EPA EAB Board decision Docket PSD 92-3, PSD 92-4, PSD 92-5 Decided October 5, 1992 Remanded Transcribed from scan

Hadson Power 14--Buena Vista

In re Hadson Power 14, Buena Vista (EAB PSD Appeal Nos. 92-3, 92-4, and 92-5): permit remanded

Apply this precedent to your situation

This is citable Board precedent from 1992, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.

Currency note: this decision dates from 1992
The EPA regulations may have been amended, penalty amounts have been adjusted, and later Board or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Final EAB decision
This Environmental Appeals Board Remand Order is a final disposition of the permit appeal. The Board remanded the PSD permit to the Virginia Department of Air Pollution Control for reconsideration of construction emissions, adverse impact determinations, and related public-notice deficiencies, while denying review of other issues. The full text below is the official EPA release, transcribed from the official PDF with proofread OCR.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official EPA EAB release. The full text is the agency's own release.
Transcribed from a scanned original: EPA EAB released this decision as an image-only file. The full text below is a machine transcription, proofread against the scan. Check the official release before quoting exact language.
Read the official release (epa.gov)

Plain-English summary

Hadson Power 14, Buena Vista proposed a 66.5-megawatt coal-fired electric generating plant in Buena Vista, Virginia. The Southern Environmental Law Center, Clean Air for Rockbridge, and the County of Rockbridge challenged the plant's Prevention of Significant Deterioration permit. The Environmental Appeals Board held that the state permitting authority had not properly addressed the Federal Land Managers' adverse-impact determinations, had excluded construction emissions without an adequate basis, and had failed to give sufficient public notice about increment consumption and the non-Guideline model. The Board denied review of several other issues, including the challenge to the nitrogen-oxide BACT condition and most modeling arguments. It remanded the permit for a new substantive review and reopened public comment on the identified issues.

Decision snapshot

  • Cited authorities: 40 C.F.R. §§ 51.166, 52.21, 81.347, 124.19, 124.41, and 1508.18; 42 U.S.C. §§ 4332, 7470, 7472, 7473, and 7475.
  • Outcome: The permit was remanded to the state permitting authority for reconsideration of construction emissions, adverse-impact determinations, public notice, and related issues. Review of the remaining issues was denied.
  • Key point: A PSD permitting authority must substantively address Federal Land Manager findings, account for construction emissions unless properly excluded, and disclose material modeling and increment-consumption information in public notice.

Full text (EPA EAB public release)

258 ENVIRONMENTAL ADMINISTRATIVE DECISIONS
IN THE MATTER OF HADSON POWER 14—BUENA
VISTA
PSD Appeal Nos. 92-3, 92-4, 92-5
REMAND ORDER
Decided October 5, 1992
Syllabus

The Southern Environmental Law Center, Clean Air for Rockbridge (CLEAR)
and the County of Rockbridge have filed petitions seeking review of a Prevention
of Significant Deterioration (PSD) permit issued to Hadson Power 14—Buena Vista.
The permit was issued by the Virginia Department of Air Pollution Control (VDAPC)
pursuant to a delegation from the U.S. EPA, and thus is considered an EPA-issued
permit for purposes of appeal. The permit authorizes the construction of a 66.5 mega-
watt coal-fired electric generating plant in Buena Vista, Virginia. The proposed facility
is located 15 km north of the James River Face Wilderness and 56 km southwest
of the Shenandoah National Park.

The most significant issue raised in the petitions is the rejection by VDAPC
of adverse impact determinations by the Federal Land Managers (FLMs) of the Wilder-
ness and the Park. Other issues raised include the ‘exclusion of sources more than
100 km from the class I areas from the increment consumption analysis, exclusion
of construction emissions from the air quality analyses, the adequacy of the emission
limits for NOx, coordination of the PSD review with the National Park Service’s envi-
ronmental impact assessment, alleged deficiencies in the notice provided on the draft
permit, and various air quality modeling issues.

Held: VDAPC erred in rejecting the FLMs’ adverse impact determinations. The
state based its rejections largely on its interpretation of the burden on the FLMs,
which interpretations EPA’s Administrator specifically found to be invalid in In re
Old Dominion Electric Cooperative, PSD Appeal No. 91-39 (Adm’r, Jan. 29, 1992).
Here, unlike in Old Dominion, this error was not harmless because VDAPC has
not articulated any alternative, legally supportable basis for rejecting the adverse
impact determinations.

VDAPC also erred in categorically excluding construction emissions from the
air quality analyses, in failing to give public notice of its intention to use an air
quality model not previously subject to public scrutiny, and in providing an incomplete
description of proposed increment consumption in its public notice of the draft permit.
No error is found in VDAPC’s determination of the NOx emissions limitation, in
the exclusion of sources more than 100 km from the class I areas from the increment
consumption analysis, and in the degree of coordination with the National Park Serv-
VOLUME 4
HADSON POWER 14—BUENA VISTA 259
|
ice’s environmental review. Review of the air quality modeling issues is denied due
to the inadequacy of the petitions in stating a basis for review.

The permit is remanded to VDAPC to perform a substantive review of the adverse
impact determinations, to reopen the public comment process, and to address the
other deficiencies in accordance with this opinion.

Before Environmental Appeals Judges Nancy B. Firestone,
Ronald L. McCallum, and Edward E. Reich.

Opinion of the Board by Judge Reich:

Three petitions have been filed with the Environmental Appeals
Board seeking review of a Prevention of Significant Deterioration
(PSD) permit issued to Hadson Power 14—Buena Vista (“Hadson
Power”) for the construction of a 66.5 megawatt coal-fired electric
generating power plant in Buena Vista, Virginia. Pursuant to a dele-
gation of authority from the U.S. EPA, Region III, the Virginia De-
partment of Air Pollution Control (VDAPC) issued the final permit
on April 18, 1992. Because of the delegation, the Virginia permit
is considered an EPA-issued permit for purposes of federal law (40
C.F.R. § 124.41 (1991); 45 Fed. Reg. 33,413 (May 19, 1980)), and
is subject to review by the Agency under 40 C.F.R. § 124.19 (1991).

PSD Appeal No. 92-3 was filed by the Southern Environmental
Law Center (SELC) on behalf of itself and other various groups.!
One of these groups, Clean Air for Rockbridge (CLEAR), and CLEAR’s
president (Michael Lonergan) and treasurer (Saundra Martis), also
filed a separate petition raising additional reasons to review the
permit (PSD Appeal No. 92-5). The third petition for review, PSD
Appeal No. 92—4, was filed by the County of Rockbridge (the “Coun-
ty”). At the request of this Board, VDAPC provided a response to
the petitions for review and submitted relevant portions of the admin-
istrative record.2 Pursuant to leave granted by the Board, both SELC
and CLEAR filed a reply to VDAPC’s response.

1These groups are the Conservation Council of Virginia, National Parks and Con-
servation Association, Virginia Council of Trout Unlimited, Virginia Wildlife Federa-
tion, Sierra Club, Environmental Defense Fund, The Wilderness Society, Southside
Concerned Citizens, Clean Air for Rockbridge (CLEAR), and Michael Lonergan and
Saundra Martis, individually and as president and treasurer of CLEAR, respectively.

2Each petition will be referred to with reference to the petitioner, eg., “SELC
Petition at .” Likewise, VDAPC’s responses will be referred to with reference
to each petitioner, e.g., “Response to SELC Petition at
.” Attachments to VDAPC’s

responses will be referred to as “Response to Petitions, Attachment __..”
VOLUME 4
260 ENVIRONMENTAL ADMINISTRATIVE DECISIONS

Under the rules that govern this proceeding, a PSD permit ordi-
narily will not be reviewed unless it is based on a clearly erroneous
finding of fact or conclusion of law, or involves an important matter
of policy or exercise of discretion that warrants review. See 40 C.F.R.
§ 124.19; 45 Fed. Reg. 33,412 (May 19, 1980). The preamble to the
promulgation of these rules states that “this power of review should
be only sparingly exercised,” and that “most permit conditions should
be finally determined at the Regional [or State] level.” Id. The burden
of demonstrating that review is warranted is on the petitioner. For
the reasons set forth below, we conclude that petitioners have met
the burden of showing that review of several issues is warranted,
and that the permit should be remanded to the state for further action consistent with this opinion.®

BACKGROUND

Under the PSD program, owners or operators of major emitting
facilities in attainment or unclassifiable areas* must obtain a PSD
permit prior to the construction of that facility. Clean Air Act (CAA)
§165, 42 U.S.C. §7475. In May 1988, Hadson Power applied for
a PSD permit to build a coal-fired power plant in Buena Vista,
Virginia capable of producing 66.5 megawatts of electrical power.
The proposed facility is located 15 km north of the James River
Face Wilderness (the “Wilderness”) and 56 km southwest of the Shen-
andoah National Park (the “Park”). One of the stated purposes of
the PSD program is “to preserve, protect, and enhance the air quality
in national parks [and] national wilderness areas.” CAA § 160(2);
42 U.S.C. § 7470(2). Therefore, many of these parks and wilderness
areas are designated as class I areas under CAA §162(a), 42 U.S.C.
§ 7472(a). As discussed below in more detail, class I areas are entitled

3Due to the extensive briefing of these issues on appeal, further briefing would
not be helpful. See In re Renkiewicze SWD-18, UIC Appeal No. 91-4, slip op. at
n.5 (EAB, June 24, 1992) (“Although § 124.19 * * * contemplates that additional
briefing will be submitted upon the grant of a Petition for Review, a direct remand
without additional submissions is appropriate where, as here, it does not appear
that further briefs on appeal would shed light on the issues to be addressed on
remand.”).

4An attainment area is one in which the national ambient air quality standards
for particular pollutants are met. PSD rules apply to these areas (and to these pollut-
ants) to ensure that air quality is maintained. See 40 C.F.R. §52.21(a). PSD rules
also apply to areas where attainment status cannot be classified. 40 C.F.R. §52.21(i)(3);
In re American Re-Fuel Company of Essex County, PSD Appeal No. 86—1, unpub.
op. at n.5 (Adm’r, Oct. 6, 1986). The City of Buena Vista and Rockbridge County
are attainment areas for TSP and SO2, and are unclassifiable for O3, CO & NOx.
See 40 C.F.R. § 81.347.
VOLUME 4
HADSON POWER 14—BUENA VISTA 261
to additional protection under the PSD program. Both the Wilderness
and the Park are class I areas.

PSD permit applicants must demonstrate that emissions from
a proposed facility “will not cause, or contribute to, air pollution
in excess of,” inter alia, certain statutorily allowable increases in
pollution levels, called “increments.” CAA § 165(a)(3). Only small in-
crements are available in class I areas. CAA § 163(b)(1); 42 U.S.C.
§ 7473(b)(1). Because the proposed facility is located in complex ter-
rain within 100 km of two class I areas, existing models were deter-
mined to be invalid for the air quality analysis in this case. EPA
approved a hybrid model created by Hadson Power from existing
models to perform the increment consumption analysis. EPA allowed
Hadson Power to divide the Park into northern and southern portions
for the increment consumption analysis. See Memorandum from Exec-
utive Director, VDAPC, to Virginia Air Pollution Control Board Mem-
bers at 5-3 (Mar. 26, 1992) (Response to Petitions, Attachment IV)
(hereinafter “VDAPC Memo.”). Hadson Power followed VDAPC’s pol-
icy of examining only the effect of increment-consuming sources with-
in 100 km of a class I area, and in one instance went beyond the
minimum requirements of this policy by modeling sources far more
than 100 km from the northern portion of the Park.

EPA has a longstanding policy of using significance levels to
determine whether a proposed source will cause or contribute to
an increment violation.5 According to VDAPC, the net effect of emis-
sions from Hadson Power’s proposed facility and previously permitted
projects, after considering the offsets provided by Georgia Bonded
Fibers, Inc. (“Georgia Bonded Fibers”), is to consume 48 to 91%

5 See 43 Fed. Reg. 26,398 (June 19, 1978) (adopting minimum amount of ambient
impact that is significant). These significance levels, however, do not apply to analyses
of increment consumption in class I areas. Hadson Power requested and received
EPA approval to use significance levels proportional to the class II levels for the
analysis of increment consumption in the Wilderness and the Park class I areas.
See Memorandum from John Calcagni, Director, EPA Air Quality Management Divi-
sion, to Thomas J. Maslany, Director, Region III Air, Radiation and Toxics Division
(Sept. 10, 1991) (Response to Petitions, Attachment V).

6Hadson Power intends to provide eight percent of its steam generation to Georgia
Bonded Fibers, a manufacturer located across the Maury River from the proposed
facility. While operating under this contractual arrangement with Hadson Power, Geor-
gia Bonded Fibers has agreed to shut down its boilers, and the resulting emissions
reduction will partially offset the emissions from Hadson Power. VDAPC Memo. at
5-34. At the time of permit issuance, Hadson Power and Georgia Bonded Fibers
were negotiating this agreement. Id. These offsets were included in Hadson Power's
increment consumption analysis in support of its permit application. Id.

