FMSHRC ALJ decision Docket PENN 85-312 Decided June 9, 1987 Citations affirmed Judge Avram Weisberger

Alt, Incorporated

Alt, Incorporated (FMSHRC PENN 85-312): Highwall rock citation affirmed with a $500 penalty

Apply this to your situation

This order from 1987 bound only the parties to this case; it isn't precedent. Ask about your situation and see what the current MSHA standards and Commission precedent say, with citations.

Currency note: this decision dates from 1987
The MSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Final ALJ decision, not Commission precedent
This decision became final under the 40-day rule in 30 U.S.C. § 823(d)(1) because no later Commission review appears in the official index. It binds the parties but is not Commission precedent. The full text below is from the official FMSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official FMSHRC release. The full text is the agency's own release.
Read the official release (fmshrc.gov)

Plain-English summary

Alt operated the Iselin surface coal mine, where MSHA found a large overhanging rock near the top of a highwall. Judge Avram Weisberger found that the operator violated 30 C.F.R. § 77.1001 by failing to strip loose hazardous material a safe distance from the highwall. He found the violation significant and substantial and caused by unwarrantable failure because mine personnel knew or should have recognized the hazard. The citation was affirmed and a $500 civil penalty was assessed.

Decision snapshot

  • Cited standard: 30 C.F.R. § 77.1001
  • Outcome: Citation 2409178 was affirmed and a $500 civil penalty was assessed.
  • Key point: A known, cracked rock hanging over a highwall must be removed or otherwise stripped back before workers operate below it.

Full text (FMSHRC public release)

CCASE:
SOL (MSHA) V. ALT, INC.
DDATE:
19870609
TTEXT:


Page 2

~1079
Federal Mine Safety and Health Review Commission
Office of Administrative Law Judges

SECRETARY OF LABOR, CIVIL PENALTY PROCEEDING
MINE SAFETY AND HEALTH
ADMINISTRATION (MSHA), Docket No. PENN 85-312
PETITIONER A.C. No. 36-06352-03505

          v.                       Iselin Mine

ALT, INCORPORATED,
RESPONDENT

                                 DECISION

Appearances: Mark Swartz, Esq., Office of the Solicitor,
U.S. Department of Labor, Philadelphia,
Pennsylvania, for the Petitioner;
Donald P. Tarosky, Esq., Greensburg,
Pennsylvania, for the Respondent.

Before: Judge Weisberger

                          Statement of the Case

 The Secretary (Petitioner) filed a petition for Assessment

of Civil Penalty for an alleged violation by Respondent of 30
C.F.R. 77.1001. Pursuant to notice the case was heard in
Pittsburgh, Pennsylvania, on March 12, 1987. Wendell A. Hill
testified for Petitioner, and Harold Altmire and Jay Altmire
testified for the Respondent.

 Petitioner, at the onset of the hearing, made a motion to

disallow Respondent from introducing evidence on the issues of
"significant and substantial" and "unwarrantable failure."
Decision was reserved to allow the Parties to brief this issue.

 Petitioner filed its posthearing brief on May 7, 1987, and

Respondent filed its brief on May 13, 1987.

                               Stipulations

    The Parties have stipulated as follows:

         1. Alt, Incorporated owned and operated the Iselin Mine
         on May 5, 1985, and is subject to the jurisdiction of
         the Federal Coal Mine Safety and Health Act of 1977,
         Public Law 91Ä173, as amended by Public Law 95Ä164
         (Act).

Page 3

~1080
2. Alt, Incorporated owned and operated the Iselin Mine as of
November 19, 1984.

      3. The Iselin Mine is a surface coal mine and is
      subject the regulations found at 30 C.F.R., Part 77.

      4. The Administrative Law Judge has jurisdiction over
      this proceeding pursuant to section 105 of the 1977
      Act.

      5. A copy of Citation Number 2409178 (attached to the
      Petition for Adjudication (sic.) of Civil Penalty) is
      an authentic copy of the original citation.

      6. The Parties stipulate to the authenticity and
      admissibility of the following documents:

           a. A copy of Citation Number 2409178 issued by
           Wendell E. Hill on May 15, 1985.

           b. A copy of the inspector's notes prepared by
           Wendell E. Hill concerning his May 15, 1985
           inspection of the Iselin Mine.

      7. During the period from November 19, 1984 through May
      14, 1985, the Alt, Incorporated Iselin Mine had a
      history of one assessed and paid violation: 104(a)
      Citation Number 2408087 issued on February 1, 1985,
      with an assessment of $20.00.

      8. The assessment of $500 penalty in this matter will
      not affect the Respondent's ability to continue in
      business.

      9. Currently, there is no production at the Iselin
      Mine.

                             Issues

 The issues are whether the Respondent violated 30 C.F.R.

