material in size
using a hydraulic hammer. Id. at 2393, 2396. The Commission held that
the operator did not qualify for the borrow pit exception because: (1)
extraction did not occur on an intermittent basis; (2) the operator engaged in
“milling” by crushing the excavated material into smaller particles; and (3)
the material was sized for its intended use as fill, and was therefore not
solely “bulk” in nature. Id. at 2396. Here, Respondent similarly drilled,
blasted, and excavated material for the purpose of road construction, extracted
the material more than intermittently, and milled the material by sizing it
with the hoe ram and slotted bucket.

In State of Alaska, Department
of Transportation , the Commission held that the Interagency Agreement classifies
open pit mining of sand and gravel as an example of “unquestioned MSHA
authority under the Mine Act.” 36 FMSHRC at 2648 (citing 44 Fed. Reg. at
22,829). By separating excavated material by size and excluding oversized rock,
the Commission found that the operator was engaging in “sizing” and “milling,”
and therefore was not covered by the Interagency Agreement’s borrow pit
exception. Id. at 2649. In the instant matter, Respondent was required
to conform to TDOT’s size requirements for graded solid rock, and achieved
those requirements through the use of blasting, the hoe ram, and the slotted
bucket. Respondent “did more than ‘scalp’ away large rocks” and debris from the
blasted material by using the hoe ram and slotted bucket, and therefore State
of Alaska instructs that Respondent’s operation is not a borrow pit.

In its post-hearing brief,
Respondent cited to David Duquette Excavating , 37 FMSHRC 744 (Apr. 2015)
(ALJ) and Kerr Enterprises, Inc. , 26 FMSHRC 953 (Dec. 2004) (ALJ). [13]
Resp’t Br. at 10–11. In Duquette , the ALJ ruled that the earthen
material extraction operation was a borrow pit and exempt from Mine Act
jurisdiction because no milling was involved. Duquette , 37 FMSHRC at

  1. The extracted material in Duquette was stipulated to be “generally
    clean fill” from an embankment, and the operator used a single scalping screen
    only to remove large rocks, wood, and trash on an as-needed basis. Id. The
    extracted material was then loaded onto a dump truck and taken offsite, where the
    material was used in the form it was extracted as bulk fill. Id. In Kerr ,
    the operation involved the “full time continuous extraction” of earthen
    material from a pit over multiple years. 26 FMSHRC at 954, 957. The operator in
    Kerr then processed approximately 20 percent of the extracted material by
    using a scalping screen to remove debris. Id. at 954. The processed
    material was sold to more than fifty customers as far as twenty-five miles away
    from the extraction pit. Id. Although Respondent argues that its
    excavation site “is much closer to Duquette than Kerr ,” I find
    that neither case is a close comparison to the circumstances at Respondent’s operation.
    Respondent extracted minerals far more frequently than the “three times in two
    years” in Duquette , and less frequently than the “full time continuous
    extraction” over multiple years in Kerr . Additionally, unlike the
    extracted “clean fill” material in Duquette , the material from
    Respondent’s operation could not have been used in the form it was extracted
    because of the presence of dirt and mud seams. Finally, the material Respondent
    excavated was not used primarily as bulk fill but instead for its intrinsic
    value.

In sum, Respondent fails to meet all
of the elements of a borrow pit, as set forth in the Interagency Agreement. Because
Respondent’s excavation site is not a borrow pit and because Respondent extracted,
milled, and prepared minerals in an operation that affected commerce,
Respondent’s excavation site is a “mine” under the Act and is subject to MSHA
jurisdiction.