. VOLUME 4
262 ENVIRONMENTAL ADMINISTRATIVE DECISIONS

of SO2 7 and 74% of NOx increments available in the Wilderness,
and 69 to 90% of SO2 and 91% of NOx increments available in
the southern portion of the Park. VDAPC Memo. at 5-2. VDAPC
concluded that Hadson Power will not cause or contribute signifi-
cantly to a class I increment violation in either area. Id. at 5-10
to 5-12.

The Clean Air Act also requires that written notice of a proposed
PSD permit be provided to the Federal Land Manager (FLM) for
a class I area that may be affected by emissions from the proposed
facility. CAA § 165(d)(2)(A). If the increment analysis indicates no
violation of a class I increment, as VDAPC concluded was the case
here, a permit may be issued unless the FLM demonstrates to the
state’s satisfaction that the proposed emissions will have an adverse
impact on air quality-related values (AQRVs) in the class I area.
CAA § 165(d)(2)(C)(ii).

As discussed in more detail below, on January 31, 1992, the
Park FLM® submitted a final adverse impact determination for
Hadson Power’s draft permit. See Letter from James M. Ridenour,
Director, National Park Service, to Wallace N. Davis, Executive Direc-
tor, VDAPC (Jan. 31, 1992), SELC Petition, App. D (hereinafter “Park
AID”). On February 3, 1992, the Wilderness FLM® also submitted
a final adverse impact determination for Hadson Power’s proposed
facility. See Letter from Joy E. Berg, Forest Supervisor, Jefferson
National Forest, to Donald L. Shepherd, Director, Region I], VDAPC
(Feb. 3, 1992), SELC Petition, App. C (hereinafter “Wilderness AID”).
VDAPC rejected the FLMs’ adverse impact determinations.

The final permit allows emissions of 797 tons per year (tpy)
for NOx, 358 tpy for SO2, and 96.5 tpy for volatile organic compounds
(VOCs). See Permit, Part I, Condition 22, Response to Petitions, At-
tachment X (hereinafter “Permit”). Hadson agrees to control its NOx
emissions through combustion controls and the application of selective
catalytic reduction (SCR), which VDAPC decided is the best available
control technology (BACT) for this pollutant. The permit reflects the
use of SCR by requiring that the boilers be designed to achieve
an emission rate of 0.10 lbs/10^6 Btu. Permit, Part I, Condition 7.

7These percentages relate to the different SO2 increments with various averaging
periods. See VDAPC Memo. at 5-11 to 5-12.

8The Park FLM is the Assistant Secretary for Fish and Wildlife and Parks,
Department of the Interior.

®The Wilderness FLM is the Jefferson National Forest Supervisor in the Forest
Service, Department of Agriculture. The Wilderness is located in the Jefferson National
Forest.

VOLUME 4
HADSON POWER 14—BUENA VISTA 263
According to VDAPC, SCR has never been applied in circumstances
like Hadson Power’s, and to allow for contingencies that may result
from the application of this technology, the permit allows NOx emis-
sions of 0.25 lbs/10^6 Btu. Permit, Part I, Condition 20. The permit
also allows review of the NOx emission limit prior to initial issuance
of an operating permit and each renewal of such permit. Id.

These appeals followed.10 The numerous issues raised in this
appeal may be summarized as follows. First, several issues pertain
to the increment consumption analysis. SELC maintains that the
increment consumption analysis is faulty because of VDAPC’s policy
of excluding sources more than 100 km from a class I area. The
County contends that Hadson Power’s proposed emissions violate the
SO2 increment for the Park. In a related issue, SELC contends that
the notice of the public hearing on the draft permit was defective
because it did not include the predicted increment consumption at
the Park. CLEAR argues that emissions from the construction of
the proposed facility are required to be included in the air quality
analysis. Second, several issues pertain to VDAPC’s rejection of the
adverse impact determinations. SELC contends that VDAPC’s rejec-
tion of the FLMs’ adverse impact determinations is clear error under
In re Old Dominion Electric Cooperative, PSD Appeal No. 91-39
(Adm’r, Jan. 29, 1992). SELC and the County also contend that
VDAPC failed to seriously consider or directly address the FLMs’
specific determinations. Third, SELC asserts that the permit does
not reflect emission limits based upon BACT for NOx. Fourth, SELC
and the County contest the adequacy and reliability of the modeling
and air quality analysis submitted by Hadson Power in support of
its permit application. Lastly, the County and CLEAR argue that
the permit should not be issued until the National Park Service
completes its environmental review of a proposed easement linking
the proposed facility and Georgia Bonded Fibers.

ANALYSIS

I. Increment Consumption Analysis

The Clean Air Act requires all PSD permit applicants to show
that emissions from the proposed facility “will not cause, or contribute
to, air pollution in excess of any * * * maximum allowable increase

10 Although VDAPC rejected both FLMs’ findings, neither FLM sought review
of the final permit decision under § 124.19.

VOLUME 4
264 ENVIRONMENTAL ADMINISTRATIVE DECISIONS

      • for any pollutant.” CAA § 165(a)(3).1! As noted above, these
        maximum allowable increases are called “increments.” The Act also
        contains provisions which discuss the relationship between this re-
        quirement as it relates to class I areas and the affirmative respon-
        sibility of FLMs to protect the air quality-related values of such
        areas. Section 165(d)(2)(C), provides in part:

(ii) In any case where the Federal Land Manager

demonstrates to the satisfaction of the State that

the emissions from such facility will have an adverse

impact on the air quality-related values (including

visibility) of such lands, notwithstanding the fact

that the change in air quality resulting from emis-

sions from such facility will not cause or contribute

to concentrations which exceed the maximum allow-

able increases for a class I area, a permit shall not

be issued.

(iii) In any case where the owner or operator of such

facility demonstrates to the satisfaction of the Fed-

eral Land Manager, and the Federal Land Manager

so certifies, that the emissions from such facility will

have no adverse impact on the air quality-related

values of such lands (including visibility), notwith-

standing the fact that the change in air quality re-

sulting from emissions from such facility will cause

or contribute to concentrations which exceed the

maximum allowable increases for class I areas, the

State may issue a permit.
Thus, the increment analysis determines who has the burden of dem-
onstrating whether there is an adverse impact on air quality-related

11 Section 165(d)(2\C)(i) of the CAA also requires an increment consumption analy-

sis. It provides that when an FLM “files a notice alleging that emissions from a
proposed * * * facility may cause or contribute to a change in the air quality in
{a class I area], a permit shall not be issued unless the [applicant] demonstrates
that emissions of particulate matter and sulfur dioxide will not cause or contribute
to concentrations which exceed the maximum allowable increases for a class I area.”
SELC contends that the Park’s September 25, 1990 letter to VDAPC was notice
for the purposes of this section. SELC Petition at 24, n.14. In other words, SELC
contends that the Park FLM’s September 25, 1990 letter triggered an obligation for
Hadson Power to perform an increment analysis. We cannot address this issue, as
the September 25, 1990 letter is not in the record before us. In any event, Hadson
Power was required to perform an increment consumption analysis under CAA
§ 165(a)(3), and there has been no showing that this analysis would have been any
different if performed pursuant to CAA § 165(d)(2)(C)(i).
VOLUME 4
HADSON POWER 14—BUENA VISTA 265
values and to whose satisfaction the demonstration must be made.
If the analysis demonstrates an increment violation, the applicant
bears the burden of demonstrating that the proposed facility will
not have an adverse impact. If an increment violation is not estab-
lished, the FLM bears the burden of demonstrating that the proposed
facility will have an adverse impact.

VDAPC policy is “that sources beyond 100 kilometers from class
I areas do not consume increment.” Response to SELC Petition at

  1. Therefore, “[i]t has been the consistent policy of the VDAPC to
    require analyses of the cumulative impact due to appropriate class
    I increment-consuming sources within 100 km of either of the two
    class I areas in Virginia.” Id. Hadson Power performed an increment
    consumption analysis consistent with VDAPC policy. SELC contends
    that this policy, by excluding sources beyond 100 km, fails to consider
    all increment-consuming sources. SELC represents that both the
    VDAPC and FLMs agree that a substantial portion of the air pollu-
    tion problem at the two class I areas results from transport from
    sources more than 100 km away from those areas, and SELC asserts
    that some of those sources clearly consume class I increment. SELC
    Petition at 24-25. According to SELC, Hadson Power cannot dem-
    onstrate whether it will violate an increment without considering
    these sources, and therefore VDAPC clearly erred in issuing the per-
    mit based on this allegedly incomplete increment analysis.

SELC disputes VDAPC’s assertion that its policy is consistent
with the limitations of air quality modeling and exceeds the require-
ments of many other states. SELC lists a few states that it says
routinely model increment-consuming sources beyond 100 km. SELC
argues that VDAPC’s “categorical determination that sources beyond
100 km are not class I increment-consuming sources is clearly illegal
and contrary to EPA policy.” SELC Petition at 25.

VDAPC explains and defends its policy as follows:

The DAPC policy that sources beyond 100 kilometers
from Class I areas do not consume increment is not
contrary to law and policy. It has been the consistent
policy of the VDAPC to require analyses of the cumu-
lative impact due to appropriate Class I increment-
consuming sources within 100 km of either of the
two Class I areas in Virginia. This is done using
EPA-approved models and techniques. The models
used are widely understood by experts in the field
to overpredict pollutant concentrations at great dis-
VOLUME 4
266 ENVIRONMENTAL ADMINISTRATIVE DECISIONS
tances (in excess of 50 km). It is the VDAPC’s opin-
ion that cumulative Class I impact analyses should
be restricted to increment consuming sources within
100 km of Class I areas. The above-described policy
was carefully designed to be conservative, that is,
designed to overestimate increment consumption in
order to provide as much protection of the Class I
increment as is reasonable.

Response to SELC Petition at 8.

Both SELC and VDAPC discuss the Administrator’s recent deci-
sion in Old Dominion, supra. In that case, petitioners (including
SELC) challenged a permit issued by VDAPC to Old Dominion be-
cause, among other reasons, Old Dominion did not perform an incre-
ment analysis relative to impacts at the Park. Old Dominion will
be located approximately 135 km from the Park’s nearest boundary.
VDAPC indicated that no demonstration was required since its policy
is to require a class I increment analysis only for sources proposing
to locate within 100 km of a class I area. In upholding VDAPC’s
action, the Administrator noted that the demonstration at the Wilder-
ness, which is closer to Old Dominion’s proposed location and there-
fore potentially subject to even greater adverse impacts, showed that
class I increments would not be violated there. The Administrator
also mentioned as a consideration “that EPA has not issued any
final guidance that would contravene the State’s policy.” Old Domin-
ion, unpub. op. at 6. In a footnote to this statement, the Adminis-
trator said:

Draft guidance released by EPA in October 1990 and
distributed to the States recommends analysis be-
yond 100 kilometers when there are potential im-
pacts on a class I area. While this guidance has
not yet become final, it reflects EPA’s concern that
increments analysis include class I areas when there
are reasonable questions about a proposed facility’s
impacts on such areas. As a draft policy, however,
it does not have the same weight as a binding Agen-
cy position and does not prohibit the States from
adopting their own policies that are consistent with
the Clean Air Act and applicable regulations. Never-
theless, EPA’s draft policy reflects the Agency’s latest
thinking on when it is appropriate to require incre-
ment analyses for class I areas, and is based upon
the availability and feasibility of modeling tools for
VOLUME 4
HADSON POWER 14—BUENA VISTA 267
assessing such impacts. For this reason, Virginia
should consider reexamining its current policy.
Old Dominion, unpub. op. at n.6.

SELC, in its petition, focuses on the Administrator’s advice to
Virginia to reexamine its current policy. VDAPC, on the other hand,
focuses on the statement that as a draft policy, the 1990 draft guid-
ance does not have the same weight as a binding Agency position
and does not prohibit states from adopting their own policies consist-
ent with the Act and implementing regulations.

The issue presented in Old Dominion was somewhat different
than the issue presented here. In Old Dominion, the issue was wheth-
er a proposed source more than 100 km from a class I area needed
to do an increment analysis. Here, the issue is whether, when a
proposed source locating within 100 km of a class I area does its
increment analysis, it must consider other sources more than 100
km from the class I area. However, the underlying technical issues,
relating to the likelihood of a substantial impact on a class I area
of a source more than 100 km away and the accuracy of modeling
at such distances, are essentially the same.

We find the Old Dominion decision conclusive as to the effect
of the 1990 draft guidance, which continues to remain in draft form.
For the reasons stated in the footnote in Old Dominion previously
quoted, the draft guidance does not provide a basis for overturning
the state’s action.

