Port Townsend Paper Corp. (Board decision, January 12, 1998)
In re Port Townsend Paper Corp. (EAB PSD Appeal Nos. 97-13, 97-14): appeals dismissed
Apply this precedent to your situation
This is citable Board precedent from 1998, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.
Plain-English summary
Port Townsend Paper Company and Rebound each petitioned the EAB to review a PSD permit approved by Washington's Department of Ecology and EPA Region X. Port Townsend withdrew its petition as untimely, while Rebound's petition did not show that it had commented on the draft permit or participated in the public hearing. The Board dismissed Rebound's petition for lack of standing and dismissed Port Townsend's petition with prejudice. The order did not decide the merits of the claim that either petition was untimely.
Decision snapshot
- Cited authorities: 40 C.F.R. § 124.19 and 40 C.F.R. § 124.19(a).
- Outcome: Rebound's appeal was dismissed for lack of standing, and Port Townsend's appeal was dismissed with prejudice after withdrawal.
- Key point: A petitioner generally must have commented on the draft permit or participated in the public hearing to challenge final-permit conditions that were already in the draft permit.
Full text (EPA EAB public release)
BEFORE THE ENVIRONMENTAL APPEALS BOARD
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY WASHINGTON, D.C.
)
In re: )
)
Port Townsend Paper Corp. ) PSD Appeal Nos. 97-13, 97-14 )
Permit No. PSD 96-01
)
)
)
ORDER DISMISSING APPEALS
On September 22, 1997, the Board received two petitions
asking that the Environmental Appeals Board review a PSD permit
approved jointly by the State of Washington’s Department of
Ecology ("WDOE") and U.S. EPA Region X. One was filed by the
permittee, Port Townsend Paper Company ("Townsend") (PSD Appeal
No. 97-13), and the other was filed by Rebound (PSD Appeal No.
97-14), a group of citizens living and working in the vicinity of
the permitted facility.
On December 8, 1997, Townsend filed a motion seeking
dismissal of Rebound’s petition for review on the ground that the
petition was not timely filed. In addition, Townsend states that
it is withdrawing its own petition for the same reason. See Port
Townsend Paper Corporation’s Withdrawal of PSD Appeal No. 97-13
and Motion to Dismiss PSD Appeal No. 97-14 for Failing to Comply
with 40 CFR § 124.19 ("Withdrawal") and Port Townsend Paper
Corporation’s Memorandum Re Withdrawal of PSD Appeal No. 97-13
and in Support of Motion to Dismiss PSD Appeal No. 97-14 for
Failing to Comply with 40 CFR § 124.19 ("Memorandum"). In
particular, the memorandum states that the above-referenced PSD
permit was issued on June 18, 1997, and served on June 23, 1997,
and that neither Townsend’s nor Rebound’s petition for review was
filed within the 30-day time period required by 40 C.F.R.
§ 124.19. Memorandum at 3. In addition, Townsend contends that
because Rebound did not file comments on the draft PSD permit
issued by WDOE, Rebound lacks standing to appeal pursuant to 40
C.F.R. § 124.19(a). Memorandum at 9.1
After reviewing the record on appeal, we agree with Townsend
that Rebound’s failure to comment on the draft permit requires
dismissal of Rebound’s appeal. As the Board has previously
stated, under the regulations governing permit appeals before the
Board:2
[A] petitioner has "standing" to pursue an appeal of the conditions of a final permit that are identical to the conditions of the draft permit only if the petitioner filed timely comments on the draft permit or participated in the public hearing on the draft permit.
-
-
- A petitioner who failed to file comments on a draft permit or participate in the public hearing will only have standing to pursue an appeal to the extent that the conditions in the draft permit are changed in the final permit. * * * This requirement is imposed in order to "ensure that the Region has an opportunity to address potential problems with the draft permit before
-
1
Rebound has not filed a reply to Townsend’s Withdrawal or its Memorandum.
2
See 40 C.F.R. § 124.19(a).
the permit becomes final."
In re Commonwealth Chesapeake Corp., PSD Appeal Nos. 96-2 through
96-5, slip op. at 9 (EAB, Feb. 19, 1997), 6 E.A.D. ___ (quoting
In re Envotech, L.P., UIC Appeal No. 95-2 through 95-37, slip op.
at 6, Feb. 15, 1996), 6 E.A.D. ___).
Rebound’s petition does not claim or demonstrate that it
filed comments on the draft permit or otherwise participated
during the public comment period,3 nor does the petition purport
to relate to changes from the draft to the final permit. Based
on the record before the Board, it does not appear that Rebound
has fulfilled the regulatory prerequisites to having standing to
petition for review from WDOE’s and Region X’s permit decision.
Accordingly, Rebound’s petition must be dismissed for lack of
standing.
Finally, based on Townsend’s statement that it is
3
Our review of the record before us verifies that Rebound did not participate in the proceedings below. See letter accompanying final permit to Marion L. Rideout, Port Townsend Paper Corp., from Richard B. Hibbard, WDOE (June 23, 1997) (stating that Port Townsend was the only non-WDOE commenter).
withdrawing its petition as untimely, Townsend’s petition is
hereby dismissed with prejudice.4
ENVIRONMENTAL APPEALS BOARD
Dated: 1/13/98 By: /s/
Ronald L. McCallum
Environmental Appeals Judge
4
In dismissing Townsend’s petition, we are relying solely on Townsend’s statement that it is withdrawing its appeal. We do not reach, and express no opinion on, the merits of Townsend’s assertion that both its and Rebound’s petition were untimely.
CERTIFICATE OF SERVICE
I hereby certify that copies of the foregoing Order
Dismissing Appeals in the matter of Port Townsend Paper Corp.,
PSD Appeal Nos. 97-13 and 97-14 were sent to the following
persons in the manner indicated:
First Class Mail,
Postage Prepaid: Matthew Cohen
Heller, Ehrman, White,
& McAuliffe
610 Columbia Center
701 Fifth Ave.
Seattle, WA 98104-7098
Otto Herman
Rebound
2700 First Ave., Suite 103
Seattle, WA 98121
Mary Sue Wilson
Kurt B. Peterson
Assistant Attorneys General
State of Washington
Ecology Division
P.O. Box 40117
Olympia, WA 98504-0177
Chuck Clarke
Regional Administrator
U.S. EPA, Region X
1200 Sixth Ave.
Seattle, WA 98101
Anita Frankel, Director
Office of Air Quality
U.S. EPA, Region X
1200 Sixth Ave.
Seattle, WA 98101
Dated: 1/13/98
/s/
Mildred T. Johnson
Staff Assistant
Does this precedent still control your case?
Ezel checks whether it still stands, including any court review since, and applies it to your situation with citations.
Opens in Ezel Pro.
- Checks the law as it stands today, not only this page
- Cites every source it relies on, so you can verify it
- Chat, drafting and research in one workspace