B.     Negligence
Assessment for Citations and Orders

Respondent indicated that besides the issue
of Mine Act jurisdiction, Respondent solely wished to contest the level of
negligence assessed for each citation and order. Tr. I at 118–19. The Secretary
argued that the negligence assessment issued by Inspector Williams for each
citation and order was correct and should be upheld. Sec’y Br. at 20–25. The
Respondent argued that the negligence assessment issued by Inspector Williams
should be disregarded because Inspector Williams relied on the statement of one
of Respondent’s employees regarding management’s knowledge of the potential for
Mine Act jurisdiction over the excavation site, and the employee’s statement
was unreliable hearsay. Resp’t Br. at 32–34. As I have noted above, I discount
the alleged statement made to Inspector Williams due to reliability concerns. The
following section contains an analysis of the level of negligence for each
violation.

i.          
Citation
No. 8817591

Citation No. 8817591 has a proposed penalty
of $100.00 and was assessed as involving high negligence. Ex. S-4. Citation No.
8817591 alleges a violation of 30 C.F.R. § 56.1000, which requires the operator
of any mine to “notify the nearest MSHA Metal and Nonmetal Mine Safety and
Health district office before starting operations, of the approximate or actual
date mine operation will commence.” 30 C.F.R. § 56.1000. The narrative portion
of the citation is as follows:

The operator of
the mine, Jones Bros., Inc., did not notify the local Mine Safety and Health
Administration office before starting operations, of the approximate or actual
date mine operations commenced. The notification shall include the mine name,
location, company name, mailing address, person in charge, and whether the
operation will be continuous or intermittent. Drilling, blasting, and sizing of
the rock material was occurring in the open pit mine. The rock material was
being sold to the State of Tennessee, on a nearby project. This action was
affecting interstate commerce.

Ex.
S-4 at 1. Respondent terminated the citation by “notif[ying] MSHA in the
Southeast District Office of their work in the open pit mine.” Id. at 2.

Inspector
Williams testified that he assessed Citation No. 8817591 as involving high
negligence because Respondent was previously a contractor at other mines and
was therefore familiar with MSHA’s regulations. Tr. I at 120–21. I agree with
Inspector Williams’ negligence assessment. I find the gravity of this violation
to be serious because without notification of the commencement of operations,
MSHA has no reliable way to ensure the health and safety of miners through inspections
and enforcement of the Act.

ii.          
Citation
No. 8817592

Citation No. 8817592 has a proposed
penalty of $100.00 and was assessed as involving moderate negligence. Ex. S-17.
Citation No. 8817592 alleges a violation of 30 C.F.R.

§ 56.4402, which provides that “[s]mall quantities of flammable liquids drawn
from storage shall be kept in safety cans labeled to indicate the contents.” 30
C.F.R. § 56.4402. The narrative portion of the citation is as follows:

A red Eagle brand
5 gallon safety can was filled almost full with an unknown liquid. The portable
temporary container was not labeled nor with any markings to indicate its
contents. The can had been in the present condition for approximately a week,
and was located on the Mack fuel truck #13606. This created a hazard to an
unbeknownst miner being exposed to flammable characteristics and physical
conditions without HazCom warnings.

Ex.
S-17 at 1. Respondent terminated the citation by labeling “the safety can . . .
to identify the contents, ‘GAS.’” Id . Inspector Williams took
photographs of the safety can before and after it was labeled. Ex. S-3 at 16,
19; Ex. S-19.

Inspector Williams testified that he
assessed Citation No. 8817592 as involving moderate negligence because
Inspector Williams “was told[] management . . . did not know that the can
needed to be labelled,” and Inspector Williams credited that statement. Tr. I
at 141. I agree with Inspector Williams’ negligence assessment. I find the
gravity of this violation to be reasonably serious because the risk that a
miner might mistake the contents of the safety can for a different liquid is
somewhat mitigated by the red color and warnings on the can. Ex. S-3 at 16, 19.

iii.          
Citation
No. 8817593

Citation No. 8817593 has a proposed
penalty of $243.00 and was assessed as involving moderate negligence. Ex. S-20.
Citation No. 8817593 alleges a violation of 30 C.F.R.

§ 56.14132(a), which provides that “[m]anually-operated horns or other audible
warning devices provided on self-propelled mobile equipment as a safety feature
shall be maintained in functional condition.” 30 C.F.R. § 56.14132(a). The
narrative portion of the citation is as follows:

The Mack dump
truck #16334 did not have a maintained back up alarm while being operated on
the mine site. The driver has an obstructed view to the rear and could not see other
miners who were on foot in the common area of the mine, i.e. restrooms, parking
lot and ingress/egress roadway. This created a hazard to any miner being backed
over when no advance warning was heard of any sudden movement. The heavy equipment
could cause crushing injuries, leading up to death, being sustained if struck
with the truck.