77.1001 and, if so, whether that violation was of such a nature
as could significantly and substantially contribute to the cause
and affect of a mine safety or health hazard, and whether the
alleged violation was the result of the Respondent's
unwarrantable


Page 4

~1081
failure. If section 77.1001, supra, has been violated, it will be
necessary to determine the appropriate civil penalty to be
assessed in accordance with section 110(i) of the Federal Mine
Safety and Health Act of 1977, 30 U.S.C. 801 et. seq., (the
"Act").

                            Citation

 Citation 2409178, issued on May 15, 1985, alleges a

significant and substantial violation in that "loose hazardous
material was not placed for a safe distance from the top of the
highwall there was a piece of rock 10 feet long, 5 and 1/2 feet
wide, and 8 to 12 inches thick that had not been removed."

                           Regulation

 30 C.F.R.   77.1001, as pertinent, provides as follows:

"Loose hazardous material shall be stripped for a safe distance
from the top of pit or highwalls. . . ."

Findings of Facts and Conclusions of Law

                               I

 On May 15, 1985, Wendell A. Hill, MSHA Inspector, with over

13 years of experience as an inspector, arrived at Respondent's
Iselin Mine (a surface mine) to make a complete inspection. While
in the pit, Hill observed a rock overhanging, or jutting out from
the top of the highwall. He estimated the size of the overhanging
rock to be 6 feet long, 5 and 1/2 feet wide, and 8 to 10 inches
thick. He told the two miners, who were working in the pit, to
stay clear of the rock. He then proceeded to the top of the
highwall to make a closer examination of the rock. He observed a
crack 2 or 3 feet from the tip of the rock. He testified that
there was no dirt or other material on top of the rock that was
jutting out. Hill described the rock as sand rock and estimated
its weight to be more than a ton. Hill brought the rock to the
attention of the Respondent's President, Harold Altmire, and
indicated that it should be taken down. Altmire agreed to
cooperate, and made a road to the top of the highwall so that a
backhoe could be driven there to remove the rock. Jay Altmire, a
miner employed by Respondent, took the backhoe to the top of the
highwall to remove the rock. Hill testified that he stood off to
the side approximately 6 feet from the highwall when the backhoe
was removing the rock. It was further his testimony that no dirt
had to be removed from the top of the rock and that it was only
necessary to remove soil from behind the rock. He further stated
that when the bucket of the backhoe initially touched the back of
the rock, which was lying on solid ground, the tip fell off. He
estimated that it took approximately 30 seconds for the backhoe
to dislodge and push the rock


Page 5

~1082
down the highwall. When Hill returned to the pit, he measured two
large pieces of rock that had fallen down as being 6 feet long, 5
and 1/2 feet wide, and 8 to 10 inches thick, and 3 feet wide, 4
feet long, and 8 to 12 inches thick respectively. He indicated
that the latter rock was the piece that had broken off when the
bucket of the backhoe touched the rock.

 Hill offered his opinion that prior to its removal the rock

was loose as it was overhanging the highwall and there were no
rocks on top of it. He also opined that it could have been shaken
loose by vibrations from equipment present at the mine or from
thunderstorms. He also testified, in essence, that rain could
have washed out the dirt around the rock and caused it to fall.

 Harold Altmire, who has over 25 years experience running

open pit mining operations, testified that the rock at issue had
been in the same position for about 5 or 6 days prior to May 15,
1985. He stated, in contrast to Hill, that when he saw the rock
during a preshift examination on May 15, 1985, he was about 12
feet away and did not see any cracks in it. He testified that
when he observed the rock from the pit that it was not extended
over the edge of the pit. He also said that there was rock, soil,
dust, and clay on top of the rock in question and that in
addition it was covered by another rock. All these observations
were corroborated by Jay Altmire, who further testified, in
contrast to Hill, that the latter was not present when he
operated the backhoe, and that it took him (Jay Altmire)
approximately 4 minutes to remove the dirt from the rock and push
it off the highwall. Harold Altmire also testified that after
Hill told him to remove the rock, the latter drove up the haul
road and returned after the rocks were removed. Jay Altmire
testified that about a week prior to May 15, his brother tried to
remove the rock with a dozer and could not. Harold Altmire
testified that in his opinion the rock was not in any danger of
falling. He said that if he thought there was any danger of the
rock falling, that he would have removed it as he would not have
wanted to cause any injury to his two sons who were the only
miners working below in the pit.

