FMSHRC ALJ decision Docket SE 2008-389-R, SE 2008-521-R Decided October 29, 2008 Citations vacated Judge Jacqueline R. Bulluck

Jim Walter Resources, Inc.

Jim Walter Resources, Inc. (FMSHRC SE 2008-389-R and SE 2008-521-R): Sealed-area pump citations vacated

Apply this to your situation

This order from 2008 bound only the parties to this case; it isn't precedent. Ask about your situation and see what the current MSHA standards and Commission precedent say, with citations.

Currency note: this decision dates from 2008
The MSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Final order, not Commission precedent
This decision by a FMSHRC Administrative Law Judge became the final decision of the Commission 40 days after issuance because the Commission did not direct review (30 U.S.C. § 823(d)(1)). It binds the parties but is not binding on the Commission in other cases. The full text below is from the official FMSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official FMSHRC release. The full text is the agency's own release.
Read the official release (fmshrc.gov)

Plain-English summary

Jim Walter Resources used nonpermissible deep well pumps to remove water from permanently sealed areas of its No. 4 and No. 7 mines. MSHA cited the pumps because their power connections were outby the last open crosscut, were not permissible, and were not in intake air. On cross-motions for summary decision, the Judge concluded that the cited standard governed accessible, ventilated mine areas and did not extend to permanently sealed areas with stagnant atmospheres. She also concluded that an MSHA program bulletin could not add that substantive requirement without rulemaking. The Judge granted JWR's motion and vacated both citations.

Decision snapshot

  • Cited standard: 30 C.F.R. § 75.507
  • Outcome: JWR received summary decision, and both pump citations were vacated.
  • Key point: The power-connection standard did not reach inaccessible sealed areas, and agency guidance could not expand its scope to impose a new substantive duty.

Full text (FMSHRC public release)

FMSRHC ALJ DECISION

FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION

OFFICE OF ADMINISTRATIVE LAW JUDGES

601 NEW JERSEY AVENUE, N.W., SUITE 9500

WASHINGTON, DC 20001-2021

TELEPHONE: 202-434-99 / FAX: 202-434-9949

October 29, 2008

JIM WALTER RESOURCES, INC.,

Contestant

v.

SECRETARY OF LABOR,

MINE SAFETY AND HEALTH

ADMINISTRATION (MSHA),

Respondent

:

:

:

:

:

:

:

:

:

:

:

:

:

CONTEST PROCEEDINGS

Docket No. SE 2008-389-R

Citation No. 7691158; 03/04/2008

Mine ID 01-01401

Mine: No. 7

Docket No. SE 2008-521-R

Citation No. 7691159; 03/04/2008

Mine ID 01-01247

Mine: No. 4

SUMMARY DECISION

Before: Judge Bulluck

These cases are before me on Notices of Contest filed by Jim Walter Resources,
Incorporated (“JWR”), against the Secretary of Labor, acting through her Mine Safety and Health
Administration (“MSHA”), pursuant to section 105(d) of the Federal Mine Safety and Health Act
of 1977 (“the Act”), 30 U.S.C. § 815(d). JWR challenges citations issued by MSHA under
section 104(a) of the Act, alleging violations of the Secretary’s mandatory safety standard found
at 30 C.F.R. § 75.507.

The parties have filed cross Motions for Summary Decision.

The Commission rule
governing summary decisions, Rule 67(b), provides as follows:

A motion for summary decision shall be granted only if the entire record . . .
shows: (1) That there is no genuine issue as to any material fact; and (2) That the
moving party is entitled to summary decision as a matter of law.

29 C.F.R. § 2700.67(b). Based upon the stipulations and uncontested facts represented by the
parties, I find that there is no genuine issue as to any material fact. Having reviewed the parties
Motions, I conclude that, for the reasons stated below, JWR is entitled to summary decision as a
matter of law.

I. Stipulations

The parties stipulated as follows:

1. The Administrative Law Judge and the Federal Mine Safety and Health Review
Commission have jurisdiction to hear and decide this [contest] proceeding pursuant to section
105 of the Federal Mine Safety and Health Act of 1977;

2. JWR is a mine operator subject to the jurisdiction of the Federal Mine Safety and
Health Administration;

3. JWR is the owner and operator of the No. 7 Mine located in Tuscaloosa County,
Alabama;

4. Operations at the No. 7 Mine are subject to the requirements of the [Federal] Mine
Safety and Health Act;

5. MSHA Inspector John M. Church was acting in his official capacity as an authorized
representative of the Secretary of Labor when he issued Citation No. 7691158; and

6. Citation No. 7691158 was served on JWR or its agent as required by the Act.

JWR Mot. at 1.

