FMSHRC Commission decision Docket SE 2011-146-M Decided June 9, 2011 Remanded

Robert Coleman, Employed by Carmeuse Lime and Stone

Robert Coleman, Employed by Carmeuse Lime and Stone (FMSHRC SE 2011-146-M): Penalty case remanded because Coleman lacked notice

Apply this precedent to your situation

This is citable Commission precedent from 2011, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.

Currency note: this decision dates from 2011
The MSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Decision of the Commission
This is a decision of the Federal Mine Safety and Health Review Commission, the highest level of agency review, citable as Commission precedent. It may have been appealed to a U.S. Court of Appeals after issuance under 30 U.S.C. § 816; check subsequent history before relying on it. The full text below is from the official FMSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official FMSHRC release. The full text is the agency's own release.
Read the official release (fmshrc.gov)

Plain-English summary

MSHA proposed an individual civil penalty against Robert Coleman under section 110(c) of the Mine Act. The assessment was delivered to the mine and signed for by another employee, but Coleman said he never received it and first learned of the penalty through a delinquency notice. The Commission held that delivery had not provided Coleman the actual notice required by its procedural rules. The assessment therefore had not become a final Commission order. The Commission remanded the matter for assignment to a judge and proceedings on the penalty.

Decision snapshot

  • Governing provisions: 30 U.S.C. §§ 815(a) and 820(c); 29 C.F.R. §§ 2700.25, 2700.26, and 2700.27
  • Outcome: The assessment was held not final, and the penalty case was remanded for proceedings before a judge.
  • Key point: An individual penalty assessment does not become final when delivery to the mine fails to give the charged person actual notice.

Full text (FMSHRC public release)

Federal Mine Safety and Health Review Commission

FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION

601 NEW JERSEY AVENUE, NW

SUITE 9500

WASHINGTON, DC 20001

June 9, 2011

SECRETARY OF LABOR,

MINE SAFETY AND HEALTH

ADMINISTRATION (MSHA)

v.

ROBERT COLEMAN, Employed by

CARMEUSE LIME AND STONE

:

:

:

:

:

:

:

:

:

Docket No. SE 2011-146-M

A.C. No. 09-01038-226939 A

BEFORE: Jordan, Chairman; Duffy, Young, Cohen, and Nakamura, Commissioners

ORDER

BY THE COMMISSION:

This matter arises under the Federal Mine Safety and Health Act of 1977, 30 U.S.C.
§ 801 et seq. (2006) (“Mine Act”). On December 6, 2010, the Commission received from Robert Coleman (“Coleman”) a motion requesting that the Commission reopen a penalty
assessment against Coleman under section 110(c) of the Mine Act, 30 U.S.C. § 820(c), that had become a final order of the Commission pursuant to section 105(a) of the Mine Act, 30 U.S.C. § 815(a). On January 4, 2011, the Commission received a letter from the Secretary of
Labor (“Secretary”) stating that she did not oppose the motion to reopen.

Under the Commission’s Procedural Rules, an individual charged under section 110(c)
has 30 days following receipt of the proposed penalty assessment within which to notify the
Secretary that he or she wishes to contest the penalty. 29 C.F.R. § 2700.26. If the individual
fails to notify the Secretary, the proposed penalty assessment is deemed a final order of the
Commission. 29 C.F.R. § 2700.27.

Order No. 6505780 was issued by the Mine Safety and Health Administration (“MSHA”)
on June 16, 2009, to Carmeuse Lime and Stone (“Carmeuse”). On August 2, 2010, the MSHA
issued Proposed Assessment No. 00226939A to Coleman, alleging that he was personally liable,
pursuant to section 110(c) of the Mine Act, for the violation alleged in Order No. 6505780. The
proposed assessment was apparently delivered to the Marble Hill Mine on August 5, 2010.
According to Coleman, it was signed for by a “W. Weaver,” whom he identifies as William
Weaver, an hourly employee of Carmeuse. William Weaver states in an affidavit that he has no
recollection of receiving the proposed assessment. Weaver further states, that even if he did
receive the assessment, he does not recall “personally hand deliver[ing] it to Robert Coleman.”

In his motion to reopen, Coleman asserts that he did not timely contest the proposed
penalty because he did not receive the proposed assessment.

Coleman states that he first learned
that a penalty had been issued to him for the order on November 1, 2010, after receiving a
delinquency notice from MSHA. Coleman requests that the proceeding be reopened so that the
penalty case can move forward.

Commission Procedural Rule 25 provides, in pertinent part, that the Secretary “shall
notify . . . any other person against whom a penalty is proposed of the violation alleged.”

29 C.F.R. § 2700.25. Accordingly, a proposed assessment under section 110(c) does not become a final order within 30 days, if the manner in which the proposed penalty was delivered
to the individual does not provide him or her with actual notice of the proposed assessment. See Stech, employed by Eighty-Four Mining Co., 27 FMSHRC 891 (Dec. 2005) (finding that a
proposed assessment does not become a final order when it was mistakenly delivered to a
separate firm in counsel’s office building, and addressed to the respondent himself rather than “in care of” his counsel). In Stech, the Commission advised that “[i]f the Secretary had sent the
penalty proposal at issue here to [the respondent] at his home address or ‘in care of’ counsel at
the counsel’s address, the confusion would presumably have been avoided.” 27 FMSHRC at 892 n.1.

We conclude that Coleman was not provided with notice, as required by Procedural Rule 25. Accordingly, Proposed Assessment No. 00226939A is not a final order of the
Commission. We remand this matter to the Chief Administrative Law Judge for assignment to a
judge. This case shall proceed pursuant to the Mine Act and the Commission’s Procedural
Rules, 29 C.F.R. Part 2700.

______

Mary Lu Jordan, Chairman

______

Michael F. Duffy, Commissioner

______

Michael G. Young, Commissioner

______

Robert F. Cohen, Jr., Commissioner

______

Patrick K. Nakamura, Commissioner

Distribution:

R. Henry Moore, Esq.

Jackson Kelly, PLLC

Three Gateway Center, Suite 1340

401 Liberty Avenue

Pittsburgh, PA 15222

W. Christian Schumann, Esq.

Office of the Solicitor

U.S. Department of Labor

1100 Wilson Blvd., Room 2220

Arlington, VA 22209-2296

Melanie Garris

Office of Civil Penalty Compliance

MSHA

U.S. Dept. Of Labor

1100 Wilson Blvd., 25th Floor

Arlington, VA 22209-3939

Chief Administrative Law Judge Robert J. Lesnick

Federal Mine Safety & Health Review Commission

601 New Jersey Avenue, N. W., Suite 9500

Washington, D.C. 20001-2021

Get today's answer for your situation

You just read Commission precedent from 2011. Ezel checks whether it still stands, including any court review since, and answers your specific situation, with citations.

Opens in Ezel Pro. Every answer cites the authority it relies on.