However, SELC also argues that the VDAPC policy is contrary
to current EPA policy, not just the draft guidance discussed in Old
Dominion. In support of its position, SELC quotes from three docu-
ments.

The first document cited is the preamble to the 1978 PSD regula-
tions. In discussing comments received on the “Guideline on Air Qual-
ity Models,” one issue identified was whether the modeled estimate
of source impact should be limited to a certain distance or a minimum
numerical impact or both. In addressing this issue, the document
says:

[T]he Administrator intends to limit generally the

application of air quality models to a downwind dis-

tance of no more than 50 kilometers. This is because

dispersion parameters commonly in use are based
VOLUME 4
268 ENVIRONMENTAL ADMINISTRATIVE DECISIONS
on experiments relatively close to sources, and ex-
tending these parameters to long downwind distances
results in great uncertainty as to the accuracy of
the model estimates at such distances. Also, since
the air quality impact of many sources falls off rap-
idly to insignificant levels, EPA does not intend to
analyze the impact of a source beyond the point
where the concentrations from the source fall below
certain levels (which are generally based on the
Class I increments).

43 Fed. Reg. 26,398 (June 19, 1978).

The preamble then states, in the language cited by SELC:
However, since the 1977 Amendments provide special
concern for Class I areas, any reasonably expected
impacts for these areas must be considered irrespec-
tive of the 50 kilometer limitation or the above sig-
nificance levels.

Id.

A second document cited by SELC is EPA’s “Guideline on Air
Quality Models,” revised as of July 1986, which states at pages 7—
8 that “[slince in many cases Class I areas may be threatened at
distances greater than 50 km from new sources,” some procedure
is needed to determine if a significant impact will occur and identify
the model to be used in such cases.

Finally, SELC quotes from a 1979 memorandum 12 which con-
tains the following sentences: “Very large sources, however, may be
expected to affect ‘air quality related values’ at distances greater
than 100 kilometers. The appropriate Federal Land Manager should
be notified if such impacts are expected on a case by case basis.”
SELC reasons that if the FLM is to be notified, the potential impact
of these sources should be assessed through modeling.

VDAPC, in its response to SELC’s petition, does not address
the interpretation or significance of any of these documents but relies
solely on the rationale for its policy as previously discussed, the
lack of binding effect of the 1990 draft guidance, the fact that the

12Memorandum from David G. Hawkins, Assistant Administrator for Air, Noise,
and Radiation to Regional Administrators (Mar. 19, 1979) (entitled “Notification to
Federal Land Manager Under Section 165(d) of the Clean Air Act”).

VOLUME 4
HADSON POWER 14—BUENA VISTA 269
analysis here was consistent with that of several other sources re-
cently permitted in Virginia none of whose permits were remanded,
and that neither FLM petitioned for review of the permit.}%

We find that the documents cited by SELC do not clearly estab-
lish a requirement to model sources beyond 100 km. The 1978 Fed-
eral Register does evidence that EPA intended the air quality analy-
sis for class I areas to extend to “any reasonably expected impacts”
without regard to the 50 km limit otherwise applicable. However,
this preamble language is not self-executing and has to be viewed
in light of subsequently developed policy and Agency practice.

EPA’s most current “Guideline on Air Quality Models” is the
July 1986 revision (supplemented in 1987), which at Section 7.2.6.
states:

Since in many cases Class I areas may be threatened

at distances greater than 50 km from sources, some

procedure is needed to determine (1) if a significant

impact will occur, and (2) identify the model to be

used in setting an emission limit if the Class I incre-

ments are threatened (models for this purpose should

be approved for use on a case-by-case basis as re-

quired in Section 3.2). This procedure and the models

selected for use should be determined in consultation

with the EPA Regional Office and the appropriate

FLM.
While this guideline recognizes the potential threat to air quality
from sources beyond 50 km, it only requires that a procedure and
models be established in consultation with the EPA Regional Office
and the appropriate FLM.

Region III, while encouraging the state to consider revising its
policy, nonetheless appears to have accepted Virginia’s policy relative
to increment analysis as consistent with current federal law and
EPA policy.14 We note that in the Region’s comments on the Hadson

13 Concerning this last argument, see infra note 27.

M4This is consistent with the Administrator's statement in Old Dominion that
“EPA has not issued any final guidance that would contravene the State’s policy.”
Old Dominion, unpub. op. at 6. .

VOLUME 4
270 ENVIRONMENTAL ADMINISTRATIVE DECISIONS

Power draft permit,!5 the Region did not raise any objection to the
state’s increment analysis. There were extensive discussions between
the Region and Virginia on modeling issues yet it does not appear
that the Region objected to the application of Virginia’s policy.'®
Under those circumstances, VDAPC satisfied its obligation under cur-
rent policy of consulting with the EPA Regional Office regarding
the development of procedures and models for considering sources
beyond 50 km.?7

Finally, while the 1979 memorandum recognizes that very large
sources more distant than 100 km can affect AQRVs, this memoran-
dum is focused on the process for notifying FLMs and cannot by
itself be interpreted as requiring inclusion of such sources in the
increment analysis.

We recognize that Hadson Power did conduct increment consump-
tion modeling including sources far more than 100 km from the
northern part of the Park.18 This does not change our analysis. The
fact that a permittee goes beyond the minimum requirements of
VDAPC policy does not in any way invalidate an otherwise acceptable
policy. Indeed, it would be poor public policy to create such a strong
disincentive for going beyond minimum requirements.

Having determined that Virginia policy does not contravene cur-
rent Agency policy, we would strongly reiterate the Administrator’s
suggestion that Virginia reexamine its current policy, in light of the
potentially serious consequences to air quality of its exclusion policy.
We would similarly urge the Agency to move expeditiously to issue
its final guidance addressing this concern, which the state, as the
Agency’s delegatee, will be constrained to follow.

The County contends that even excluding sources beyond 100
km, Hadson Power’s modeling showed it would contribute to viola-

15Letter from Bernard E. Turlinski, Chief, Air Enforcement Branch, Region III
to Wallace N. Davis, Executive Director, VDAPC (Jan. 31, 1992), Response to Petitions,
Attachment VII.

16 See Response to Petitions, Attachment VII.

17The record is less clear as to VDAPC’s consultation with the FLMs. We note,
however, that this is the most recent in a series of PSD permits issued by VDAPC
for sources impacting these class I areas. Through the course of these permit proceed-
ings, the FLMs have presented their positions to, and engaged in a dialogue with,
VDAPC.

18Tt is not alleged that sources beyond 100 km were included in the increment
consumption analyses for the southern portion of the Park or for the Wilderness.
As noted above, VDAPC concluded that Hadson Power would not violate any increment
in either the northern or southern portions of the Park or in the Wilderness.

VOLUME 4
HADSON POWER 14—BUENA VISTA 271
tions of the class I three-hour increment for SO2 in the Park, and
therefore the permit should not have been issued. Specifically, the
County contends that the allowable three-hour SO2 increment for
the Park is 25 pg/m3, and that Hadson Power’s modeling showed
that it will consume 32.1 yg/m3.

VDAPC does not contest that Hadson Power’s preliminary model-
ing predicted increment violations in the Park. VDAPC concluded,
however, that the violations are due primarily to two previously per-
mitted but not yet constructed sources, not Hadson Power, and that
Hadson Power would contribute only a small amount to these viola-
tions. Hadson Power requested and received approval from VDAPC
(and EPA) to conduct modeling with different meteorological data.19
In addition, because significance levels for class I increment consump-
tion had not been established by EPA, VDAPC proposed, and EPA
approved, that for this permit, the class I significance levels be pro-
portional to those used for class II areas.2° Based on this analysis,
VDAPC concluded that Hadson Power would not contribute signifi-
cantly to the violation. The County has not demonstrated that this
conclusion is in error.

In another issue related to the increment analysis, SELC argues
that the public notice of the hearing on the draft permit was defective
because it failed to include the predicted amount of increment con-
sumption in the Park. (The notice did provide the amount for the
Wilderness.) VDAPC regulations require that the public notice state
“the degree of increment consumption that is expected from the
source.” Virginia Air Pollution Control Regulations § 102—08-
02(R)(2\c). VDAPC, which does not deny the omission, responds that
the public notice was not defective because it presented the worst-
case class I increment consumption expected from Hadson Power's
emissions. This worst-case consumption was expected in the Wilder-
ness, not the Park. According to VDAPC, the “degree of increment
consumption that is expected” does not require numerous increment

19 See VDAPC Memo. at 5—4, which states:

EPA policy normally requires that the applicant (Hadson-14) must
use its own meteorological data in assessing the effects of multiple
sources. When Hadson modeled Coors [another increment-consum-
ing source] * * * emissions using Buena Vista meteorological
data, increment violations were * * * predicted. In June 1991
[VDAPC] proposed to EPA that Hadson be allowed to use meteoro-
logical data most appropriate to each region of [the Park]; in
August 1991, EPA agreed to let Hadson model Coors with Coors
meteorological data, and the increment violation was resolved.

20 See supra note 5.

VOLUME 4
272 ENVIRONMENTAL ADMINISTRATIVE DECISIONS

consumption values at various receptors, only the maximum incre-
ment consumed. In addition, VDAPC notes that the actual figures
were sent to the FLMs and made available at the VDAPC Roanoke
office and at local public libraries in Buena Vista and Lexington.

We find the VDAPC’s explanation unpersuasive. The Clean Air
Act requires meaningful public participation in the PSD permitting
process. Section 165(a)(2) requires a public hearing allowing for inter-
ested persons “to appear and submit written and oral presentations
on the air quality impact of such source, alternatives thereto, control
technology requirements, and other appropriate considerations.” In
implementing this provision, the Agency regulations defining the re-
quirements for state PSD plans require the reviewing authority to:

Notify the public, by advertisement in a newspaper

of general circulation in each region in which the

proposed source would be constructed, of the applica-

tion, the preliminary determination, the degree of in-

crement consumption that is expected from the source

or modification, and of the opportunity for comment

at a public hearing as well as written public com-

ment.
40 C.F.R. § 51.166(q)(2)(iii) (emphasis added). The state regulation
cited by SELC is identical to this federal regulation.

To allow for meaningful comment, the public must be apprised
of all of the proposed source’s increment consumption as determined
through the modeling analysis. We do not believe that the phrase
“degree of increment consumption” can be read as allowing for provid-
ing data at only one location, albeit the one with the greatest pro-
jected consumption. Different potential commenters may have an in-
terest in different areas to be impacted and would want, and would
reasonably be entitled to, available data on increment consumption
at the area of their particular concern. Otherwise, their ability to
comment on the air quality impact and proposed alternatives would
be severely limited. While VDAPC indicates that such data were
made available at designated locations within the vicinity of the
proposed plant, the regulation specifically requires these data to be
in the public notice. VDAPC will be required to provide a new public
notice in response to the remand ordered by this decision, and such
notice should detail all of the increment to be consumed by the
proposed source, including any increment consumed at the Park.
VOLUME 4
HADSON POWER 14—BUENA VISTA 273

Finally, CLEAR objects to the permit on the grounds that Hadson
Power failed to include emissions from the construction of the pro-
posed facility in its demonstration that neither a national ambient
air quality standard or an increment will be exceeded. According
to CLEAR, inclusion of construction emissions is required by the .
Clean Air Act and federal and state regulations.

CLEAR cites section 165(a)(3) of the Clean Air Act, which pro-
vides that no major emitting facility may be constructed unless “the
owner or operator of such facility demonstrates * * * that emissions
from construction or operation of such facility will not cause or con-
tribute to air pollution in excess of [any applicable PSD increment
or national ambient air quality standard.]” (Emphasis added.) CLEAR
also cites Virginia Air Pollution Control Regulations sections 120-
08—02(L) and (B)(3), which respectively require the air quality dem-
onstrations to include “secondary emissions” and define “secondary
emissions” as “emissions which would occur as a result of the con-
struction or operation of a major stationary source * * * but do
not come from the major stationary source * * * itself.” In addition,
CLEAR points to the Clean Air Act’s prohibition of construction,
rather than just operation, prior to permit issuance as additional
authority.

VDAPC, in its response, states that “[t]here is no requirement
to include construction site emissions associated with the proposed
source in its air quality analysis.” Response to CLEAR Petition 1.
VDAPC further states:

In addition, the secondary emissions must be specific,
well-defined and quantifiable. Likewise, temporary
emissions, such as those from construction, would
have to be quantifiable to be included in any dem-
onstration of impact. EPA guidance does not include
any suggested methodology to quantify emissions
from the temporary construction phase.
Id.

