Secretary of Labor (MSHA) v. U. S. Steel Corporation (ALJ decision, July 16, 1980)

U. S. Steel Corporation (FMSHRC PITT 79-186-P): Two settlements approved

Decision type
ALJ decision
Dockets
PITT 79-186-P, PITT 79-185-P
Decided
July 16, 1980
Presiding judge
Outcome
Settled
Precedential status
Final order, not precedent
Checked against source
2026-10-23

Apply this to your situation

This order from 1980 bound only the parties to this case; it isn't precedent. Ask about your situation and see what the current MSHA standards and Commission precedent say, with citations.

Currency note: this decision dates from 1980
The MSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Final ALJ decision, not Commission precedent
The judge later corrected the penalty amount for PITT 79-186-P from $688 to $648. No Commission review appears in the official index, so the corrected ALJ decision became final under the 40-day rule in 30 U.S.C. § 823(d)(1). It binds the parties but is not Commission precedent. The full text below is from the official FMSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official FMSHRC release. The full text is the agency's own release.
Transcribed from a scanned original: FMSHRC released this decision as an image-only file. The full text below is a machine transcription, proofread against the scan. Check the official release before quoting exact language.
Read the official release (fmshrc.gov)

Plain-English summary

The Secretary sought penalties for seven alleged safety violations at U. S. Steel's Cumberland Mine. The judge approved settlements covering five citations in PITT 79-186-P and one citation in PITT 79-185-P. The order printed $688 for the first settlement, but the judge later corrected that amount to $648 in a separate order. The second settlement required a $72 payment. The Secretary vacated the remaining citation after finding no violation, and the judge dismissed it.

Decision snapshot

  • Cited standards: 30 C.F.R. §§ 77.701, 77.506, 77.902, 77.508, 70.250(a), and 77.1713(d).
  • Outcome: Settlements approved; $688 printed for PITT 79-186-P, later corrected to $648, plus $72 for PITT 79-185-P; one citation vacated.
  • Key point: The judge approved the agreed penalties and dismissed the citation that the Secretary had vacated.

Full text (FMSHRC public release)

FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION OFFICE OF ADMINISTRATIVE LAW JUDGES
2 SKYLINE, 10th FLOOR
5203 LEESBURG PIKE
FALLS CHURCH, VIRGINIA 22041

(703) 756-6210/11/12
16 JUL 1980

SECRETARY OF LABOR,
: Civil Penalty Proceedings
MINE SAFETY AND HEALTH
:
ADMINISTRATION (MSHA),
: Docket No. PITT 79-186-P
Petitioner
: A.O. No. 36-05018-02012
:
v. : Docket No. PITT 79-185-P
: A.O. No. 36-05018-03010
U. S. STEEL CORP.,
:
Respondent
: Cumberland Mine

DECISIONS APPROVING SETTLEMENTS

These civil penalty proceedings were initiated by the petitioner against the respondent through the filing of proposals for assessment of civil penalties pursuant to section 110(a) of the Federal Mine Safety and Health Act of 1977, 30 U.S.C. 820(a), seeking civil penalty assessments for seven alleged violations of certain mandatory safety standards promulgated pursuant to the Act.
Respondent filed timely answers in the proceedings and the cases were consolidated for hearing in Pittsburgh, Pennsylvania, on March 19, 1980. Subsequently, by motion filed June 17, 1980, petitioner now seeks approval of a proposed settlement negotiated by the parties as follows.

Docket No. PITT 79-186-P
This docket concerns five citations which the parties propose to dispose of by settlement. The citations, initial assessments, and the proposed settlement amounts are as follows:

Citation No. Date 30 CFR Standard Assessment Settlement 235178 11/30/78 77.701 $ 160.00 $ 160.00 235179 11/20/78 77.506 90.00 90.00 235180 11/27/78 77.902 160.00 160.00 235621 11/30/78 77.508 160.00 160.00 235622 11/30/78 77.506 78.00 78.00
$ 688.00 $ 688.00

L

1831

Discussion

The proposed settlement is for 100% of the initial proposed assessments made by MSHA for the violations in question. In support of the proposed settlement, petitioner has submitted information pertaining to the six statutory factors set forth in section 110(i) of the Act. In addition, petitioner has submitted a full and complete discussion and analysis of the facts and circumstances surrounding each of the citations, including the factors of gravity, negligence, and good faith compliance. After review and consideration of the arguments presented in support of the proposed settlement, I find that it is reasonable and in the public interest, and that it should be approved.

Order

Pursuant to Commission Rule 30, 20 CFR 2700.30, petitioner's motion is granted, settlement is approved, and respondent is ordered to pay civil penalties in the amount of $688.00 in satisfaction of the aforesaid citations, payment to be made to MSHA within thirty (30) days of the date of this decision and order. Upon receipt of payment, this matter is dismissed.

Docket No. PITT 79-185-P

This docket concerns two citations, 7-0049, 12/13/77, 30 CFR 70.250(a), and 235657, 11/13/78, 30 CFR 77.1713(d), for which civil penalties of $72 and $66 were initially proposed by the petitioner. Petitioner's motion seeks approval of a settlement for citation 7-0049, for the full amount of the $72 assessment, and in support of its proposal petitioner has submitted a full and complete discussion of the facts and circumstances surrounding the citation, including information with respect to the six statutory factors found in section 110(i) of the Act.

With regard to citation 235657, petitioner states that it has been vacated because no violation of the cited standard occurred, and no civil penalty should be assessed,

Order

Pursuant to Commission Rule 30, 29 CFR 2700.30, settlement is approved and respondent is ordered to pay a civil penalty in the amount of $72 in satisfaction of the citation in question, payment to be made to MSHA within thirty (30) days of the date of this decision and order. Upon receipt of payment, this matter is dismissed. The vacated citation is dismissed.

George A. Koutras
Administrative Law Judge

Distribution:

Sidney Salkin, Esq., U.S. Department of Labor, Office of the Solicitor, 3535 Market St., Philadelphia, PA 19104 (Certified Mail)

Louise Q. Symons, Esq., U.S. Steel Corp., 600 Grant Street, Pittsburgh, PA 15230 (Certified Mail)

1833

What applies to your situation today?

This order bound one employer. Ezel checks the current MSHA standards and Commission precedent against your facts, with citations.