Secretary of Labor (MSHA) v. Republic Steel Corporation (Commission decision, July 2, 1979)

Republic Steel Corporation (FMSHRC PITT 78-156-P): Settlement approval affirmed

Decision type
Commission decision
Dockets
PITT 78-156-P, PITT 78-157-P, PITT 78-396-P, PITT 78-397-P, PITT 78-406-P, PITT 78-407-P, PITT 78-408-P, PITT 78-409-P, PITT 78-410-P
Decided
July 2, 1979
Outcome
Settled
Precedential status
Citable Commission precedent
Checked against source
2026-10-23

Apply this precedent to your situation

This is citable Commission precedent from 1979, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.

Currency note: this decision dates from 1979
The MSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Decision of the Commission
The Commission affirmed the judge's approval of a settlement in nine penalty proceedings. This is a final Commission disposition of the settlement. The full text below is from the official FMSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official FMSHRC release. The full text is the agency's own release.
Read the official release (fmshrc.gov)

Plain-English summary

Republic Steel's penalty proceedings covered nine dockets associated with four mines. A judge approved a settlement, and the Commission directed him to add his reasons and supporting facts to the record. After reviewing that supplement, the Commission found no error in the approval and affirmed it. This release does not identify the safety standards, describe the settlement terms, or state a penalty amount.

Decision snapshot

  • Cited standards: None identified in this release.
  • Outcome: Settlement approval affirmed in nine penalty proceedings; terms and amount not stated.
  • Key point: The Commission affirmed after the judge supplied reasons and facts supporting settlement approval.

Full text (FMSHRC public release)

CCASE:
MSHA V. REPUBLIC STEEL
DDATE:
19790702
TTEXT:
FEDERAL MINE SAFETY & HEALTH REVIEW COMMISSION WASHINGTON, D.C. July 2, 1979 SECRETARY OF LABOR, Civil Penalty Proceedings MINE SAFETY AND HEALTH
ADMINISTRATION (MSHA),
Docket Nos. PITT 78-156-P
PITT 78-157-P
v. PITT 78-396-P
PITT 78-397-P
REPUBLIC STEEL CORPORATION
PITT 78-406-P
PITT 78-407-P
PITT 78-408-P
PITT 78-409-P
PITT 78-410-P
Banning Mine
Russelton Mine
Clyde Mine
Newfield Mine
DECISION
On November 27, 1978, the Commission directed review of a decision approving a settlement in this penalty proceeding. The case was remanded to the administrative law judge so that he could supplement the record with a statement of his reasons for approving the settlement and the facts supporting his approval. Based upon our review of the record as supplemented, we have determined that the judge did not err in approving the settlement. Accordingly, the decision of the judge is affirmed.

Does this precedent still control your case?

Ezel checks whether it still stands, including any court review since, and applies it to your situation with citations.

Opens in Ezel Pro.

  • Checks the law as it stands today, not only this page
  • Cites every source it relies on, so you can verify it
  • Chat, drafting and research in one workspace