Despite VDAPC’s rather categorical statement that there is no
requirement to include construction emissions in the air quality anal-
ysis, such emissions generally must be considered. In addition to
the language of section 165(a)(3) itself, this is clearly demonstrated
by the inclusion of a provision in the PSD regulations allowing, upon
written request of a governor, the Administrator to exclude from
the increment analysis “concentrations of particulate matter attrib-

VOLUME 4
274 ENVIRONMENTAL ADMINISTRATIVE DECISIONS

utable to the increase in emissions from construction or other tem-
porary emission-related activities of new or modified sources.” 40
C.F.R. §52.21(f)(3). There would be no reason to include a provision
relating to the exclusion of construction emissions unless they were
otherwise included.?1

The obligation to consider construction emissions was also clearly
articulated in Save the Valley, Inc. v. Ruckelshaus, 565 F. Supp.
709, 710 (D. D.C. 1983) (“Pursuant to the plain language of the
statute and its obvious intent to regulate pollution attendant to con-
struction * * *.”). Thus, VDAPC was in error in citing as a basis
for exclusion of construction emissions the absence of any legal obliga-
tion to consider them.

It is possible that the construction emissions will be in whole
or in part fugitive in nature.22 To the extent this is the case, fugitive
emissions must be included only if quantifiable.28 VDAPC asserts
that there is no methodology for quantifying construction emissions.
However, in the absence of a detailing of what the construction emis-
sions are expected to be, it is not possible to determine whether
construction emissions at Hadson Power can be properly excluded
on this basis.

In addition, 40 C.F.R. § 52.21(i)(6) provides as follows:

The requirements of paragraphs (k), (m) and (0) of
this section [relating to source impact analysis, air
quality analysis, and additional impact analysis]
shall not apply to a major stationary source or major

21] is unclear whether this potential exclusion could be available here. The pre-
amble to the promulgation of this provision indicates that it is applicable only where
the state has a fully approved PSD program. See 45 Fed. Reg. 52,719 (Aug. 7, 1980).
However, the regulation on its face is not so limited. In any event, there clearly
has been no request from the governor, the prerequisite to invoking this provision.

22“Fugitive emissions” are defined as “those emissions which could not reasonably
pass through a stack, chimney, vent or other functionally equivalent opening.” 40
C.F.R. §52.21(b)(20).

23 See New Source Review Workshop Manual at c.47 (Draft, Oct. 1990) (restating
current policy that “[t]he applicant must also include any quantifiable fugitive emis-
sions from the proposed source or any nearby sources”) (emphasis added). We note
that VDAPC also argues that “secondary emissions” must be quantifiable but we
do not believe these emissions would necessarily be secondary as opposed to primary.
Secondary emissions are those “which would occur as a result of the construction
or operation of a major stationary source * * * but do not come from the major
stationary source * * * itself.” 40 C.F.R. §52.21(b)(20). Here, presumably much of
the emissions would come from the construction of the facility itself.

VOLUME 4
HADSON POWER 14—BUENA VISTA 275
modification with respect to a particular pollutant,
if the allowable emissions of that pollutant from the
source, or the net emissions increase of that pollut-
ant from the modification:
(i) Would impact no Class I area and no area
where an applicable increment is known to be vio-
lated, and
(ii) Would be temporary.
Construction emissions can be considered temporary. It is possible
that because construction emissions are predominately of particulate
matter and there have been no concerns about particulate matter
impacts raised in this appeal, this provision might be applicable.
However, in the absence of a clear description of proposed construc-
tion emissions and how this provision might apply, we cannot sustain
VDAPC’s action based on speculation as to the possible applicability
of this provision.

VDAPC’s exclusion of construction emissions based on its
misreading of its legal obligations, and its generalized assertion that
such emissions must be and cannot be quantified, cannot be sus-
tained. VDAPC, on remand, must supplement the record with a full
description of anticipated construction emissions and must either in-
clude those emissions in its air quality analysis, or show why they
can be properly excluded.

II. Adverse Impact Determinations
A. Legal Background

The Clean Air Act contemplates an active role for FLMs in the
PSD permitting process. An FLM is entitled to notice of a proposed
PSD permit if emissions from the proposed source may affect the
FLM’s class I area. CAA § 165(d)(2)(A). The FLM has an “affirmative
responsibility to protect” the AQRVs in the class I area. CAA
§ 165(d)(2)(B). The FLM does this by determining whether the emis-
sions from the proposed source will have an adverse impact on the
AQRVs in the class I area.?4

24 As explained with reference to the increment consumption analysis arguments,
the FLM will have to either establish the existence of an adverse impact or certify
its absence, depending upon who bears the burden of proof on this issue. See CAA
§§ 165(d)(2)(C)(ii) and (iii).

VOLUME 4
276 ENVIRONMENTAL ADMINISTRATIVE DECISIONS

As noted above, the outcome of the increment consumption analy-
sis establishes who bears the burden of proving the presence or
absence of an adverse impact. According to VDAPC, the increment
consumption analysis in this case indicates that Hadson Power's pro-
posed emissions will not cause or significantly contribute to an incre-
ment violation. Therefore, in this case, the FLMs bear the burden
of demonstrating an adverse impact.25 Under the applicable Clean
Air Act provision, if the FLM demonstrates to the satisfaction of
the state26 that emissions from the proposed source will have an
adverse impact on the AQRVs in the class I area, the permit shall
not be issued. CAA § 165(d)(2)(C)(ii).

States do not have unfettered discretion to reject an FLM’s ad-
verse impact determination. Old Dominion, unpub. op. at n.9. If a
state determines that an FLM has not satisfactorily demonstrated
an adverse impact on AQRVs from the proposed facility, the state
must provide a “rational basis” for such a conclusion, “given the
FLMs’ affirmative responsibility and expertise regarding the Class
I areas within their jurisdiction.” 50 Fed. Reg. 28,549 (July 12, 1985).
Arbitrary and capricious rejections of adverse impact determinations
are not sustainable. Old Dominion, unpub. op. at n.9.

B. The Wilderness

The Wilderness FLM identified water quality as the AQRV that
would be adversely impacted by Hadson Power’s proposed emissions.
Specifically, the Wilderness FLM concluded that based on Hadson
Power’s modeling, the proposed facility’s projected emissions will in-
crease SO2 concentrations in the Wilderness by two to three percent,
which in turn will produce a 0.01 unit decrease in pH and a 1
ueq/l decrease in acid neutralizing capacity (ANC) in the Wilderness’
streams, which are already sensitive to acidification. Wilderness AID
at 4. These consequences will be particularly adverse in Belfast

25 As previously stated, this permit is being remanded for VDAPC to determine
whether construction emissions must be included in the air quality analysis. If VDAPC
determines that they must be, and if the results of the increment consumption analysis
show that the proposed facility will cause or significantly contribute to an increment
violation, Hadson Power will assume the burden of demonstrating to the FLMs the
absence of an adverse impact.

26 Because EPA is the final permitting authority for the Hadson Power facility,
notwithstanding the delegation to Virginia, it is ultimately EPA’s “satisfaction” with
the FLM’s finding that is at issue. See Citizens for Clean Air v. EPA, 959 F.2d
839 (9th Cir. 1992) (in reviewing PSD permit issued by delegated state, court focused
not on the state action but instead on EPA—whether Agency's final decision, in an
administrative appeal under 40 C.F.R. § 124.19, allowing the permit to issue was
reasonable).

VOLUME 4
HADSON POWER 14—BUENA VISTA 277
Creek, a primary stream in the Wilderness identified by Forest Serv-
ice screening criteria as having very high acid levels and thus unable
to tolerate additional sulfur loading. Id. at 5.

VDAPC rejected the Wilderness FLM’s adverse impact deter-
mination because the FLM “provided no definitive data as to the
specific effects that a small change in sulfur deposition, acid neutral-
izing capacity, and pH units will have on the streams” in the Wilder-
ness. VDAPC Memo. at 5-13, 5-86. In addition, VDAPC expressed
its “uncertainty” about some assumptions used in the adverse impact
analysis. Id. at 5-88. The only assumption VDAPC singled out is
the FLM’s assumption that “all dry/SO2 deposited was converted to
sulfate which affects the acid neutralizing capacity of the soil.” Id.

VDAPC also rejected the Wilderness FLM’s adverse impact deter-
mination on the ground that the Forest Service criteria for determin-
ing adverse impacts are inadequate because they fail to “include
a scientifically accepted minimum impact below which a specific
source’s contribution would be considered insignificant. This is a long-
standing fundamental principle of federal and state PSD * * * per-
mitting policies and procedures.” VDAPC Memo. at 5-88. VDAPC
further stated that it cannot accept “the notion that ’any’ emission
increase and subsequent increase in pollutant deposition is an accept-
able demonstration of adverse impact.” Id.

On appeal, SELC contends that VDAPC rejected the Wilderness
FLM’s quantified adverse impact finding without responding specifi-
cally to it. SELC asserts that because water quality is the AQRV
of concern, the FLM need not, as VDAPC would require, demonstrate
more than an adverse impact on water quality. In other words, SELC
argues that having demonstrated an adverse impact on water quality,
the FLM need not go any further and demonstrate the effects of
that adverse impact on water quality. SELC Petition at 3—4. In addi-
tion, SELC states that VDAPC did not explain how or why the
FLM’s assumption on sulfur deposition invalidated the adverse im-
pact determination. Id. at 5-6.

SELC notes that instead of addressing the demonstration of ad-
verse impact, VDAPC flatly stated that it cannot accept the notion
that any increase in pollutant deposition demonstrates adverse im-
pact. SELC contends the Wilderness FLM specifically quantified the
adverse impact, and thus does not base her determination on the
assumption that “any” emission increase produces an adverse impact.
SELC Petition at 2-7. SELC further contends that Old Dominion
plainly rejected VDAPC’s position that de minimis criteria are re-

VOLUME 4
278 ENVIRONMENTAL ADMINISTRATIVE DECISIONS

quired for evaluating an adverse impact determination. Id. at 11-

  1. In sum, SELC contends that VDAPC erroneously failed to con-
    sider the FLM’s conclusions. Similarly, the County contends that
    VDAPC did not seriously consider the adverse impact determinations.
    VDAPC responds without reference to Old Dominion by merely re-
    peating its responses to the comments on the draft permit.?’

We conclude that VDAPC clearly erred by failing to consider
the merits of the specific quantified adverse impact demonstration
submitted by the Wilderness FLM. Although VDAPC attempts to
use much of the same reasoning it employed in Old Dominion, we
conclude that the facts of this case require a different outcome.

In Old Dominion, as in this case, the Wilderness FLM predicted
an adverse impact on water quality, namely, that the proposed emis-
sions would produce a two to nine percent decrease in ANC and
pH in the Wilderness’ streams.28 VDAPC rejected this finding, identi-
fying several reasons why the FLM may have overestimated the
impact of the proposed emissions.29 VDAPC also relied upon the
absence of guidance as to significance or de minimis levels for deter-
mining adverse impacts as a basis for rejecting the Wilderness FLM’s
finding. The Administrator plainly rejected this reasoning, stating
“[njational guidance on de minimis impacts for class I air quality
related values is in no way a prerequisite to a reasonable determina-
tion by a permit-issuing authority that the [FLM] has demonstrated
a proposed source will have adverse impacts.” Old Dominion, unpub.
op. at n.20.

27In addition, VDAPC repeatedly notes (here and with reference to other argu-
ments) that neither FLM petitioned for review of the final permit decision. Although
VDAPC does not indicate why this fact is relevant, we assume VDAPC believes that
the absence of a petition by the FLMs demonstrates acquiescence to issuance of
the final permit. We disagree with the inference made by VDAPC from the FLMs’
failure to file a petition. Neither adverse impact determination has been withdrawn.
Indeed, after the final permit was issued, the Wilderness FLM reiterated her concerns
expressed in the adverse impact determination. SELC Reply, App. 7. There are many
possible considerations that may affect a FLM’s decision whether to file a petition
for review, and speculation as to those reasons is not productive. Therefore, we find
it irrelevant that neither FLM petitioned for review of the permit.

28Thus, in Old Dominion, there was no dispute that the Wilderness FLM quan-
tified the adverse impact. Instead, the issue was whether this quantified, adverse
impact was credible, and VDAPC concluded it was not.

29In sum, these reasons were that the FLM did not supply its calculations until
after the public comment period, that modeling conducted by the EPA (RELMAP)
showed pollutant deposition one-tenth of that estimated by the FLM, and that another
Region had questioned a similar analysis in another case. Old Dominion, unpub.
op. at 12.

VOLUME 4
HADSON POWER 14—BUENA VISTA 279

VDAPC’s reliance in this case upon the reasoning plainly rejected
in Old Dominion is clearly erroneous. VDAPC has not pointed to,
and we have not found, any authority to indicate that national stand-
ards, including a minimum standard, for assessing adverse impacts
are a “long-standing fundamental principle” of PSD permitting proce-
dures. The only authority on this issue, Old Dominion, unequivocally
indicates the opposite.