Ex.
S-20 at 1. Respondent terminated the citation by replacing “the backup alarm .
. . with a new unit.” Id. at 2.

Inspector Williams testified that he
assessed Citation No. 8817593 as involving moderate negligence because Respondent
was not aware of the hazardous condition, and because Inspector Williams
thought that the truck had a back-up alarm, “but it just wasn’t working.” Tr. I
at 145. I agree with Inspector Williams’ negligence assessment. I find the
gravity of this violation to be reasonably serious because Respondent had less
than ten employees working at the project, and few employees were outside of
equipment while trucks were being loaded—thereby somewhat mitigating the risk
of a vehicle strike.

iv.          
Citation
No. 8817594

Citation No. 8817594 has a proposed penalty
of $243.00 and was assessed as involving moderate negligence. Ex. S-22. Citation
No. 8817594 alleges a violation of 30 C.F.R.

§ 56.14104(b)(2), which requires the use of “a stand-off inflation device which
permits persons to stand outside of the potential trajectory of wheel
components” during tire inflation. 30 C.F.R. § 56.14104(b)(2). The narrative
portion of the citation is as follows:

The mine had
access to various air compressors on the site. These units were being used to
inflate tires on the heavy equipment, as needed. The mine operator did not have
a stand-off inflation device to limit a miner's exposure to exploding tires. Injuries
of lacerations, contusions, fractures, impalement and/or leading up to death
could be sustained from flying debris when near the potential trajectory of
wheel components.

Ex.
S-22 at 1. Respondent terminated the citation by “purchas[ing] a stand-off
devise [sic] to be used on the mine site.” Id. at 2. Inspector Williams
took photographs of an air compressor and the stand-off device. Ex. S-3 at 17,
18, 25; Ex. S-24.

Inspector Williams testified that he
assessed Citation No. 8817594 as involving moderate negligence because “management
was not aware that they needed a stand-off device,” and Inspector Williams
credited that statement by management. Tr. I at 147. I agree with Inspector
Williams’ negligence assessment. I find the gravity of this violation to be
serious because of the risk of fatal injury, and the fact that there were
multiple air-compressors on site, as well as multiple vehicles and pieces of equipment
that used rubber tires.

v.          
Order
No. 8817595

Order No. 8817595 has a proposed penalty of
$1,842.00 and was assessed as involving high negligence. Ex. S-9. Order No.
8817595 alleges a violation of 30 C.F.R. § 46.5(a), which requires that each
new miner receive no less than 24 hours of new miner training. 30 C.F.R.

§ 46.5(a). The narrative portion of the citation is as follows:

The mine operator
had failed to train six (6) of their employees. They had not received the
MSHA-required 24 Hour New Miner training within the 90 days after beginning
work at the mine. These six employees could not provide documentation of any
previous mining experience. The mine operator was aware of the Part 46 training
requirements. The mine operator must withdraw the . . . miners from the mine
until they receive the required 24 hours of training.

Ex.
S-9 at 1. Respondent terminated the order by delivering “24 hours of New Miner
training to the 6 miners” on April 7, 2016. Id. at 3.

Inspector Williams testified that he
assessed Order No. 8817595 as involving high negligence because Respondent was
previously a contractor at other mines and was therefore familiar with MSHA’s
regulations. Tr. I at 130–31. I agree with Inspector Williams’ negligence
assessment. I find the gravity of this violation to be serious because an
untrained miner is a hazard to himself and other miners.

vi.          
Order
No. 8817596

Order No. 8817596 has a proposed penalty of
$112.00 and was assessed as involving moderate negligence. Ex. S-11. Order No.
8817596 alleges a violation of 30 C.F.R.

§ 46.8(a)(1), which requires that each miner be provided with “no less than 8
hours of annual refresher training” within “12 months after the miner begins
work at the mine.” 30 C.F.R.

