Secretary of Labor v. Active Minerals International, LLC (Commission decision, November 16, 2009)
Secretary of Labor v. Active Minerals International, LLC (FMSHRC SE 2010-38-M): Timely misdirected contest reopened
Apply this precedent to your situation
This is citable Commission precedent from 2009, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.
Plain-English summary
Active Minerals intended to contest penalties for five citations within the 30-day period but mailed its contest to the local MSHA district office instead of the Civil Penalty Compliance Office identified on the assessment form. The Secretary did not oppose reopening. The Commission noted that the filing was timely, went to an MSHA office, and was not part of a pattern of misdirected contests. In the interests of justice, it reopened the final assessment and remanded the case for proceedings on the merits.
Decision snapshot
- Governing provisions: 29 C.F.R. §§ 2700.1(b) and 2700.28; 30 U.S.C. § 815(a)
- Outcome: The assessment was reopened and remanded to the Chief Administrative Law Judge.
- Key point: A timely contest mistakenly sent to the wrong MSHA office may support reopening when the error is isolated and the Secretary does not oppose relief.
Full text (FMSHRC public release)
Federal Mine Safety and Health Review Commission
FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION
601 NEW JERSEY AVENUE, NW
SUITE 9500
WASHINGTON, DC 20001
November 16, 2009
SECRETARY OF LABOR,
MINE SAFETY AND HEALTH
ADMINISTRATION (MSHA)
v.
ACTIVE MINERALS INTERNATIONAL, LLC
:
:
:
:
:
:
:
Docket No. SE 2010-38-M
A.C. No. 09-01192-189515
BEFORE: Jordan, Chairman; Duffy, Young, and Cohen, Commissioners
ORDER
BY THE COMMISSION:
This matter arises under the Federal Mine Safety and Health Act of 1977, 30 U.S.C.
§ 801 et seq. (2006) (“Mine Act”). On October 13, 2009, the Commission received from Active Minerals International, LLC (“Active”) a motion from counsel to reopen a penalty assessment that had become a final order of the Commission pursuant to section 105(a) of the Mine Act, 30 U.S.C. § 815(a).
Under section 105(a) of the Mine Act, an operator who wishes to contest a proposed penalty must notify the Secretary of Labor no later than 30 days after receiving the proposed penalty assessment. If the operator fails to notify the Secretary, the proposed penalty assessment is deemed a final order of the Commission. 30 U.S.C. § 815(a).
We have held, however, that in appropriate circumstances, we possess jurisdiction to reopen uncontested assessments that have become final Commission orders under section 105(a). Jim Walter Res., Inc., 15 FMSHRC 782, 786-89 (May 1993) (“JWR”). In evaluating requests to reopen final section 105(a) orders, the Commission has found guidance in Rule 60(b) of the Federal Rules of Civil Procedure under which, for example, a party could be entitled to relief from a final order of the Commission on the basis of mistake, inadvertence, or excusable neglect. See 29 C.F.R. § 2700.1(b) (“the Commission and its Judges shall be guided so far as practicable by the Federal Rules of Civil Procedure”); JWR, 15 FMSHRC at 787. We have also observed that default is a harsh remedy and that, if the defaulting party can make a showing of good cause for a failure to timely respond, the case may be reopened and appropriate proceedings on the merits permitted. See Coal Prep. Servs., Inc., 17 FMSHRC 1529, 1530 (Sept. 1995).
The Department of Labor’s Mine Safety and Health Administration (“MSHA”) issued Proposed Assessment No. 000189515 to Active on June 30, 2009, proposing penalties for five citations that had been issued to Active in early May 2009. Counsel for Active contends that she timely contested all five penalties on behalf of the operator by letter to the local MSHA district office dated July 13, 2009. The Secretary of Labor does not oppose reopening, but states that the proposed assessment form instructs that notices of contest are to be mailed to MSHA’s Civil Penalty Compliance Office in Arlington, Virginia.
The Secretary correctly points out that the proposed assessment form specifies that contests of proposed penalties are to be sent to the Arlington office. Nevertheless, we note that Active did send its letter to the local MSHA district office within the 30-day period for contests, and there is no indication that Active has previously sent contests to the wrong address.
Having
reviewed Active’s request and the Secretary’s response, in the interests of justice, we hereby reopen this matter and remand it to the Chief Administrative Law Judge for further proceedings pursuant to the Mine Act and the Commission’s Procedural Rules, 29 C.F.R. Part 2700. Accordingly, consistent with Rule 28, the Secretary shall file a petition for assessment of penalty within 45 days of the date of this order. See 29 C.F.R. § 2700.28.
Mary Lu Jordan, Chairman
Michael F. Duffy, Commissioner
Michael G. Young, Commissioner
Robert F. Cohen, Jr., Commissioner
Distribution:
Carla J. Gunnin, Esq.
Constancy, Brooks & Smith, LLC
Suite 2400
230 Peachtree St.
Atlanta, GA 30303-1557
W. Christian Schumann, Esq.
Office of the Solicitor
U.S. Department of Labor
1100 Wilson Blvd., Room 2220
Arlington, VA 22209-2296
Myra James, Chief
Office of Civil Penalty Compliance, MSHA
U.S. Dept. of Labor
1100 Wilson Blvd., 25th Floor
Arlington, VA 22209-3939
Chief Administrative Law Judge Robert J. Lesnick
Federal Mine Safety & Health Review Commission
601 New Jersey Avenue, N.W., Suite 9500
Washington, D.C. 20001-2021
Does this precedent still control your case?
Ezel checks whether it still stands, including any court review since, and applies it to your situation with citations.
Opens in Ezel Pro.
- Checks the law as it stands today, not only this page
- Cites every source it relies on, so you can verify it
- Chat, drafting and research in one workspace