In describing its reasons for rejecting the Wilderness FLM’s ad-
verse impact determination, VDAPC stated that it “cannot accept
the notion that ‘any’ emission increase * * * is an acceptable dem-
onstration of adverse impact.” VDAPC Memo. at 5-88. The Wilder-
ness FLM, however, does not base her adverse impact determination
on “any” emission increase, but on the projected impact of a two
to three percent increase in SO2 concentrations that will result from
Hadson Power’s proposed emissions. VDAPC’s reasoning seems to
ignore this fact, which distinguishes this case from the Park FLM’s
adverse impact determination in Old Dominion, where the determina-
tion rested on the unproven assumption that any emissions from
the proposed facility would have an adverse impact. Old Dominion,
unpub. op. at 14.

The Forest Service has developed criteria for assessing adverse
impacts, which are detailed in the Wilderness AID. While VDAPC
has the discretion to accept or reject an adverse impact determination
founded on those criteria, it must provide a rational basis for doing
so and cannot summarily reject the determination because the criteria
do not contain a de minimis impact or significance level that is
not required by law. VDAPC’s approach of summarily rejecting an
adverse impact determination because of the lack of such guidance
or criteria is an abdication of its responsibility to assess an adverse
impact determination,2° and as such eviscerates some of the class
I area protection provided by the Clean Air Act.

In Old Dominion, VDAPC’s reliance on invalid reasoning was
harmless error because VDAPC also relied upon other reasonable
grounds for rejecting the adverse impact determination, namely that
the FLM overestimated the impact of the proposed emissions. Here,
unlike the situation in Old Dominion, VDAPC has not presented
any other reasonable basis for rejecting the Wilderness AID.31

30 See Old Dominion, unpub. op. at 13.

31With respect to the specific grounds relied upon in Old Dominion, (see supra
note 29), the only one raised in this case concerns the use of RELMAP. SELC argues,
and VDAPC agrees, that RELMAP is irrelevant on this issue owing to the proximity

Continued
VOLUME 4
280 ENVIRONMENTAL ADMINISTRATIVE DECISIONS
VDAPC asserts that the Wilderness AID was inadequate because
it failed to provide “definitive data as to the specific change that
a small change in sulfur deposition, [ANC] and pH units will have
on the streams” in the Wilderness. VDAPC Memo. at 5-86. This
statement, as SELC correctly notes, fails to acknowledge that water
quality is the AQRV of concern. The FLM is required only to state
the impact on the AQRV, and demonstrate that it is adverse. In
this case, the FLM identified and quantified the impact on the AQRV
of concern, water quality, by showing that the proposed emissions
would increase acidification by producing a 0.01 unit decrease in
pH and a 1 uegq/ decrease in ANC. In addition, the FLM qualitatively
described why this impact is adverse by indicating that streams in
the Wilderness are already acid sensitive and that increases in acidi-
fication could reasonably be expected to produce a shift towards more
acid tolerant species. VDAPC apparently would require an FLM to
quantify the adversity produced by an impact on an AQRV, for exam-
ple, by quantifying the degree of shift to more acid tolerant species.
This would impose a requirement not found in the Clean Air Act.
See CAA § 165(d)(2)(C)(ii). Therefore, VDAPC erred in rejecting the
Wilderness AID on this ground.
VDAPC also expresses an “uncertainty” about some assumptions
the Wilderness FLM relied upon. VDAPC specifically mentions only
one assumption, that “all dry deposited SO2 was converted to sulfate,”
which affects acidification, and summarily states that this assumption
“increases the likelihood that the analysis may overestimate the pH
unit change as calculated in the * * * adverse impact determination.”
VDAPC Memo. at 5-88. VDAPC, however, failed to detail why this
assumption was in error and how it would lead to overestimation.”
VDAPC does not provide an alternative or preferable assumption.
This is in stark contrast to the scenario in Old Dominion, where
Agency modeling confirmed that the FLM overestimated impacts.
For these reasons, we conclude that VDAPC clearly erred by
relying on reasoning rejected in Old Dominion and failing to consider
the merits of the adverse impact determination as required. Because
the record shows that VDAPC did not have any other clear, support-
able rationale for rejecting the Wilderness AID, the error is not harm-
less. Consequently, we remand this permit to VDAPC for reconsider-
of the proposed source and the Wilderness. In addition, VDAPC states that even
though RELMAP has been used for other permits, its results were “inconclusive and
not a major factor” in this case. Response to SELC Petition at 7.
32VDAPC also failed to respond to evidence provided with the petition that the
assumption is a valid one. See SELC Petition, Attachments F and G.
VOLUME 4
HADSON POWER 14—BUENA VISTA 281
ation of the merits of the Wilderness FLM’s adverse impact deter-
mination in accordance with this opinion.

SELC raises other issues in its petition that may reappear in
the remand proceedings, and therefore we will briefly address them
here. SELC contends that VDAPC’s failure to consider the cumulative
impact of all previously permitted sources on the class I areas is
clear error. SELC relies upon the statement in Old Dominion that
“in determining whether a proposed source will cause an adverse
impact on visibility, the cumulative visibility impacts of the pending
PSD applicant and all PSD-permitted sources, including those not
yet constructed, must be assessed.” Old Dominion, unpub. op. at
n.24,33 SELC contends that VDAPC failed to meet this requirement
because it did not include in the cumulative analysis previously per-
mitted sources beyond 100 km of the class I areas. These sources
were not included because they were not included in Hadson Power’s
increment modeling.

VDAPC responds by referring to its increment consumption anal-
ysis, noting that “it has worked to develop policies and procedures
designed to ensure consistency and protection of Class I increment.”
Response to SELC Petition at 4 (emphasis added). VDAPC further
responds that its consistent policy has been to “require analyses
of the cumulative impact due to appropriate class 1 increment-con-
suming sources within 100 km of” the Wilderness. Id. (Emphasis
added.)

We find VDAPC’s reference to the increment consumption analy-
sis unresponsive to the issue of adverse impact analysis, which, as
the Clean Air Act makes plain, is separate.24 The increment consump-
tion analysis focuses on whether and to what extent the proposed
source will consume any of the available increment. An adverse im-
pact, which may exist even if no increment is violated, see CAA
§ 165(d)(2)(C)(ii), focuses on broader concerns, namely, whether emis-
sions from the proposed source will have an adverse impact on
AQRVs such as visibility or vegetation.

VDAPC’s response indicates that no sources beyond 100 km of
the class I areas were included in the cumulative impact analysis.

33In Old Dominion, other PSD permitted sources were examined for their cumu-
lative impact on visibility. SELC argues, and we agree, that non-visibility AQRVs
should be similarly assessed.

34Indeed, VDAPC relies upon this distinction in its argument that the Park AID
was properly rejected because class I increment significance levels are not relevant
to adverse impact determinations.

VOLUME 4
282 ENVIRONMENTAL ADMINISTRATIVE DECISIONS

Unlike VDAPC’s policy for increment consumption, however, there
is no 100 km cut-off for requiring an adverse impact determination.
See CAA § 165(d)(2)(C)(ii). See also, Old Dominion (adverse impact
determination submitted for Park, 1385 km from facility). VDAPC’s
response indicates that it also did not consider any non-increment-
consuming source within 100 km of the class I areas, even though
such sources, if they exist, may contribute to an adverse impact
on the class I areas. Accordingly, we conclude that based on the
record before us, it is not clear that VDAPC conducted separate
increment consumption and adverse impact analyses. When assessing
the adverse impact determinations on remand, VDAPC is required
to consider the cumulative impact of all previously permitted PSD
sources on the class I area.*5

SELC also asserts that VDAPC erroneously rejected the role
of episodic deposition of sulfur (as the result of storms) in causing
an adverse impact. VDAPC responds that the FLM did not quantify
the impact of such episodic deposition. SELC replies that quantifica-
tion is not required because the adverse impact is quantified and
it is “well accepted” that episodic deposition will exacerbate the ad-
verse impact. SELC Petition, at 15. We agree that the FLM has
failed to quantify the impact of Hadson Power’s proposed emissions
in light of storm episodes. Although the Wilderness FLM has quan-
tified an impact from the proposed emissions, namely increased sulfur
deposition, there has been no demonstration as to how or to what
extent this impact would be exacerbated by storms.°® We reject
SELC’s argument that VDAPC erred in this respect.

In addition, SELC contends that VDAPC clearly erred by issuing
the permit without requiring offsets to eliminate the adverse impact.
SELC Petition at 18. This argument presupposes that there is an
adverse impact to offset, and that offsets are required by law. SELC
contends that because VDAPC “has failed to provide any reasonable
basis for rejecting the FLM’s findings of adverse impact, these find-
ings stand.” Id. SELC’s argument, in essence, is that an otherwise

35This is not to say that there is no reasonable cut-off based on distance, so
that sources beyond that distance need not be considered in an adverse impact analy-
sis. This cut-off is best determined by the permitting authority on a case-by-case
basis. When determining if a source contributes to an adverse impact, the source’s
distance from the class I area is an appropriate consideration.

36The Wilderness FLM merely asserted that “[a]cute pulses of sulfate in precipita-
tion during storms can be responsible for increases in acidity’ and that 21% of the
precipitation in the area comes from the direction of the proposed source. Wilderness
AID at 4. From this, the FLM concludes that Hadson Power's proposed emissions
would “frequently add to the acidity of precipitation at the Wilderness.” Id.

VOLUME 4
HADSON POWER 14—BUENA VISTA 283
unsatisfactory adverse impact determination would have to be accept-
ed merely because the permitting authority articulated inappropriate
reasons for rejecting it. We disagree. In such circumstances, a remand
for reconsideration would be the most appropriate relief. In addition,
even if an adverse impact is determined to exist, offsets are not
required by law, although they have been recognized as a means
to alleviate an adverse impact, thus allowing a permit to issue. See
In re Multitrade Limited Partnership, PSD Appeal Nos. 91-2 et alia,
(Adm’r, Remand Order and Dismissal of Petitions for Review, Jan.
21, 1992). Accordingly, SELC’s argument is without merit.

C. The Park

In September 1990, the Park FLM publicized its preliminary
conclusion that AQRVs in the Park are currently experiencing ad-
verse impacts, and that emissions from Hadson Power and other
proposed facilities would exacerbate these already adverse condi-
tions.37 On January 3, 1992, VDAPC rejected these preliminary deter-
minations, largely for the same reasons it rejected them in Old Do-
minion.38

In Old Dominion, the Administrator was not persuaded by the
Park FLM’s reasoning “that since certain [AQRVs], visibility pri-
marily, are subject to deterioration in the Park, the addition of new
sources of pollution * * * will by necessity only exacerbate existing
impaired conditions.” Old Dominion, unpub. op. at 9. The Adminis-
trator concluded that the Park FLM had failed to demonstrate a
causal link between the source and the predicted impact. Without
this link, the Park FLM’s determination rested on the unproven and
unacceptable assumption that any increase in pollutants produces
an adverse impact. VDAPC rejected modeling performed by the Park
on the ground that it overstated impacts. VDAPC instead relied upon
modeling performed by Region III, which did not confirm the Park
FLM’s findings. Because VDAPC did not abuse its discretion in reject-

37 See 55 Fed. Reg. 38,404 (Sept. 18, 1990).

38SELC also argues that in the January 3, 1992 response to the Park FLM’s
preliminary adverse impact determination, VDAPC said that it needs EPA guidance
on the impact of the 1990 Clean Air Act Amendments (the “Amendments”) before
it can determine if there is an adverse impact on AQRVs in the Park. The Amend-
ments, which were enacted prior to the issuance of this permit, are intended to
reduce acid deposition and ozone pollution, and to increase visibility. SELC argues
that VDAPC cannot rely on the benefits to be produced by the Amendments as a
basis for rejecting an adverse impact determination. Because the statement at issue
was made on January 3, 1992, before the draft permit issued in this case, and was
not made in response to the Park FLM’s final adverse impact determination, it is
irrelevant to these proceedings.

VOLUME 4
284 ENVIRONMENTAL ADMINISTRATIVE DECISIONS

ing the adverse impact determination, VDAPC’s reliance on other
grounds, namely the absence of de minimis criteria, was harmless
error.

Following the Old Dominion decision, the Park FLM submitted
a final adverse impact determination during the public comment pe-
riod on Hadson Power’s draft permit. Instead of performing its own
modeling, the Park FLM relied upon Hadson Power’s modeling, which
shows that the proposed facility will annually contribute as much
as .33 ug/m3 of NO2 in the Park.3® This amount is three times
greater than Virginia’s class I increment consumption significance
level. According to the Park FLM, this quantified ambient impact
on air quality in the Park will exacerbate already adverse conditions
in the Park. The Park FLM described this impact qualitatively, con-
cluding that this amount of increase in NOx will: (1) contribute to
already high ozone levels in the Park, thus impacting ozone sensitive
vegetation, (2) deposit additional nitrogen in sensitive streams and
soils, and (3) exacerbate already adverse visibility conditions. Park
AID at 1.

