Laura D Coal, Inc. (ALJ decision, October 14, 1994)

Laura D Coal, Inc. (FMSHRC PENN 94-238-R and PENN 94-384): Citation modified and penalty reduced to $175

Decision type
ALJ decision
Dockets
PENN 94-238-R, PENN 94-384
Decided
October 14, 1994
Presiding judge
Outcome
Modified
Precedential status
Final order, not precedent
Checked against source
2026-08-13

Apply this to your situation

This order from 1994 bound only the parties to this case; it isn't precedent. Ask about your situation and see what the current MSHA standards and Commission precedent say, with citations.

Currency note: this decision dates from 1994
The MSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Final ALJ decision, not Commission precedent
This decision became final under the 40-day rule in 30 U.S.C. § 823(d)(1) because no later Commission review appears in the official index. It binds the parties but is not Commission precedent. The full text below is from the official FMSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official FMSHRC release. The full text is the agency's own release.
Read the official release (fmshrc.gov)

Plain-English summary

Laura D Coal, Inc. contested a citation issued at the Stufft Mine and faced a proposed $1,800 civil penalty. The parties later settled the civil penalty matter, and Laura D Coal agreed to withdraw its contest. The settlement reclassified the citation from a section 104(d)(1) significant-and-substantial citation to a section 104(a) significant-and-substantial citation, affirmed it as modified, and reduced the penalty to $175. The matter was to be dismissed after payment.

Decision snapshot

  • Cited standard(s): 30 C.F.R. § 77.1000; 29 C.F.R. § 2700.31
  • Outcome: Citation No. 3711113 was modified from a section 104(d)(1) S&S citation to a section 104(a) S&S citation and affirmed as modified. The penalty was reduced from $1,800 to $175.
  • Key point: A settlement may change the statutory designation and reduce the penalty when the record supports lower negligence and the operator's good-faith compliance efforts.

Full text (FMSHRC public release)

CCASE:
LAURA D COAL INC. V. SOL (MSHA)
SOL (MSHA) V. LAURA D COAL INC.
DDATE:
19941014
TTEXT:


Page 2

~2103
FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION

OFFICE OF ADMINISTRATIVE LAW JUDGES
2 SKYLINE, 10th FLOOR
5203 LEESBURG PIKE
FALLS CHURCH, VIRGINIA 22041

LAURA D COAL, INC.,
: CONTEST PROCEEDING
Contestant :
v. : Docket No. PENN 94-238-R
: Citation No. 3711113; 2/11/94
SECRETARY OF LABOR,
:
MINE SAFETY AND HEALTH
: Stufft Mine
ADMINISTRATION (MSHA),
:
Respondent :
:
SECRETARY OF LABOR,
: CIVIL PENALTY PROCEEDING
MINE SAFETY AND HEALTH
:
ADMINISTRATION (MSHA),
: Docket No. PENN 94-384
Petitioner : A.C. No. 36-07661-03509 :
: Stufft Mine
:

DECISIONS

Appearances: John M. Strawn, Esq., Office of the Solicitor, U.S. Department of Labor, Philadelphia,
Pennsylvania, for the Respondent/Petitioner;
Joseph A. Yuhas, Esq., Barnesboro, Pennsylvania, for the Contestant/Respondent.

Before: Judge Koutras

Statement of the Proceedings

These consolidated proceedings concern a Notice of Contest filed by the Laura D Coal Company pursuant to section 105(d) of the Federal Mine Safety and Health Act of 1977, challenging the violation of mandatory safety standard 30 C.F.R. 77.1000. The civil penalty case concerns a proposed civil penalty assessment of $1,800, for the alleged violation. A hearing was held in Somerset, Pennsylvania, and the parties appeared and participated fully therein.

Issues

The issues presented in these proceedings are whether the cited conditions or practices constituted a violation of the cited safety standard; whether the alleged violation was


Page 3

~2104
"significant and substantial"; whether the alleged violation resulted from an "unwarrantable failure" to comply with the cited standard; and the appropriate civil penalty criteria found in section 110(i) of the Act.

Applicable Statutory and Regulatory Provisions

1. The Federal Mine Safety and Health Act of 1977; 30 U.S.C. 301 et seq.

2. Section 104(d), and 110(a) and (i) of the Act.

3. Commission Rules, 29 C.F.R. 2700.1 et seq.

Stipulations

The parties stipulated to the following (Tr. 9-11).

1. The Stufft Mine is owned and operated by Laura D. Coal Inc., and it is subject to the jurisdiction of the Act.

2. The presiding judge has jurisdiction in this matter.

3. The citation in question was properly issued and served by an authorized representative of the Secretary on an agent of Laura D. Coal, Inc., on the date and at the time and place stated therein, and may be admitted for the purpose of establishing its issuance.

4. The proposed civil penalty assessment will not affect Laura D Coal's ability to continue in business.

5. Laura D. Coal's, annual coal production for 1993, was 29,632 tons, and the Stufft Mine production for that year was 5,834 tons.

6. Laura D Coal, Inc., was assessed for three citations during six inspection days in the 24-month period preceding the issuance of the citation in issue in this case.