§ 46.8(a)(1). The narrative portion of the citation is as follows:

Kevin Williams,
excavator operator, had not received Annual Refresher Training within the last
twelve (12) months. Refresher training was last given to this miner, February
2015. [T]he mine operator was aware of the training requirements. The operator
is hereby ordered to withdraw Kevin Williams from the mine until he has
received the 8 hours of required training.

Ex.
S-11 at 1. Respondent terminated the order by delivering “8 hours of Annual
Refresher Training to the miner” on April 8, 2016. Id. at 2.

Inspector Williams testified that he
assessed Order No. 8817596 as involving moderate negligence because Kevin
Williams “was somewhat trained . . . and he was an experienced miner.” Tr. I at

  1. Therefore, Inspector Williams credited Respondent “for at least having him
    trained once a long time ago.” Id. I agree with Inspector Williams’
    negligence assessment. I find the gravity of this violation to be reasonably
    serious because the risk of an untrained miner was somewhat mitigated by Kevin
    Williams having worked for Respondent for many years and having some training
    as a miner.

vii.          
Citation
No. 8817597

Citation No. 8817597 has a proposed
penalty of $100.00 and was assessed as involving high negligence. Ex. S-6. Citation
No. 8817597 alleges a violation of 30 C.F.R. § 41.11, which requires the mine
operator to notify MSHA of the operator’s legal identity within 30 days of
commencing operations at the mine. 30 C.F.R. § 41.11. The narrative portion of
the citation is as follows:

The operator of
the mine failed to notify the appropriate district manager of the Mine Safety
and Health Administration in the Southeast district in which the mine is
located of the legal identity of the operator. This mine had been in production
since 28 August 2015, with numerous miners performing drilling, blasting, and
sizing of rock material.

Ex.
S-6 at 1. Respondent terminated the citation by filing “the required Legal Identity
Report (2000-7 form) [sic] with MSHA” on April 18, 2016. Id. at 2.

Inspector Williams testified that he
assessed Citation No. 8817597 as involving high negligence because Respondent
was previously a contractor at other mines and was therefore familiar with
MSHA’s regulations. Tr. I at 126. I agree with Inspector Williams’ negligence
assessment. I find the gravity of this violation to be moderate because Respondent’s
failure to submit the legal identity report was a recordkeeping violation.

viii.          
Citation
No. 8817598

Citation No. 8817598 has a proposed
penalty of $100.00 and was assessed as involving moderate negligence. Ex. S-13.
Citation No. 8817598 alleges a violation of 30 C.F.R.

§ 50.30(a), which requires mine operators to complete and submit a MSHA Form
7000-2 within 15 days after the end of each calendar quarter. 30 C.F.R. §
50.30(a). The narrative portion of the citation states that “[a]n MSHA #7000-2
(Quarterly Employment Report) for the 3rd Quarter 2015 (July, August,
September) was not completed nor mailed to MSHA’s Health and Safety Analysis
Center prior to the required 15 days after the end of each calendar quarter,
October 15, 2015.” Ex. S-13 at 1. Respondent terminated the citation by filing
“the Q3 Mine Employment and Production Report.” Id. at 2.

Inspector Williams testified that he assessed
Citation No. 8817598 as involving moderate negligence because Respondent
previously submitted information while serving as a contractor at other mines
and was therefore familiar with the reporting requirement. Tr. I at 135. I
agree with Inspector Williams’ negligence assessment. I find the gravity of
this violation to be moderate because Respondent’s failure to submit the
quarterly employment form was a recordkeeping violation.

ix.          
Citation
No. 8817599

Citation No. 8817599 has a proposed penalty
of $100.00 and was assessed as involving moderate negligence. Ex. S-15. Citation
No. 8817599 alleges a violation of 30 C.F.R.

§ 50.30(a), which requires mine operators to complete and submit a MSHA Form
7000-2 within 15 days after the end of each calendar quarter. 30 C.F.R. §
50.30(a). The narrative portion of the citation states that “[a]n MSHA #7000-2
(Quarterly Employment Report) for the 4th Quarter 2015 (October, November,
December) was not completed nor mailed to MSHA's Health and Safety Analysis Center
prior to the required 15 days after the end of each calendar quarter, January
15, 2016.” Ex. S-15 at 1. Respondent terminated the citation by filing “the Q4
Mine Employment and Production Report.” Id. at 2.