VDAPC agrees that the AQRVs in the Park are currently experi-
encing adverse impacts. VDAPC Memo. at 5-13. Nevertheless,
VDAPC rejected this adverse impact determination on the ground
that the Park FLM failed to demonstrate that Hadson Power would
significantly worsen the impacts. Id. Specifically, VDAPC noted that
“current tools are inadequate to demonstrate individual source im-
pacts, especially in light of pollutant contributions from other states,”
and that “[t]he FLM’s position that any emission increase is unaccept-
able is contrary to the concept of [a] de minimis [impact] which
has been part of both the PSD and nonattainment area provisions
for a number of years.” VDAPC Memo. at 5-85 (emphases added).
In other words, VDAPC argues as it did in Old Dominion that the
Park FLM failed to provide a link between the proposed facility
and the predicted adverse impact. Addressing the amount of NO2
predicted to reach the Park and the three specific adverse impacts
identified by the Park FLM, VDAPC concluded that there is a lack
of scientific and EPA consensus on assessing ozone impacts due to
NOx emissions, and that this lack of consensus “raises serious ques-
tions about the credibility of any modeling of point source impacts.”
VDAPC Memo. at 5-86.

39SELC contends and VDAPC does not dispute that NO2 can be used to represent
all nitrogen compounds. See SELC Petition, at 7 n.5.

VOLUME 4
HADSON POWER 14—BUENA VISTA 285

On appeal, SELC contends that VDAPC clearly erred in rejecting
the adverse impact determination because, in contrast to the situation
in Old Dominion, the Park FLM did not rely on the assumption
that any increase in pollutants produces an adverse impact. Instead,
SELC notes, the Park FLM concluded that Hadson Power’s modeled
impact on air quality in the park (an annual contribution of .33
ug/m3 NO2), will exacerbate already threatened AQRVs in the Park.
SELC argues that VDAPC erroneously disregarded this analysis, and
relied upon reasoning rejected in Old Dominion.*°

VDAPC responds that “[w]hile air quality modeling performed
by Hadson does quantify the NO2 impact upon the [Park], the impact
cannot be legitimately compared to the class I increment significance
levels adopted by Virginia.” Response to SELC Petition at 2. VDAPC
further responds that because significant impact levels cannot be
used “in the context of adverse impact, and since the National Park
Service has not established scientifically accepted minimum impacts
below which a specific source’s contribution can be considered insig-
nificant, the [Park FLM’s] finding of adverse impact is clearly based
on the assumption that any additional impact is considered adverse.”
Id. at 3.

We agree with SELC that VDAPC clearly erred by failing to
consider the merits of the particular adverse impact determination
submitted by the Park FLM in this case. VDAPC made the same
mistake here that it made in connection with the Wilderness AID,
apparently hoping for the same results as in Old Dominion despite
the explicit rejection of some of its arguments in that case and the
significant factual differences between that case and this case.

The most obvious difference is that here, the Park FLM did
not base his adverse impact determination on the assumption that
“any” increase in pollutants would produce an impact, but on Hadson
Power’s modeled NOx impact on Park air quality. Unlike the situation
in Old Dominion, the Park FLM has attempted to link the emissions
from Hadson Power’s proposed facility with the predicted adverse
impact. Also, unlike Old Dominion, the Park FLM did not rely on
its own modeling, which was reasonably rejected by VDAPC in Old
Dominion, but upon Hadson Power’s. VDAPC’s attempts to discredit

40SELC makes several arguments that apply to VDAPC’s rejection of both the
Park and the Wilderness FLM’s adverse impact determinations. For example, SELC’s
argument that VDAPC should consider the cumulative impact of all previously per-
mitted facilities applies to both adverse impact determinations. Each of these argu-
ments was addressed with reference to the Wilderness, and there is no need to repeat
that discussion here.

VOLUME 4
286 ENVIRONMENTAL ADMINISTRATIVE DECISIONS

the modeling for these purposes are not persuasive, because VDAPC
relied upon Hadson Power’s modeling in other respects, and because
VDAPC failed to explain how or why its doubts about the modeling
undermine the Park FLM’s conclusions.

We do agree with VDAPC that references to the significance
levels for determining increment consumption do not, by themselves,
establish an adverse impact.41 But, the Park FLM does not represent
that the impact on air quality is the adverse impact. Instead, the
Park FLM states that AQRVs in the Park are already experiencing
adverse impacts, a conclusion with which VDAPC agrees, and that
these adverse impacts will be exacerbated by the predicted impact
on air quality, specifically, the modeled amount of NO2 predicted
to reach the Park. The adverse impact presented by the Park FLM
in this case is not the quantified impact on air quality itself, but
the exacerbation of already existing adverse impacts from that air
quality impact, which is qualitatively described in the Park AID.
While these data do not directly quantify the adverse impact on
the AQRVs themselves, and thus may be entitled to less weight
than the data presented in the Wilderness AID, they certainly war-
rant serious substantive consideration.

At a minimum, to fulfill the statutory objective of providing pro-
tection to class I areas, VDAPC was obliged to consider the merits
of this demonstration, and not summarily dismiss it, which VDAPC
appears to have done by erroneously relying on a position flatly
rejected in Old Dominion, that is, the absence of standards, including
a de minimis standard, by which to assess the Park FLM’s conclu-
sions. For the same reasons discussed with reference to the Wilder-
ness AID, we conclude that such reasoning is clearly erroneous.
Again, in contrast to Old Dominion, this error is not harmless be-
cause the record does not show an alternative, supportable rationale
for rejecting the Park AID. Accordingly we direct VDAPC to reevalu-
ate the Park AID on remand.

III. Best Available Control Technology for NOx

SELC asserts in its petition that the permit fails to require
best available control technology (BACT) for emissions of NOx.

41See Memorandum from John Calcagni, Director, EPA Air Quality Management
Division, to Thomas J. Maslany, Director, Region III Air, Radiation and Toxics Division
(Sept. 10, 1991) (VDAPC’s use of class II increment consumption levels for Hadson
Power's class I increment consumption analysis “does not include their use for deter-
mining whether a source should conduct an adverse impact analysis for any [AQRV]
in a class I area, or whether a source would have an adverse impact on an AQRV”).
VOLUME 4
HADSON POWER 14—-BUENA VISTA 287
BACT 42 is required by 40 C.F.R. § 52.21(j)(2) for each pollutant sub-
ject to regulation under the Clean Air Act that the facility would
have the potential to emit in significant amounts. There is no dispute
that BACT is required for NOx emissions from the Hadson Power
plant.
VDAPC determined that BACT for NOx should be based upon
the use of selective catalytic reduction (SCR) technology. SELC agrees
with that determination and in fact commends VDAPC for that selec-
tion.42 SELC’s concern is with how the SCR requirement is translated
into permit terms.
Part I, Condition 7 of the permit provides that nitrogen oxide
emissions shall be controlled by “a continuous coal feed system,
staged combustion, low excess air, and selective catalytic reduction
(SCR).” Condition 7 further provides that the SCR system shall be
designed, constructed and optimized to achieve a nitrogen oxides
emissions rate of 0.10 lbs/10^6 Btu on a 30-day rolling average. Condi-
tion 8 provides that:
In the event that the nitrogen oxides emission rate
exceeds 0.10 lbs/106 Btu on a 30-day rolling average,
the permittee shall do either or both of the following,
as necessary:
a. Maintain the ammonia-to-nitrogen-oxides mole
ratio at the design level, provided that no detrimen-
tal effect on equipment downstream of the SCR sys-
tem occurs.
b. Replace and/or add catalyst as necessary to
achieve a nitrogen oxides emissions limit of 0.10 lbs/
106 Btu on a 30-day rolling average to the extent
42“Best available control technology” is defined in part as:

an emissions limitation * * * based on the maximum degree of
reduction for each pollutant subject to regulation under Act which
would be emitted from any proposed major stationary source * * *
which the Administrator, on a case-by-case basis, taking into ac-
count energy, environmental, and economic impacts and other
costs, determines is achievable for such source * * * through ap-
plication of production processes or available methods, systems,
and techniques, including fuel cleaning or treatment or innovative
fuel combustion techniques for control of such pollutant.

40 C.F.R. §52.21(b)(12).

43 SELC Petition at 31.

VOLUME 4
288 ENVIRONMENTAL ADMINISTRATIVE DECISIONS
that catalyst replacement or addition does not exceed
50 percent in any 3-year period.

SELC does not object to the 0.10 lbs/10^6 Btu design level.

However, Part I, Condition 20 of the permit establishes the NOx
emissions limitations applicable to the operation of each primary
coal boiler as 0.25 lbs/10^6 Btu, 94.8 lbs/hr as a 30-day rolling average
and 398 tons/yr as an annual average. In a footnote, this limit is
characterized as a “worst-case” emission limit in the event of mar-
ginal performance or deterioration of the SCR system. SELC takes
exception to the 0.25 lbs/10^6 Btu emission limitation as not reflecting
BACT. More specifically, SELC asserts that this limitation “is not
the emission limitation based on the maximum degree of reduction
considering cost and technical feasibility.” 44

SELC points out that other coal-fired boilers have been permitted
with lower NOx emission rates using either SCR or selective non-
catalytic reduction (SNCR). Most of these have been permitted at
0.17 lbs/10^6 Btu. SELC further cites as support a letter from EPA
Region III to VDAPC during the comment period recommending that
the permit limitation be set at 0.10 lbs/10^6 Btu or 80% control. (The
0.25 rate is based on 50% control.) 45

In addition, SELC makes reference to a NOx guideline of 0.15
lbs/10^6 Btu for new coal-fired boilers adopted in June 1991 by the
Virginia Air Pollution Control Board. SELC states that this level
can be consistently achieved and improved upon. SELC further states
that with a design limit of 0.1 lbs/10^6 Btu, an operating limitation
of 0.15 is “clearly technically and economically feasible.” SELC Peti-
tion at 32.

VDAPC, in its response, stresses that this is the first application
of SCR technology to a spreader-stoker boiler. It also notes that
SCR has not been operated commercially on a coal-fired boiler in
the United States, although it has been established on pulverized
coal-fired boilers in Japan and Germany. In light of this, VDAPC
asserts that “[t]he risks involved in a first-time application neces-
sitate more moderate regulation.” Response to SELC Petition at 10.

44SELC Petition at 31.

45SELC Petition at 32 and Appendix L (Letter from Bernard E. Turlinski, Chief,
Air Enforcement Branch, Region III, to Wallace N. Davis, Executive Director, VDAPC
(Jan. 31, 1992)).

VOLUME 4
HADSON POWER 14—BUENA VISTA 289
VDAPC elaborates on its concerns by identifying the following
as being of primary concern:
—potential differences in the properties of coal used
overseas and in this country, and
—potential differences in the characteristics of ash
produced by spreader-stoker and pulverized coal fir-
ing.

More specifically, VDAPC states that:
[T]he ash produced by a spreader-stoker boiler is
more coarse, causing a higher tendency to blind the
SCR catalyst. Other differences involve excess air,
furnace temperature, furnace volume, and heat
transfer surface arrangement. All of these factors af-
fect temperature and temperature fluctuations with-
in the SCR unit, which are critical to optimal SCR
performance.

Response to SELC Petition 10-11.

Finally, VDAPC argues that the approach taken at Hadson
Power is “totally consistent” with the precedent set by the Chambers
Works cogeneration facility in New Jersey, one of the facilities cited
in the SELC petition. VDAPC explains that since the Chambers
Works’ boilers would have had uncontrolled NOx emissions of 0.27
lbs/10^6 Btu and the permit sets an emission limitation of 0.17 lbs/
10^6 Btu, it only requires 37% NOx removal. At Hadson Power, uncon-
trolled emissions would be at the rate of 0.50 lbs/10^6 Btu and the
emission limitation is 0.25 lbs/10^6 Btu, thus requiring a 50% reduc-
tion. Therefore, the reduction required at Hadson Power is greater,
on a percentage basis, than at the Chambers Works. Response to
SELC Petition at 11.

In its reply to the VDAPC response, SELC indicates that a per-
mit issued to Orlando Utilities Commission’s Curtis E. Stanton En-
ergy Center Second Unit, issued prior to the Hadson Power permit,
also set a maximum emission limitation at 0.17 lbs/10^6 Btu and
that the issuance of this and the New Jersey permits demonstrates
that SCR with an emission rate of 0.17 lbs/10^6 Btu or lower is
BACT for the Hadson Power plant.

VOLUME 4
290 ENVIRONMENTAL ADMINISTRATIVE DECISIONS

We note that the explanation VDAPC gives in its response to
the petition repeats almost verbatim its response to similar comments
raised on the draft permit. See Response to Petitions, Attachment
IV at 5-71 to 5-72. SELC was undoubtedly aware of the rationale
set forth by the VDAPC in its response to comments. Yet, SELC
has not explicitly addressed the explanation given by VDAPC in
either its petition or its reply. Most significantly, SELC does not
address at all the transferability of SCR technology to spreader-stoker
boilers.