II. Factual Background

These matters concern JWR’s use of non-permissible deep well submersible pumps in
sealed areas of its No. 4 and No. 7 Mines. JWR’s operation of these pumps in No. 7 was
challenged by MSHA in October of 2004, under section 75.507-1.

JWR duly contested the
citation, and the case was heard and adjudicated by me. See Jim Walter Resources, Inc., 27
FMSHRC 968, 978 (Dec. 2005) (ALJ) (“JWR-I”). In its Motion for Summary Decision, JWR
asserts that the instant proceeding and JWR-I involve the same parties and controlling facts.
JWR Mot. at 5. The Secretary does not challenge this assertion. As in JWR-I, here MSHA cited
the submersible “deep well” pump systems in No. 4 and No. 7 Mines, with both surface and
underground components, which JWR uses to remove vast accumulations of water from
permanently sealed, worked-out underground areas where coal was formerly mined.

The conditions in the areas being dewatered remain consistent with the description set
forth in JWR-1:

Once the permanent seals are erected, the sealed areas are totally isolated and
inaccessible; they cannot be traveled, examined, inspected or ventilated. The
water that collects in the sealed area at issue forms a large underground lake that
requires constant management, so as to prevent the water from compromising the
seals and inundating the active workings of the No. 7 Mine. The pumps,
therefore, are situated at the lowest elevations of the sealed areas in natural water
collection basins. In addition to the pumps, as part of its methane drainage
system, JWR has numerous degas wells situated at intervals throughout the sealed
area, which are the sole means of determining atmospheric conditions in the
otherwise inaccessible area.

27 FMSHRC at 969-70 (footnote and citations omitted).

The pumps at issue are active electric submersible pumps, utilized in the sealed area of
No. 7 since 1987, and are described in JWR-1 as follows:

All electric controls for the pump are housed above ground in a pump starter unit. From
the starter unit, a high voltage power conductor cable, encased in a steel pipe, runs some
2,000 feet underground to the original mine floor, and an additional 200 feet beneath that
surface, where the electric motor and pump assembly are situated in a sump. The steel
casing, at ground level on the surface, is capped by a metal well head. The motor sits at
the bottom of the sump and is 30 feet high, there is a 5-foot seal between the motor and
the pump, and the pump, itself, also 30 feet high, sits on top of the seal. According to the
manufacturer’s specifications, in order for the pump to operate, there must be at least 30
feet of water (“head”) above the inlet of the pump, so that the motor and pump assembly
require 65 feet of water in which to operate. Inside the steel casing is also a metal
discharge pipe. The casing is slotted just below the water level, allowing water into the
casing where it is forced down a second set of slots at the bottom, where it cools the
electric motor. The pump, with a 500-gallon-per-minute capacity, then transports the
water up the discharge pipe to a surface settlement pond. A vacuum sensor, located on
the surface, automatically shuts off the power from the pump starter to the entire system,
if it detects that the water level had dropped below 30 feet of head above the pump.
Additionally, JWR has installed a redundant safety system, undercurrent protection, that
will also disable the system.

Id. at 970 (citations omitted).

III. Procedural Background

The enforcement history associated with JWR’s deep well submersible pumps is set forth
in JWR-I, as well:

JWR’s submersible pumps . . . had always been inspected by MSHA under Part
77 regulations applicable to surface areas of underground mines, and the National
Electric Code (“NEC”). Under Part 77, the pumps were not required to be
permissible. Sometime in 2003, in response to inconsistent enforcement in the
districts, i.e., some were inspecting submersible pumps under Part 75 while others
were applying Part 77, MSHA’s Safety Division decided to impose uniform,
nationwide compliance under Part 75. As a consequence, in order to continue use
of nonpermissible pumps behind the seals underground, operators who had been
inspected under Part 77 were required to file Petitions for Modification under
section 101(c) of the Act.

JWR opposed MSHA’s application of Part 75 underground standards and when
extensive informal discussions about the safety of JWR’s pumps proved
unfruitful, JWR filed a Petition for Modification with MSHA on July 22, 2003,
seeking approval to continue operation of its nonpermissible submersible pumps
in sealed areas of its Alabama mines, including No. 7 herein at issue. In the
meantime, before issuing its decision on the Petition, MSHA issued Program
Information Bulletin No. P03-26 (“PIB”), clarifying compliance requirements for
nonpermissible electric submersible dewatering pumps installed in sealed areas,
return air courses or bleeder entries in underground coal mines. The PIB notified
the mine industry of MSHA’s application of section 75.507 to submersible
pumps, that the pumps are located in return air for purposes of the regulation, and
that they are required to be permissible, unless a modification is approved by
MSHA.

MSHA issued its Proposed Decision and Order (“PDO”) on June 17, 2004,
authorizing JWR to continue use of its submersible pumps under specific detailed
conditions. JWR found the conditions unacceptable and appealed the PDO,
arguing, inter alia, that section 75.507 does not apply to the pumps at issue.

