Oak Grove Resources LLC (Commission decision, February 7, 2011)

Oak Grove Resources LLC (FMSHRC SE 2011-16): Reopening denied pending fuller explanation

Decision type
Commission decision
Docket
SE 2011-16
Decided
February 7, 2011
Outcome
Procedural
Precedential status
Citable Commission precedent
Checked against source
2026-08-08

Apply this precedent to your situation

This is citable Commission precedent from 2011, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.

Currency note: this decision dates from 2011
The MSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Decision of the Commission
This is a decision of the Federal Mine Safety and Health Review Commission, the highest level of agency review, citable as Commission precedent. It may have been appealed to a U.S. Court of Appeals after issuance under 30 U.S.C. § 816; check subsequent history before relying on it. The full text below is from the official FMSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official FMSHRC release. The full text is the agency's own release.
Read the official release (fmshrc.gov)

Plain-English summary

Oak Grove sought to reopen an assessment of nearly $125,000 covering 80 citations and orders, intending to contest 27 penalties totaling nearly $111,000. It blamed a miscommunication between counsel and its safety director and said a contest form went to MSHA's payment address, while the Secretary disputed the payment details and opposed reopening. The Commission noted that Oak Grove had recently used almost the same explanation in other cases and had not timely supplied the detailed account requested there. It denied reopening without prejudice and required any renewed request within 30 days to fully explain both the missed deadline and the corrective procedures adopted.

Decision snapshot

  • Governing provision: 30 U.S.C. § 815(a)
  • Outcome: The reopening request was denied without prejudice, with a detailed renewed request allowed within 30 days.
  • Key point: Repeated reliance on the same internal communication failure requires a detailed explanation and concrete procedural corrections before reopening is justified.

Full text (FMSHRC public release)

Federal Mine Safety and Health Review Commission

FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION

601 NEW JERSEY AVENUE, NW

SUITE 9500

WASHINGTON, DC 20001

February 7, 2011

SECRETARY OF LABOR,

MINE SAFETY AND HEALTH

ADMINISTRATION (MSHA)

v.

OAK GROVE RESOURCES LLC

:

:

:

:

:

:

:

Docket No. SE 2011-16

A.C. No.02-00851-221338

BEFORE: Jordan, Chairman; Duffy, Young, Cohen, and Nakamura, Commissioners

ORDER

BY THE COMMISSION:

This matter arises under the Federal Mine Safety and Health Act of 1977, 30 U.S.C.
§ 801 et seq. (2006) (“Mine Act”). On October 5, 2010, the Commission received from Oak Grove Resources LLC (“Oak Grove”) a motion made by counsel to reopen a penalty assessment that had become a final order of the Commission pursuant to section 105(a) of the Mine Act, 30 U.S.C. § 815(a).

Under section 105(a) of the Mine Act, an operator who wishes to contest a proposed penalty must notify the Secretary of Labor no later than 30 days after receiving the proposed penalty assessment. If the operator fails to notify the Secretary, the proposed penalty assessment is deemed a final order of the Commission. 30 U.S.C. § 815(a).

We have held, however, that in appropriate circumstances we possess jurisdiction to reopen uncontested assessments that have become final Commission orders under section 105(a). Jim Walter Res., Inc., 15 FMSHRC 782, 786-89 (May 1993) (“JWR”). In evaluating requests to reopen final section 105(a) orders, the Commission has found guidance in Rule 60(b) of the Federal Rules of Civil Procedure under which, for example, a party could be entitled to relief from a final order of the Commission on the basis of mistake, inadvertence, or excusable neglect. See 29 C.F.R. § 2700.1(b) (“the Commission and its Judges shall be guided so far as practicable by the Federal Rules of Civil Procedure”); JWR, 15 FMSHRC at 787. We have also observed that default is a harsh remedy and that, if the defaulting party can make a showing of good cause for a failure to timely respond, the case may be reopened and appropriate proceedings on the merits permitted. See Coal Prep. Servs., Inc., 17 FMSHRC 1529, 1530 (Sept. 1995).