Inspector Williams testified that he
assessed Citation No. 8817599 as involving moderate negligence for the same
reason as the violation in Citation No. 8817598—because Respondent previously
submitted information while serving as a contractor and was therefore familiar
with the reporting requirement. Tr. I at 135. I agree with Inspector Williams’
negligence assessment. I find the gravity of this violation to be moderate
because Respondent’s failure to submit the quarterly employment form was a
recordkeeping violation.

IV.           
PENALTY

Section 110(i) of
the Mine Act grants the Commission the authority to assess all civil penalties
provided for by the Act. Mize Granite Quarries, Inc. , 34 FMSHRC 1760,
1763 (Aug. 2012) (citing 30 U.S.C. § 820(i)). In determining penalty
amounts, Section 110(i) directs the Commission to consider:

[T]he operator’s
history of previous violations, the appropriateness of such penalty to the size
of the business of the operator charged, whether the operator was negligent,
the effect on the operator’s ability to continue in business, the gravity of
the violation, and the demonstrated good faith of the person charged in
attempting to achieve rapid compliance after notification of a violation.

30
U.S.C. § 820(i).

The
Commission and its ALJs are not bound by the penalties proposed by the
Secretary, nor are they governed by MSHA’s Part 100 regulations, although ALJ
penalty assessments “must reflect proper consideration” of the Section 110(i)
criteria. Am. Coal Co. , 38 FMSHRC 1987, 1992-93 (Aug. 2016) (citations
omitted). In addition to considering the Section 110(i) criteria, the judge
must provide a factual basis upon which the Commission can perform its review
function. See Martin Co. Coal Corp. , 28 FMSHRC 247, 265-66 (May 2006)
(citing Sellersburg , 5 FMSHRC 287, 292-93 (Mar. 1983)). My analysis of
the Section 110(i) factors is set forth below.

A.     Violation History;
Size of Operator; Ability to Continue in Business

Respondent previously
received two section 104(a) citations while serving as a contractor, and paid
the $343.00 proposed penalty. Ex. S-8 at 2. Additionally, Anthony Williams
testified that he supervised seven of Respondent’s employees at the road repair
project. Tr. I at 247. I find that Respondent is a small-sized operator with a
minimal history of violations. Additionally, there is no evidence that the
proposed penalty would directly impact Respondent’s ability to continue in
business, and Respondent did not raise such a claim. “The Commission has held
that ‘[i]n the absence of proof that the imposition of authorized penalties
would adversely affect [an operator’s] ability to continue in business, it is
presumed that no such adverse [e]ffect would occur.”’ John Richards Constr. ,
39 FMSHRC 959, 965 (May 2017) (quoting Sellersburg Co. , 5 FMSHRC 287,
294 (Mar. 1983)).

B.     Negligence and
Gravity

My analysis of the
negligence and gravity of the violations is set forth in section III.B.i–ix.

C.     Good Faith

Good faith is
reflected in the actions taken to abate the violations and in the testimony
regarding Respondent’s abatement efforts, as described in section III.B.i–ix.

D.     Conclusion

After considering
the six statutory penalty criteria, I assess a penalty of $2,940.00 for the
violation at issue in this case.

ORDER

Respondent is
hereby ORDERED to pay a total penalty of $2,940.00 for the violation at
issue in this docket within thirty (30) days of the date of this Decision and
Order. [14]

/s/ Priscilla M.
Rae

Priscilla M. Rae

Administrative
Law Judge

Distribution:

Willow
Eden Fort, Attorney, Office of the Solicitor, 618 Church Street, Suite 230
Nashville, TN 37219 ( [email protected] )

Douglas
R. Pierce, Esq., KING & BALLOW, 315 Union Street, Suite 1100, Nashville, TN
37201 ( [email protected] )  

Michael
D. Oesterle, Esq., KING & BALLOW, 315 Union Street, Suite 1100, Nashville,
TN 37201 ( [email protected] )

[1] In this decision,
“Tr. I” refers to the transcript from the first day of the hearing, and “Tr.
II” refers to the transcript from the second day of the hearing. The
Secretary’s exhibits are numbered Ex. S-1 to S-31. The Respondent’s exhibits
are numbered Ex. R-2 to R-8. The Secretary’s post-hearing brief is abbreviated
as “Sec’y Br.,” and the Respondent’s post-hearing brief is abbreviated as “Resp’t
Br.” The parties did not submit joint stipulations.