Id. at 970-71 (footnote and citations omitted).

On October 14, 2004, MSHA cited JWR for operating a nonpermissible deep well
submersible pump in “return air” in violation of 30 C.F.R. § 75.507-1. Id. at 971-72. JWR
contested this citation which, after an evidentiary hearing, was vacated. Pending the outcome of
that proceeding, JWR’s appeal of the PDO was stayed by the Department of Labor’s presiding
ALJ. After the case was decided, on joint motion of the parties, the judge dismissed the appeal
as moot. JWR Mot. at 2, 4.

The instant consolidated proceeding arises from section 104(a) Citation Nos. 7691158
(No. 7 Mine) and 7691159 (No. 4 Mine), issued to JWR by MSHA Inspector John Church on
March 4, 2008. Both citations allege a violation of 30 C.F.R. § 75. 507 and describe the
“Condition or Practice” as follows:

The mine operator utilizes deep well pumps with power connection points that are
outby the last open crosscut and are not in intake air and permissible power
connection units are not being used.

JWR timely contested the citations and, in its Motion for Summary Decision, challenges
MSHA’s application of section 75.507 to the company’s non-permissible deep well submersible
pumps, arguing that the standard does not apply to the sealed areas of its mine. JWR Mot. at 10.
In her Motion for Summary Decision, the Secretary argues that she is “entitled to judgment as a
matter of law [because the] pumps are indisputably outby the last open crosscut, are indisputably
not located in intake air and [are] indisputably not permissible.” Sec’y Mot. at 3.

IV. Findings of Material Fact and Conclusions of Law

JWR and the Secretary essentially agree that the material facts upon which each is
entitled to judgment as a matter of law are as follows:

1. The deep well pumps installed behind the seals at the JWR Number 7 Mine have
power connection points that are not permissible;

2. The power connection points on the deep well pumps are located outby the last open
crosscut; and

3. The deep well pumps installed behind the seals at the JWR Number 7 Mine are not
located in intake air.

Sec’y Mot. at 2; JWR Mot at 2-7.

The cited regulation provides as follows:

Except where permissible power connection units are used, all power-connection
points out by the last open crosscut shall be in intake air.

30 C.F.R. § 75.507. This regulation codifies, with only a slight change in syntax, section 305(d)
of the Act, which provides:

All power-connection points, except where permissible power connection units
are used, outby the last open crosscut shall be in intake air.

30 U.S.C. § 865(d).

The issue upon which these cases turn is whether section 305(d) of the Act, codified in
the Secretary’s regulations at 30 C.F.R. § 75.507, was intended to reach beyond areas of
underground coal mines that are ventilated to those areas permanently cut off from normal
ventilation. As there is a statutory provision at issue, the first inquiry is “whether Congress has
directly spoken to the precise question at issue.” Chevron U.S.A., Inc. v. Natural Res. Defense
Council, Inc., 467 U.S. 837, 842 (1984); Thunder Basin Coal Co., 18 FMSHRC 582, 584 (Apr.
1996). If section 305(d) is clear and unambiguous, effect must be given to its language. See
Chevron, 467 U.S. at 842-43; accord Local Union 1261, UMWA v. FMSHRC, 917 F.2d 42, 44
(D.C. Cir. 1990). In determining whether Congress had an intention on the specific question at
issue, courts utilize traditional tools of construction, including an examination of the “particular
statutory language at issue, as well as the language and design of the statute as a whole.” K Mart
Corp. v. Cartier, Inc., 486 U.S. 281, 291 (1988); Local Union 1261, 917 F.2d at 44.

As mentioned previously, the material facts of these cases would seem to establish, at
first blush, the elements of a violation of section 75.507. The power connection points on JWR’s
deep well submersible pumps are, contrary to the requirements of the regulation, not permissible,
outby the last open crosscut, and not in intake air. This result, however, can be achieved only by
formulaically applying section 75.507 out of context and in such a way that ignores the
Secretary’s regulations “as a whole.” K Mart Corp., 486 U.S. at 291. When viewed in their
entirety, the vast majority of the Secretary’s regulations can only be applied reasonably to
accessible areas of a mine that, of necessity, require ventilation. As pointed out in JWR-1, “[b]y
definition and operation, intake and return air circulate and work, consistent with the demands of
active mining in the accessible parts of the mine.” 27 FMSHRC at 977 (emphasis added). Here,
however, the pumps are situated in inaccessible parts of the mines where, after the areas were
sealed, dramatic atmospheric changes occurred within a relatively short period of time due to
permanent separation from ventilation controls and circulated air systems. When seals were
erected, the resultant stagnant environment behind the seals was entirely dissimilar to that in the
active areas of the mine. In answer to the question posed in Chevron, I conclude that Congress
did not speak to “the precise question at issue.” 467 U.S. at 842. Section 305(d) was intended to
regulate use of equipment in an underground mine’s ventilated areas, where intake and return air
systems circulate to provide miners with fresh breathable air, and prevent contaminated air, laden
with combustible byproducts of mining activities, from exposure to ignition sources. This
statutory provision was not intended to regulate permanently sealed areas of mines comprised of
atmospheres wholly dissimilar to that of the active working areas.