On June 3, 2010, the Department of Labor’s Mine Safety and Health Administration (“MSHA”) issued Penalty Assessment No. 000221338 to Oak Grove, proposing penalties of nearly $125,000 for 80 citations and orders issued to the operator the previous April. In its motion to reopen the assessment so that it can contest 27 of the penalties proposed for a total of nearly $111,000,

Oak Grove states that it failed to timely file a contest due to a miscommunication between its counsel and its safety director. Its safety director further states that the contest form was submitted in July to MSHA with Oak Grove’s payment of the uncontested penalties, with both sent to MSHA’s address for penalty payments, not to the separate address for contests.

The Secretary opposes the reopening of the proposed assessment on the ground that inadequate or unreliable internal procedures do not constitute an adequate excuse for reopening. She argues that the large amounts of the penalties involved indicate that the operator’s internal procedures were particularly inadequate. She also states that payment for the uncontested penalties was by check dated October 7, 2010, that there was no contest form attached to the payment, and that the payment did not designate which penalties were being paid.

Since the time Oak Grove filed its motion and the Secretary her response, the Commission issued an order denying two other Oak Grove motions to reopen, including one which contained almost exactly the same excuse regarding a miscommunication between the safety director and counsel. We held that such an explanation provided insufficient grounds to reopen, and stated that if Oak Grove wished to renew its request to reopen with a detailed explanation of the circumstances, it should file its renewed or amended request within 30 days. Oak Grove Res., LLC, 32 FMSHRC 1253, 1254-55 (Oct. 2010).

The operator did not do so, but instead waited nearly three months, and then filed a renewed motion to reopen accompanied by a motion to permit late filing. In a separate order, the Commission is denying the motion to permit late filing and thus will not consider the renewed motion in that case.

We are also hereby denying, without prejudice, the motion to reopen the assessment in this case. We have held that an inadequate or unreliable internal processing system does not constitute inadvertence, mistake or excusable neglect so as to justify the reopening of an assessment which has become final under section 105(c) of the Mine Act. Pinnacle Mining Co., 30 FMSHRC 1061, 1062 (Dec. 2008); Pinnacle Mining Co., 30 FMSHRC 1066, 1067 (Dec. 2008); Highland Mining Co., 31 FMSHRC 1313, 1315 (Nov. 2009): Double Bonus Coal Co., 32 FMSHRC 1155, 1156 (Sept. 2010); Elk Run Coal Co., 32 FMSHRC 1587, 1588 (Dec. 2010). Should Oak Grove renew its request to reopen this assessment, it must do so within 30 days, and fully explain the circumstances in its failure to timely contest the proposed assessment. It must also address what it has done to ensure that it responds to proposed assessments in a timely manner, in order to avoid a repeat of the mistakes it outlined in its motion.


Mary Lu Jordan, Chairman


Michael F. Duffy, Commissioner


Michael G. Young, Commissioner


Robert F. Cohen, Jr., Commissioner


Patrick K. Nakamura, Commissioner

Distribution:

R. Henry Moore, Esq.

Jackson Kelly, PLLC

Three Gateway Center

Suite 1340

401 Liberty Avenue

Pittsburgh, PA 15222

W. Christian Schumann, Esq.

Office of the Solicitor

U.S. Department of Labor

1100 Wilson Blvd., Room 2220

Arlington, VA 22209-2296

Melanie Garris

Office of Civil Penalty Compliance

MSHA

U.S. Dept. Of Labor

1100 Wilson Blvd., 25th Floor

Arlington, VA 22209-3939

Chief Administrative Law Judge Robert J. Lesnick

Federal Mine Safety & Health Review Commission

601 New Jersey Avenue, N.W., Suite 9500

Washington, D.C. 20001-2021

Does this precedent still control your case?

Ezel checks whether it still stands, including any court review since, and applies it to your situation with citations.

Opens in Ezel Pro.

  • Checks the law as it stands today, not only this page
  • Cites every source it relies on, so you can verify it
  • Chat, drafting and research in one workspace