As previously noted, the petitioner has the burden of demonstrat-
ing that review of a permit condition is warranted. Recently, this
Board held that “[t]o satisfy the requirements of 40 C.F.R. § 124.19(a),
it is not enough for [petitioner] to include in its petition for review
a mere reference to comments made during the comment period on
the draft permit.” In re Adcom Wire, RCRA Appeal No. 92-2, slip
op. at 10 (EAB, Sept. 3, 1992). Instead, § 124.19(a) requires a peti-
tioner to “show why the [State’s] responses to the issues [raised
in the public comment period] are clearly erroneous or involve impor-
tant policy considerations or exercises of discretion that should be
reviewed.” Id. SELC’s failure to respond to the primary rationale
set forth by VDAPC fatally flaws its petition in this regard. As
such, review of this issue is denied.

In denying review, we recognize that SELC may ultimately prove
correct that a level more stringent than 0.25 lbs/10^6 Btu can be
consistently achieved. Even VDAPC, in its internal documents, seems
to have concluded that the use of U.S. coals should not be a signifi-
cant concern. In referring to the Chambers Works project, VDAPC
states:

In issuing the Chambers Works permit, the review-
ing authority determined that the coal to be burned
at that facility is not significantly different from the
coal being burned at successful SCR applications in
Germany and Japan. The same determination ap-
plies to Hadson Power, as no specific differences in
coal quality have been shown.

In support of this determination, the Department
has received correspondence from SCR vendors indi-
cating that the constituents of typical Virginia coal
are not prohibitive to SCR operation.

VOLUME 4
HADSON POWER 14—BUENA VISTA 291
VDAPC Memo. at 5-29. Thus, the larger concern seems to be the
transferability of SCR technology to a spreader-stoker boiler. In this
regard, while acknowledging the technical differences between pulver-
ized coal and spreader-stoker boilers as previously discussed, VDAPC
states that “neither the applicant nor the agency’s research has
shown that the gas stream from a spreader-stoker boiler is physically
or chemically different as to preclude the application of this tech-
nology.” Id. While this does not directly address what level of per-
formance can be consistently maintained, it does give some reassur-
ance as to the transferability of the technology.

We also recognize that the permit requires a review of the NOx
emission limitation prior to issuance and each renewal of an operat-
ing permit.4® It provides that “the Department may revise the NOx
emissions rate downward to reflect the maximum NOx emissions rate
that is demonstrated to be consistently achievable on a 30-day rolling
average, not including periods of malfunction.” Permit, Part I, Condi-
tion 20. We would expect that if the performance of Hadson Power
or any other spreader-stoker boiler demonstrates the achievability
of a more stringent emission limitation, the current limit will be
reconsidered and adjusted appropriately.47

In the context of its objections to the NOx emission limitation,
SELC raises one further point that needs to be addressed. It notes
that although the air quality modeling for the Hadson Power plant
is based on a shutdown of boilers at the Georgia Bonded Fibers
plant, the permit does not actually require the shutdown of that
plant. Instead, it provides that Hadson Power shall cease to operate
beyond 90 days after commencing operation unless one of the follow-
ing occurs:

i. a restriction that renders the existing boilers at
the host facility inoperable is made federally enforce-
able, or

46 See Virginia Air Pollution Control Regulations § 120-08-04(P)(1) (an operating
permit may be issued for a term not to exceed five years).

47We note that as to emissions of ammonia, the permit establishes an emission
limitation but indicates that lower limits may be imposed “after review of instack-
testing and optimizing the selective catalytic reduction system.” While it is possible
such an approach could have also been used for NOx emissions, we recognize that
this might not fully address potential deterioration of the SCR system. We do not
find the mechanism chosen by VDAPC to deal with the technical uncertainties of
application of SCR to spreader-stoker technology to be in clear error.

VOLUME 4
292 ENVIRONMENTAL ADMINISTRATIVE DECISIONS

ii. the permittee demonstrates that the permittee’s

facility in concurrent operation with the existing boil-

ers does not increase the net impact on air quality.

Such demonstration shall be done in a manner ac-

ceptable to the Department.
Permit, Part I, Condition 38(d). SELC expresses a concern that if
Hadson Power were operating at a level below 0.25 lbs/10^6 Btu,
Georgia Bonded Fibers could start up and emit the difference between
Hadson Power’s operating rate and the 0.25 lb. limit, since the air
quality analysis was premised on the 0.25 lb. limit. As such, the
permit does not provide an incentive to minimize emissions.4®

Relative to this condition, SELC also states that it should be
made more specific. It should either require shutdown of the Georgia
Bonded Fiber boilers or, in the alternative, be revised to state the
total limit in terms of emissions rather than “net impact on air
quality,” which SELC finds to be “vague and undefined.” SELC Peti-
tion at 33.

VDAPC provides a response to this issue in the context of ad-
dressing a similar comment made by the County. In its response,
VDAPC indicates that “[nJo regulatory framework is in place for
the department to apply an emissions cap to a select number of
facilities in attaining the ambient air standards. In addition, VDAPC
regulations do not allow the operation of Georgia Bonded Fibers to
be governed by a permit issued to Hadson Power 14—Buena Vista.”
Response to County Petition at 13.

Conceding to VDAPC that it cannot regulate the Georgia Bonded
Fibers facility directly in the Hadson Power permit, that still does
not fully respond to the concern raised by the petitioners. Clearly,
if appropriate, VDAPC can regulate the conduct of Hadson Power
based on whether the Georgia Bonded Fibers boilers are operating,
thus addressing the issue of concurrent operation raised by the Coun-
ty and SELC (and not specifically addressed by VDAPC).

While SELC links this issue with the NOx BACT issue, we think
this linkage is tenuous at best. The BACT limit for Hadson Power
is in no way dependent upon the availability of offsets at Georgia
Bonded Fibers. SELC may be assuming that even if the permit con-
tained an emission limit of 0.15 or 0.17 lbs/10^6 Btu that the provision

48 somewhat similar concern is raised by the County. See County Petition at
10.

VOLUME 4
HADSON POWER 14—-BUENA VISTA 293
relating to concurrent operation would be the same, thus lowering
total emissions. However, it is equally possible that modeling with
the lower emission limit could reduce or eliminate the need for offsets
for NOx entirely, resulting in the deletion of the offset provision
as it relates to NOx. We decline to speculate on this.49

More important is whether the condition is consistent with the
assumptions made in the underlying air quality modeling. The model-
ing assumed that Hadson Power would be operating at a 0.25 lbs/
106 Btu limit and that the boilers at Georgia Bonded Fibers would
be shut down. The permit provision objected to by SELC and the
County allows continued operation of the existing boilers if this “does
not increase the net impact of air quality,” demonstrated “in a man-
ner acceptable to [VDAPC].” We assume the “increase” is measured
relative to the scenario as modeled, i.e., with Hadson Power operating
at its allowable emission limitation and with the Georgia Bonded
Fibers boilers shut down. We do not find that allowing this additional
flexibility, with the limitations as specified, in any way allows adverse
impacts beyond those considered in the underlying model and we
find no error in its formulation.

IV. Air Quality Modeling

Air quality models attempt to describe the course of pollutants
as they leave the source by quantifying the qualities of air pollution
transport “to provide numerical estimates of ground level concentra-
tions based upon facility and meteorological parameters.” J.
Bromberg, Clean Air Act Handbook, at 86 (2d ed. 1985). PSD permit
applicants use modeling to demonstrate compliance with the require-
ments for obtaining a permit. For example, Hadson Power used mod-
eling in this case to demonstrate that its proposed emissions would
not cause or contribute significantly to a violation of the available
increments, and the FLMs used Hadson Power’s modeling results
in their adverse impact determinations.

SELC and the County contend that Hadson Power’s modeling
does not adequately consider local topography and meteorology. See
SELC Petition at 33-35. SELC asserts that due to Hadson Power’s
proposed location in a valley of the Blue Ridge Mountains, the site

49While SELC objects that Permit, Part I, Condition 38(d) “does not provide
incentive for emissions from Hadson Power and Georgia Bonded to be minimized,”
SELC Petition at 33, it does not cite any legal requirement for the combined emissions
to be minimized.

VOLUME 4
294 ENVIRONMENTAL ADMINISTRATIVE DECISIONS
is subject to frequent temperature inversions and air stagnation, and
that these conditions were not considered in the modeling.®°

The County similarly argues that the meteorological and air qual-
ity data collected by Hadson Power are incomplete, unreliable, inac-
curate and unsuitable.5! The County argues that these faulty data
render the modeling results suspect.

Both SELC’s and the County’s petitions fail to articulate ade-
quately a substantive basis for review. The County’s petition for
review consists of a letter stating that:

The County takes exception to several conditions of

the final permit and herein reiterates its opposition

to the issuance of the permit as it set forth in its

“COMMENTS OF THE COUNTY OF

ROCKBRIDGE, VIRGINIA IN OPPOSITION TO

THE ISSUANCE OF THE AIR PERMIT,” which

comments are attached hereto and incorporated here-

in by reference.
County Petition at 1 (emphasis added). In other words, the grounds
for review asserted in the County’s petition are identical to the Coun-
ty’s comments on Hadson Power's draft permit.5? SELC’s petition
to review the air quality data also repeats comments made by it
and others on the draft permit.53 Neither petitioner makes an argu-
ment which addresses the adequacy of VDAPC’s response to those
comments.54 In this case, VDAPC provided significant, substantial

50 Specifically, SELC protests the use of air stability data collected in Greensboro,
N.C., a non-valley location. SELC is also dissatisfied that the air quality data used
in the modelling were collected from September to April, and do not include the
summer when air stagnation frequently occurs. SELC contends that these limited
data conflict with VDAPC regulations requiring a full year’s worth of data unless
it is determined that a complete and adequate analysis can be performed using data
from a shorter period. Virginia Air Pollution Control Regulations § 120-08-02(N)(1)(d).

51For example, the County also contests the use of meteorological data collected
in Greensboro, N.C.

52The County raises one additional issue in its letter that it did not raise in
its comments on the draft permit, namely that VDAPC failed to consider seriously
the adverse impact determinations, an argument addressed supra.

53SELC’s petition refers to, and includes as attachments, the comments made
on the draft permit by Dr. Michael Williams, Edgar W. Spencer, Edwin J. Goller

and the County. SELC Petition at 34.

54The only exception to this is SELC’s reference to VDAPC’s response that it
collected data for a period less than one year because historical data gathered else-
where showed that a complete and adequate analysis could be made with less data.
SELC Petition, at 35. SELC asserts that “[gliven Buena Vista’s unique meteorological
VOLUME 4
HADSON POWER 14—-BUENA VISTA 295
responses to the comments on these issues. VDAPC Memo. at 5-
49 to 5-69. Because the County and SELC failed to meet the require-
ment of § 124.19 to address these responses, we deny review of the
various substantive issues raised relative to the air quality analyses.
See Adcom Wire, supra.

SELC raises another issue, concerning the public notice of the
models that were used in this case. The Clean Air Act requires
the Agency to specify the air quality models to be used for PSD
permits. CAA § 165(e)(3)(d). These models are listed in the “Guideline
on Air Quality Models (Revised)” (1986) and Supplement A (1987)
(hereinafter collectively “Guidelines”). See 40 C.F.R. § 52.21(i). If the
recommended models are inappropriate in a given case, other non-
Guideline models may be used pursuant to 40 C.F.R. § 52.21(l). That
section provides that “[w]ritten approval of the Administrator must
be obtained for any” non-Guideline model. “In addition, use of a
modified or substituted model must be subject to notice and oppor-
tunity for public comment * * *.” Id. The Virginia permitting regula-
tion contains an identical requirement. See Virginia Air Pollution
Control Regulations § 120-08—02(M)(2).

In this case, the models contained in the Guidelines were appar-
ently not appropriate given Hadson Power’s proposed location, and
so Hadson Power sought and obtained VDAPC and EPA approval
to use a non-Guideline model.55> VDAPC failed, however, to submit
this non-Guideline model to notice and comment prior to its use.
conditions, it is clear error to rely on historical air quality data gathered in other
areas as a basis for conditions in the Buena Vista valley.” Id. SELC’s mere allegation
of clear error is far from satisfying its burden under § 124.19 of providing a “statement
of reasons” showing that the permit is based on clear error. See In re Waste-Tech
Services and BP Chemicals America, Inc., RCRA Appeal No. 88-8, unpub. op. at
n.2 (Adm’r, Sept. 22, 1988) (“petition for review must not only identify disputed issues,
but demonstrate that special and important reasons necessitate review”).