To further illustrate the misapplication of the cited standard, I point to another standard in
Subpart F of 30 C.F.R. Part 75. JWR’s pumps are electric equipment which, following the
formulaic logic of the Secretary, would be subject to the requirements of section 75.512. This
regulation is also the codification of a statutory provision, and provides that “[a]ll electric
equipment shall be frequently examined, tested, and properly maintained by a qualified person to
assure safe operating conditions.” 30 C.F.R. § 75.512. Given that the submersible pumps are in
a “no man’s land” that cannot be examined at all, much less frequently, compliance with section
75.512 is an impossibility.

I recognize that, as to sealed areas of underground coal mines, the Secretary has
legitimate safety concerns. These concerns, however, are subject to the proposition that “a
regulation cannot be construed to mean what an agency intended but did not adequately express.”
Phelps Dodge Corp. v. FMSHRC, 681 F.2d 1189, 1193 (9th Cir. 1982) (citations omitted).
When, in 2003, the Secretary issued PIB No. P03-26, notifying mine operators that MSHA would
henceforth apply section 75.507 to submersible pumps, she attempted to graft onto section
75.507 a new substantive requirement, i.e., she widened the ambit of section 75.507 to include
sealed areas, which imposed new obligations that significantly affected private interests. See
Drummond Co., 14 FMSHRC 661, 684-85 (May 1992) (distinguishing between substantive
rules, which require notice and comment rulemaking, and procedural rules, which do not). The
Secretary’s continued attempt to do so is contrary to well established principles of administrative
law, as set forth in Drummond.

Even the Secretary’s own regulations, however, both undercut her interpretation of
section 75.507 and illustrate the unreasonableness of attempting to fit the square peg of
regulating stagnant atmosphere in sealed areas into the round hole of provisions clearly intended
to regulate accessible, ventilated areas. The Secretary’s ventilation regulations contained in
Subpart D of 30 C.F.R. Part 75 include a provision entitled “Construction and repair of seals,”
which states, in relevant part:

(a) The mine operator shall maintain and repair seals to protect miners from
hazards of sealed areas.

(b) Prior to sealing, the mine operator shall – (1) Remove insulated cables,
batteries, and other potential electric ignition sources from the area to be sealed
when constructing seals, unless it is not safe to do so. If ignition sources cannot
safely be removed, seals must be constructed to at least 120 psi[.]

30 C.F.R. § 75.337 (emphasis added). Here, when JWR sealed areas that required constant
dewatering in its No. 4 and No. 7 Mines, it placed in those sealed areas pumps that were potential
electric ignition sources. Whether it was unsafe to do so is a question that is not before me, nor
is JWR cited in the instant matters for violating the requirements of section 75.337. The
Secretary would be well advised, it would seem, to reconsider the issue in light of section 75.337,
which, at least, recognizes the unique “hazards of sealed areas,” and also contemplates utilizing
“electric ignition sources” within sealed areas, so long as they are isolated from the active mine
workings by seals constructed in accordance with the specification in the standard.

Because I find that the Secretary’s interpretation of section 75.507, as applied to deep
well submersible pumps operating in sealed areas, impermissibly expands the scope of section
75.507, no violation has been committed by JWR, and Citation Nos. 7691158 and 7691159 are
hereby vacated.

ORDER

Accordingly, for the reasons set forth herein, JWR’s Motion for Summary Decision is
GRANTED, the Secretary’s Motion for Summary Decision is DENIED, and Citation Nos.
7691158 and 7691159 are VACATED.

Jacqueline R. Bulluck

Administrative Law Judge

Distribution: (Certified Mail)

Warren B. Lightfoot, Jr., Esq., Maynard, Cooper & Gale, P.C., 1901 Sixth Ave. North, 2400
AmSouth/Harbert Plaza, Birmingham, AL 35203

Thomas A. Grooms, Esq., Office of the Solicitor, U.S. Department of Labor, 618 Church Street,
Suite 230, Nashville, TN 37219-2456

/mh

Get today's answer for your situation

You just read what one judge decided for one employer in 2008, and it binds only those parties. Ezel checks the current MSHA standards and Commission precedent and answers your specific situation, with citations.

Opens in Ezel Pro. Every answer cites the authority it relies on.