7. Laura D. Coal, Inc., is a small mine operator with a good compliance record.

8. Laura D. Coal, Inc., demonstrated ordinary good faith in obtaining compliance after the issuance of the citation.

9. The parties stipulate to the authenticity of their exhibits but not to the relevance or truth of the matters asserted therein.


Page 4

~2105
Discussion

Section 104(d)(1) "S&S" citation No. 3711113, issued at 10:00 a.m., on February 11, 1994, cites an alleged violation of 30 C.F.R. 77.1000, and the cited condition or practice states as follow:

The operator did not establish and follow a ground control plan for the safe control of all highwalls, pits and spoil banks of the active coal pit. The operator's ground control plan calls for all loose material to be removed for a safe distance from the top of the highwall and for trees to be cleared for a distance of 50 feet. The plan also calls for benches to be provided where unstable conditions exist. This highwall is about 60 feet high and 300 feet long. The top 20 to 30 feet of this is unconsolidated material consisting of large rocks, trees, and old spoil material. On 2/10/94, this material failed and slid into the 002 pit. No benches were provided and trees still exist along the top of the highwall. A review of the daily exam book indicated that solides had also occurred on 2/3/94 and 1-26-94. No appropriate action was taken to prevent more slides.

In support of the alleged violation, the Secretary presented the testimony of MSHA Inspector Mark Inspector Mark Ronan, who testified to the conditions that he observed, the reasons for issuing the citation, and his special "S&S" and "unwarrantable failure" findings (Tr. 15-114).

Laura D. Coal Company presented the testimony of its owner, James W. Stufft, who testified about the mine ground control plan and its relationship to the sediment pond that was under construction at the pit area in question. he also testified about the materials located on the spoil pile and the work being performed to remove and control this material. Mr. Stuff believed that the mine ground control plan did not apply to the pond in question because the coal that was remove from the pit was for the purpose of lining the pond with clay pursuant to State environmental guidelines (tr. 115-147).

The parties agreed to submit posthearing briefs, and without objection, the Secretary proposed to take the posthearing deposition of an expert witness, Dr. Kelvin WU, Chief of MSHA's Mine Waste and Technical Unit, Bruceton MSHA Technology Center, Pittsburgh, Pennsylvania (Tr. 155-156).


Page 5

~2106
The parties subsequently informed me that they proposed to settle the civil penalty matter, and in view of the settlement, the respondent agreed to withdraw its contest. The petitioner submitted a motion pursuant to Commission Rule 31, 29 C.F.R. 2700.31, seeking approval of the proposed settlement. In suppor of the settlement, the petitioner has submitted information pertaining to the six statutory civil penalty criteria found in section 110(i) of the Act and a full discussion and disclosure concerning the facts and circumstances surrounding the issuance of the citation.

The parties are in agreement that the respondent's negligence was not as high as initially determined. The petitioner states that it has no evidence to refute the respondent's assertion that it was not aware that its ground control plan applied to the pit in question since it was designed to serve as a pond. Further, the petitioner cannot rebut the respondent's evidence that it had taken steps to prevent employees from working under the highwall when conditions were unfavorable and that it was in the process of undercutting the spoil bank to reduce the hazard of falling material. Under the circumstance, the petitioner agrees that the section 104(d)(1) "S&S" citation should be reclassified to a section 104(a) "S&S" citation, and that a reduction of the proposed civil penalty assessment from $1,800 to $175, is warranted.

I take note of the fact that the record reflects that the respondent is a small mine operator, has a good compliance record, and demonstrated good faith in abating the violation.

Conclusion

After careful review and consideration of the pleadings, the testimony and evidence presented at the hearing, as reflected in the trial transcript, and the arguments presented in support of the proposed settlement, I conclude and find that the proposed settlement disposition is reasonable and in the public interest. Accordingly, pursuant to 29 C.F.R. 2700.31, the motion IS GRANTED, and the settlement IS APPROVED.

ORDER

In view of the foregoing, IT IS ORDERED AS FOLLOWS:

1. Section 104(d)(1) "S&S" Citation No. 3711113, February 11, 1994, citing a violation of 30 C.F.R.
77.1000, IS MODIFIED to a section 104(a) "S&S" citation, and as modified IT IS AFFIRMED.


Page 6

~2107
2. The respondent IS ORDERED to pay a civil penalty assessment in the amount of $175, in satisfaction of the violation in question. Payment is to be made to MSHA within thirty (30) days of this decision and order, and upon receipt of payment, this matter is dismissed.

George A. Koutras
Administrative Law Judge

Distribution:

Joseph A. Yuhas, Esq., 1809 Chestnut Ave., P.O. Box 25, Barnesboro, PA 15714 (Certified Mail)

John M. Strawn, Esq., Office of the Solicitor, U.S. Department of Labor, Room 14480-Gateway Building, 3535 Market Street, Philadelphia, PA 19104 (Certified Mail)

/ml

What applies to your situation today?

This order bound one employer. Ezel checks the current MSHA standards and Commission precedent against your facts, with citations.

Try Ezel Pro free for 7 days. Cancel anytime before the trial ends and you pay nothing.

  • Checks the law as it stands today, not only this page
  • Cites every source it relies on, so you can verify it
  • Chat, drafting and research in one workspace