55 As described by VDAPC:

Because the applicant’s proposed location is in complex terrain
and within 100 kilometers of two Class I areas, some unique
problems were encountered during the modeling analysis of
air quality impacts. In order to determine the maximum im-
pact on receptors located at elevations between the stack top
and the plume height (intermediate terrain), it was necessary
for Hadson-14 to develop a model that would compare results
from the simple terrain and complex terrain models in this
region where the models overlap. The worst case from either
model would be selected and incorporated into the overall
model output. Because no such model has been approved by
EPA for general use, Hadson-14 created a hybrid model,
Continued
VOLUME 4
296 ENVIRONMENTAL ADMINISTRATIVE DECISIONS

SELC contends that State and Federal regulations require public
notice and comment before a non-Guideline model may be used, and
that such notice cannot be provided in connection with the draft
permit, which is “issued long after the decision to use the model
is made and [therefore] does not give the public an opportunity to
affect the choice of models.” SELC Petition at 36. In any event,
SELC notes, the notice of the draft permit and public hearing in
this case did not indicate Hadson Power’s use of a non-Guideline
model.

SELC is correct that there is a regulatory obligation to submit
a non-Guideline model to notice and public comment. However, the
Federal regulation, §52.21(1), provides that such notice and oppor-
tunity for comment shall proceed in accordance with the procedures
developed for public participation in the process of issuing a permit.°¢
The same is true of the Virginia regulation.5? We interpret this regu-
latory language as allowing the notice and opportunity for public
comment on the use of a non-Guideline model to be provided with
the notice and opportunity for public comment on the draft permit.
SELC agrees that there is no explicit regulatory language requiring
notice and comment on the non-Guideline model prior to that stage
of the proceedings, instead arguing that the regulations implicitly
require notice and comment on a non-Guideline model prior to its
use, which would be prior to the draft permit.55 SELC Petition at
36 n.19. In light of the clear reference in §52.21(Z) to the permitting
procedures in Part 124, however, we decline to go beyond this lan-
guage and search for an alleged implicit requirement.
~~ ISCSTCPX, based on two established EPA models (ISCST and

COMPLEX 1); EPA approved ISCSTCPX in May 1991.
VDAPC Memo. at 5-3.

56This regulation provides that use of a non-Guideline model “must be subject
to notice and opportunity for public comment under procedures developed in accordance
with paragraph (q) of this section.” Paragraph (q) requires the application of 40 C.F.R.
Part 124, which “contains EPA procedures for issuing, modifying, revoking and reissu-
ing or terminating all * * * PSD permits * * *.” 40 C.F.R. § 124.1.

57 Virginia Air Pollution Control Regulations § 120-08-02(M)(2) provides that no-
tice and comment on the use of non-Guideline models should proceed in accordance
with subsection (R), which in turn provides for public notice of, among other things,
VDAPC’s preliminary determination on the permit application.

58 According to SELC, this implicit requirement stems from the fact that to be
included in the Guidelines, a model must be subject to notice and comment. SELC
Petition at 36 n.19 (citing 42 U.S.C. § 7475(e)(3), 43 Fed. Reg. 26,399 (June 19, 1978)).
SELC’s argument overlooks that Hadson Power’s model is not to be included in the
Guidelines for future application without further public notice, but was used in this
case only.

VOLUME 4
HADSON POWER 14—BUENA VISTA 297

SELC further contends that VDAPC’s notice of Hadson Power's
draft permit failed to mention the use of the non-Guideline model.
VDAPC disagrees, noting that “all appropriate information including

      • the air quality analyses * * * could be reviewed by the public
        at local libraries in Buena Vista and Lexington” and at the local
        VDAPC office in Roanoke. Response to SELC Petition at 13. In addi-
        tion, VDAPC notes that the notice of the draft permit indicated that
        an informal briefing would take place on January 15, 1992. At this
        briefing, VDAPC staff discussed the model used by Hadson Power
        in the air quality analysis. Id.

We are not persuaded by VDAPC’s response, which is strikingly
similar to its explanation for failing to include in the notice the
predicted amount of increment consumption in the Park. For the
same reasons discussed above with reference to increment consump-
tion, VDAPC’s failure to mention the non-Guideline model in the
public notice of the draft permit and public hearing deprived the
public of a meaningful opportunity to comment on the draft permit.
VDAPC is required, in connection with any public notice necessitated
by its response to the remand ordered by this decision, to give notice
of the non-Guideline model used by Hadson Power. Comments on
the model may persuade the state that some changes to the model
are appropriate. Further, any comments could support a renewed
challenge to the modeling assumptions in any further appeal after
completion of the remand if properly made in light of Adcom Wire,
supra.

V. National Park Service Environmental Assessment

Hadson Power proposed that its facility be serviced by a coal
conveyor and utility improvements running between it and Georgia
Bonded Fibers. The coal conveyor and utility improvements (steam,
condensate and water lines) would run through Glen Maury Park,
a park owned by the City of Buena Vista and supported by Federal
funds under the Land and Water Conservation Fund Act, 16 U.S.C.
§ 4601-8(f)(3). Accordingly, the Department of the Interior (DOI) must
approve the use of Glen Maury Park for this purpose.

The City of Buena Vista requested such approval. The DOI,
through the National Park Service (NPS), notified the public that
it would prepare an environmental assessment of the proposed coal
conveyor and utility improvements in order to determine whether
to prepare an environmental impact statement under the National
Environmental Policy Act (NEPA), 42 U.S.C. § 4332. See 57 Fed.
Reg. 2,928 (Jan. 24, 1992). While this appeal was pending, and before

VOLUME 4
298 ENVIRONMENTAL ADMINISTRATIVE DECISIONS

the NPS completed its environmental review, Hadson Power notified
the City of Buena Vista that it is abandoning its plans to use the
coal conveyor, and will instead rely upon truck delivery of coal.
Hadson Power informed the City of Buena Vista that it is contemplat-
ing rerouting the utility improvements to avoid Glen Maury Park.

In response to CLEAR’s comment that VDAPC should defer con-
sideration of the permit application until NPS completes its environ-
mental review pursuant to NEPA, VDAPC stated that the outcome
of the NEPA process would have no affect on the PSD permit decision
because “Hadson Power included fuel delivery by truck in its analyses
as a contingent if the conveyor system could not be utilized. The
VDAPC has evaluated both alternatives and found them to be in
accordance with PSD requirements.” VDAPC Memo. at 5-41.

On appeal, CLEAR asserts that VDAPC’s response is inadequate
because it fails to explain why “it would not have been ‘feasible’
or ‘reasonable’ to await the completion of a [NEPA] review that will
certainly provide a wealth of information relating to the environ-
mental impacts of the Buena Vista plant” as required by 40 C.F.R.
§52.21(s) and Virginia Air Pollution Control Regulations § 120-08-
02(T). CLEAR Petition at 4. CLEAR contends that by “refusing to
defer consideration of the permit and thereby allowing the project
to go forward, VDAPC undermined the efficacy of the NEPA review.”
Id. CLEAR also asserts in contradiction to VDAPC that the air qual-
ity analysis submitted by Hadson Power assumed coal delivery by
conveyor, and did not include the possibility of delivery by truck,
and therefore the permit is based on air quality data that do not
reflect the true situation. CLEAR Reply at 2-3.59

NEPA § 102(2)(C) requires that an environmental impact state-
ment shall be included “in every recommendation or report on * * *
major Federal actions significantly affecting the quality of the human
environment.” 42 U.S.C. § 4332(2)(C). Federal approval of private ac-
tions is a Federal action which may trigger the need for an environ-
mental impact statement under NEPA. 40 C.F.R. § 1508.18(a). The
NPS is currently proceeding with its obligations under these provi-
sions in connection with the proposed use of the Glen Maury Park.

59The County also contends that VDAPC should not issue the permit until the
pending NEPA process is complete. The County merely repeats the comments it made
on the draft permit without explaining how or why VDAPC’s responses to the com-
ments are inadequate, and thereby fails to comply with the requirements of 40 C.F.R.
§ 124.19. See Adcom Wire, supra. Accordingly, we deny review of the County’s claims.
VOLUME 4
HADSON POWER 14—BUENA VISTA 299
The Federal PSD regulations provide that
Whenever any proposed source or modification is
subject to action by a Federal Agency which might
necessitate preparation of an environmental impact
statement pursuant to the National Environmental
Policy Act * * *, review by the Administrator con-
ducted pursuant to this section shall be coordinated
with the broad environmental reviews under that Act

      • to the maximum extent feasible and reason-
        able. ;
        40 C.F.R. §52.21(s). The Virginia regulation is virtually identical.
        See Virginia Air Pollution Control Regulations § 120-02-08(T).

Under the plain language of this regulation, coordination is all
that is required of the PSD permitting authority, and only to the
extent feasible and reasonable. As used in this regulation, “coordi-
nate” is best given its everyday meaning, namely to harmonize or
to act together in a concerted way. In our view, then, this regulation
does not require a State to refrain from issuing a PSD permit until
the NEPA review process is complete. Accordingly, we reject CLEAR’s
argument that VDAPC clearly erred by failing to defer consideration
of this PSD permit until NPS completes its review of the proposed
easement for Glen Maury Park.6° We also disagree with CLEAR’s
argument that deferring the permit is necessary because the NEPA
review would provide a wealth of information relating to the impact
of the proposed facility. To the extent information would be relevant
to the PSD permit, such information should have already been sup-
plied in the PSD permit process. If VDAPC believed any relevant
information was lacking, it is authorized to request such information
under Virginia Air Pollution Control Regulations § 120-08-02(R).61
There is nothing in the record to suggest, and CLEAR does not
demonstrate, that VDAPC lacked information relevant to the PSD
permit proceeding that would be provided in the NEPA process.

Moreover, we conclude that VDAPC sufficiently explained why
coordination with the NPS should not be required in this case. The
only portion of the NEPA review relevant to this permit proceeding

60There may be times where the Federal action triggering NEPA requirements
involves the proposed source itself. In those circumstances, which are not present
here, waiting for completion of the NEPA process may be appropriate.

61That regulation provides, in part, that VDAPC “shall advise the applicant of
any deficiency in the application or in the information submitted.” See also 40 C.F.R.
§ 124.3(c) (“the Regional Administrator may request additional information from an
applicant but only when necessary to clarify, modify, or supplement previously submit-
ted material”).

VOLUME 4
300 ENVIRONMENTAL ADMINISTRATIVE DECISIONS

is that pertaining to the coal conveyance.®? Hadson Power’s recent
decision to abandon the plans for coal conveyance across Glen Maury
Park eliminates any need to await completion of the NPS NEPA
review. Even if the coal conveyance option were still pending, VDAPC
indicates that its permit decision is based on an air quality analysis
that included the truck delivery option, and therefore the outcome
of the NEPA review is irrelevant. The record supports this conclu-
sion.®3 Because the outcome of the NEPA review would not provide
any significant new information to the proceeding, or change the
outcome, we agree with VDAPC that coordination of the PSD permit
process and the NEPA review process is not reasonably required
in this case.

CONCLUSION

For the reasons set forth above, the Board remands this permit

to the State:

  1. to describe emissions related to the construction

of Hadson Power and to include such emissions in

the air quality analysis or demonstrate why they

can be properly excluded;

  1. to determine whether the Wilderness FLM dem-

onstrated that Hadson Power’s proposed emissions

will adversely impact AQRVs in the Wilderness; and

  1. to determine whether the Park FLM demonstrated

that Hadson Power’s proposed emissions will ad-

versely impact AQRVs in the Park.
VDAPC is hereby directed to reopen the permit proceedings for the
limited purpose of reconsidering these issues in a manner consistent
with this opinion. After reconsidering these issues, VDAPC shall re-
issue a draft permit and reopen the public comment period to allow
comments on its reconsideration. The notice of the public comment
period shall be in accordance with all applicable Federal and State
regulations, and shall provide for public comment, in accordance with

62There is nothing in the record that indicates how or why the utility improve-

ments relate to the PSD permit.

63 See VDAPC Memo. at 5-36 (“The information submitted by Hadson Power
suggests that the plant requires * * * either one train locomotive or up to 40 coal
trucks each day”) and 5-38 (“The Hadson Power air quality analysis did include
potential fugitive dust from coal handling operations (rail and truck transfer options,
storage, and crushing).”).

VOLUME 4
HADSON POWER 14—BUENA VISTA 301
this opinion, on all increment to be consumed by the proposed source
(including any increment to be consumed at the Park), and Hadson
Power’s use of a non-Guideline model in its air quality analyses.
The State’s final permit decision is subject to review under 40 C.F.R.
§ 124.19, and appeal of the remand proceedings is required to exhaust
administrative remedies under 40 C.F.R. § 124.19(f)(iii).

Review of all other issues raised in the petitions for review is
denied.
So ordered.
VOLUME 4

Get today's answer for your situation

You just read Board precedent from 1992. Ezel checks whether it still stands, including any court review since, and answers your specific situation, with citations.

Opens in Ezel Pro. Every answer cites the authority it relies on.