[2] TDOT employee Ken
Flynn testified that the “slide” damage to State Route 141 involved the roadway
“slipping and falling down.” Tr. I at 26. Respondent’s witness Stephen Wright
testified that the steep, mountainous terrain of the area can cause water to
seep out of the ground and undermine roadway foundations. Tr. II at 11–12.

[3] Core drilling
allowed Respondent to take a subsurface rock sample—without drilling, blasting,
and excavating—by using a hollow drill bit. Tr. I at 98–99.

[4] The slotted
excavator bucket, also referred to as a “shaker bucket,” had twenty-four slots
that each measured eleven inches long and seven inches wide. Tr. I at 363–64.

[5] Danny Williams
has been an MSHA inspector since July 15, 2012, and was trained at the Mine
Safety and Health Academy in Beckley, West Virginia. Tr. I at 71, 78. Williams previously
worked as a safety specialist at an underground zinc mine in Gordonsville,
Tennessee, where he trained miners, responded to accidents, performed safety
audits, served as a liaison with local first responders, and handled explosives.
Tr. I at 72–73. Williams was also previously employed as a law enforcement officer.
Tr. I at 76–77.

[6] Although I find
Inspector Williams’ testimony to be credible, I discount the miner’s alleged
statement during the inspection. The statement by the employee was made in
passing and without sufficient time for Inspector Williams to corroborate the
statement or test the reliability of the employee who made the statement. Therefore,
although the Commission’s procedural rules permit hearsay evidence, the alleged
statement to Inspector Williams does not have the necessary indicia of reliability,
and I do not consider it when determining Respondent’s level of negligence. 29
C.F.R. § 2700.63.

[7] Hinson has been
employed by Respondent since 1990 and served as a project manager at the excavation
site. Tr. I at 212, 213. Hinson was only at the job site “randomly,” and was
responsible for procuring materials and subcontractors. Tr. I at 213.

[8] Anthony Williams
is employed as a superintendent for Respondent, and has been employed by
Respondent for approximately 27 years. Tr. I at 246. Anthony Williams served as
Respondent’s foreman at the excavation site and was Respondent’s highest
ranking employee assigned to the road repair project. Tr. I at 247.

[9] Kevin Williams has
been employed by Respondent for approximately 16 years, including at Respondent’s
road repair project. Tr. I at 301.

[10] Givens was a
bulldozer operator for Respondent on the State Route 141 repair project and has
been involved with the road building business since 1996. Tr. I at 314–16.

[11] Wright is the president and
CEO of Wright Brothers Construction Company (“Wright Brothers”), a company that
is considered a competitor to Respondent and headquartered in Charleston,
Tennessee. Tr. II at 5, 7. Wright has been working for Wright Brothers since
1978, and Wright Brothers engages in highway heavy civil contracting, earth
work, bridge and road construction, paving, concrete, and other similar
activities. Tr. II at 6–7.

[12] Anthony Williams
and Jimmy Givens are either wrong in their characterization of the material
Respondent used as graded solid rock on the State Route 141 project, or
Respondent knowingly failed to meet the requirements for graded solid rock.

[13] Respondent failed
to properly cite or refer to these cases as non-precedential ALJ decisions, and
not Commission precedent.

[14] Payment should be
sent to: Mine Safety and Health Administration, U.S. Department of Labor,
Payment Office, P.O. Box 790390, St. Louis, MO 63179-0390.

Get today's answer for your situation

You just read what one judge decided for one employer in 2021, and it binds only those parties. Ezel checks the current MSHA standards and Commission precedent and answers your specific situation, with citations.

Opens in Ezel Pro. Every answer cites the authority it relies on.