Secretary of Labor v. Moran Environmental Recovery (Commission decision, November 16, 2009)
Secretary of Labor v. Moran Environmental Recovery (FMSHRC SE 2009-687-M): Wrong-address penalty contest reopened
Apply this precedent to your situation
This is citable Commission precedent from 2009, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.
Plain-English summary
Moran Environmental Recovery timely mailed its penalty contest but used the wrong MSHA address. It did not learn of the error until after the 30-day contest period expired. Moran supplied documentation showing that the original mailing was timely, and the Secretary did not oppose relief. The Commission reopened the final assessment in the interests of justice and remanded for proceedings on the merits.
Decision snapshot
- Governing provisions: 29 C.F.R. §§ 2700.1(b) and 2700.28; 30 U.S.C. § 815(a)
- Outcome: The assessment was reopened and remanded to the Chief Administrative Law Judge.
- Key point: Documentation of a timely but misaddressed contest can establish good cause to reopen a final penalty assessment.
Full text (FMSHRC public release)
Federal Mine Safety and Health Review Commission
FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION
601 NEW JERSEY AVENUE, NW
SUITE 9500
WASHINGTON, DC 20001
November 16, 2009
SECRETARY OF LABOR,
MINE SAFETY AND HEALTH
ADMINISTRATION (MSHA)
v.
MORAN ENVIRONMENTAL RECOVERY
:
:
:
:
:
:
:
Docket No. SE 2009-687-M
A.C. No. 38-00014-180422
BEFORE: Jordan, Chairman; Duffy, Young, and Cohen, Commissioners
ORDER
BY THE COMMISSION:
This matter arises under the Federal Mine Safety and Health Act of 1977, 30 U.S.C.
§ 801 et seq. (2006) (“Mine Act”). On July 7, 2009, the Commission received from Moran Environmental Recovery (“Moran”) a letter from its Director of Health & Safety seeking to reopen a penalty assessment that had become a final order of the Commission pursuant to section 105(a) of the Mine Act, 30 U.S.C. § 815(a).
Under section 105(a) of the Mine Act, an operator who wishes to contest a proposed penalty must notify the Secretary of Labor no later than 30 days after receiving the proposed penalty assessment. If the operator fails to notify the Secretary, the proposed penalty assessment is deemed a final order of the Commission. 30 U.S.C. § 815(a).
We have held, however, that in appropriate circumstances, we possess jurisdiction to reopen uncontested assessments that have become final Commission orders under section 105(a). Jim Walter Res., Inc., 15 FMSHRC 782, 786-89 (May 1993) (“JWR”). In evaluating requests to reopen final section 105(a) orders, the Commission has found guidance in Rule 60(b) of the Federal Rules of Civil Procedure under which, for example, a party could be entitled to relief from a final order of the Commission on the basis of mistake, inadvertence, or excusable neglect. See 29 C.F.R. § 2700.1(b) (“the Commission and its Judges shall be guided so far as practicable by the Federal Rules of Civil Procedure”); JWR, 15 FMSHRC at 787. We have also observed that default is a harsh remedy and that, if the defaulting party can make a showing of good cause for a failure to timely respond, the case may be reopened and appropriate proceedings on the merits permitted. See Coal Prep. Servs., Inc., 17 FMSHRC 1529, 1530 (Sept. 1995).
The Department of Labor’s Mine Safety and Health Administration (“MSHA”) issued Proposed Assessment Case Number 000180422 to Moran on March 26, 2009. Moran states that it mailed its contest of the proposed assessment to the wrong MSHA address and was not informed of its error until after the time to file has passed. Moran enclosed documentation indicating that it mailed its letter of contest timely, but to an incorrect MSHA address.
The Secretary does not oppose Moran’s motion to reopen.
Having reviewed Moran’s request and the Secretary’s response, in the interests of justice, we hereby reopen this matter and remand it to the Chief Administrative Law Judge for further proceedings pursuant to the Mine Act and the Commission’s Procedural Rules, 29 C.F.R. Part 2700. Accordingly, consistent with Rule 28, the Secretary shall file a petition for assessment of penalty within 45 days of the date of this order. See 29 C.F.R. § 2700.28.
Mary Lu Jordan, Chairman
Michael F. Duffy, Commissioner
Michael G. Young, Commissioner
Robert F. Cohen, Jr., Commissioner
Distribution:
Leanne M. Stegman
Dir. of Health & Safety
Moran Environmental Recovery
20 Commerce Rd.
Newton, CT 06470
W. Christian Schumann, Esq.
Office of the Solicitor
U.S. Department of Labor
1100 Wilson Blvd., Room 2220
Arlington, VA 22209-2296
Myra James, Chief
Office of Civil Penalty Compliance, MSHA
U.S. Dept. of Labor
1100 Wilson Blvd., 25th Floor
Arlington, VA 22209-3939
Chief Administrative Law Judge Robert J. Lesnick
Federal Mine Safety & Health Review Commission
601 New Jersey Avenue, N.W., Suite 9500
Washington, D.C. 20001-2021
Does this precedent still control your case?
Ezel checks whether it still stands, including any court review since, and applies it to your situation with citations.
Opens in Ezel Pro.
- Checks the law as it stands today, not only this page
- Cites every source it relies on, so you can verify it
- Chat, drafting and research in one workspace