 Harold Altmire's testimony with regard to the condition of

the rock was corroborated by the testimony of his son Jay. The
latter's testimony that Hill was not present when he (Jay
Altmire) removed the rock finds some corroboration in the
testimony of Harold Altmire. However, I have adopted that version
testified to by Hill. There was no motive adduced which would
tend to impeach the credibility of Hill's testimony. On the other
hand, the father-son relationship between Respondent's only two
witnesses, tends, to some extent, to dilute the corroborative
nature of their testimony. Moreover, the veracity of Hill's
testimony is but


Page 6

~1083
tressed by the existence of contemporaneous notes that he made of
his inspection. In a note, which, according to his testimony, was
written when he observed the rock from the pit, he described the
rock as being 6 feet long, 5 and 1/2 feet in width, and 8 to 12
inches thick, and being "at top of highwall edge" (emphasis
added). (Government Exhibit 2, page 5.) Also, on pages 8Ä9, of
Government Exhibit 2, there are contemporaneous statements by
Hill that "once the backhoe was in place at the top of the
highwall the piece of crack 3 feet wide by 4 feet by 8 to 12
inches thick broke off and rolled into the pit." Page 7, of
Government Exhibit 2, contains a contemporaneous statement that
it took the backhoe 30 seconds to move the rock. Also, I find
Hill's description of the rock more reliable. When he observed it
on May 15, from the top of the highwall, he was only 6 feet from
the rock and examined it specifically as he was apparently
concerned about its condition when he had observed it from the
pit. In contrast, although Harold Altmire had seen the rock prior
to May 15, when he saw it on that date he was 12 feet away, and
observed it in the course of his general examination. Inasmuch as
his attention had not been specifically drawn to the rock, in
contrast to Hill, it is concluded that Altmire's examination of
the rock on May 15 was not as thorough as that of Hill's.

 Accordingly, based on the testimony of Hill, I conclude that

on May 15, 1985, there was a portion of rock, approximately 6
feet long, 5 and 1/2 feet wide, and 8 to 12 inches thick, with a
crack in the tip, that was hanging over the top of the highwall.
I also conclude, based on the testimony of Hill, that there were
no rocks or other material on top of this portion of the rock.
Based upon these conditions, I conclude that the rock was "loose"
and was within the purview of section 77.1001, supra. In reaching
this conclusion I took into account the plain meaning of the term
"loose" as defined in Webster's New Collegiate Dictionary as
follows: "la: not rigidly fastened or securely attached b (1):
having worked partly free from attachments. . . ."

 Although Harold Altmire indicated that, in his opinion, the

rock was safe, he did not specifically rebut any of Hill's
opinions that the rock could have been shaken loose by
vibrations, or washed out by rain water. Accordingly, I find that
the rock in question constituted a "hazardous" material within
the purview of section 77.1001, supra. This conclusion is further
buttressed by Hill's testimony, which I previously adopted, that
the rock had a crack in it, and when initially touched by the
bucket of the backhoe, resulted in the tip breaking off and
falling down to the pit. Thus, I find that section 77.1001,
supra, has been violated.

                               II

  Although Respondent did not contest the citation herein

within 30 days, I find good cause to excuse Respondent, based
upon the testimony for Altmire, that when the section 104(d)(1)
order


Page 7

~1084
was terminated on May 15, 1985, he assumed that the matter had
been resolved. Petitioner has not alleged that it has suffered
any legal prejudice in Respondent's being allowed to present
evidence on the issues of "significant and substantial" and
"unwarrantable failure." In these circumstances, I find 29 C.F.R.
2700.22 to be controlling, in that the Respondent should not b
precluded from challenging the findings, in the citation, of
"significant and substantial" and "unwarrantable failure."
Accordingly, I deny Petitioner's motion to disallow Respondent
from introducing evidence on the issues of "significant and
substantial" and "unwarrantable failure."

                              III

 Respondent has argued that, considering the testimony of its

witnesses, there is no basis for a finding of "significant and
substantial." However, applying the criteria set forth by the
Commission in Mathies Coal Company, 6 FMSHRC 1 (January 1984), I
find, based upon the testimony of Hill, that I found reliable,
that section 77.1001, supra, has been violated and that the
violation herein constituted a discrete safety hazard.
Furthermore, concerning the dimensions of the rock, and its
characterization as sand rock, as testified to by Hill, and
considering that this rock has a weight of about 150 pounds per
cubic foot, as indicated by Government Exhibit 4, page 18, I
conclude that there was a reasonable likelihood that in the event
of the rock falling there would be an injury, of a reasonably
serious nature, to either of the two miners, who were working in
the area. In this connection, I note the testimony of Jay Altmire
that he was working throughout the area of the pit unprotected,
and it was the uncontradicted testimony of Hill that rock falling
down the highwall into the pit could have bounced through the
window of the equipment being operated by John Altmire causing
serious injury. Accordingly, based on the above, I conclude that
the nature of the violation herein was "significant and
substantial."

                               IV

 Respondent has argued that any alleged violation was not due

to its "unwarrantable failure", as Altmire testified that a State
Inspector, who inspected the subject mine on May 10, 1985, did
not mention the hazard of the rock. Nor did the latter cite
Respondent for the alleged condition. I did not place much weight
on the conclusions of the inspector, a person who did not
testify. Further, the written State Inspection Report,
Respondent's Exhibit 2, does not indicate that the subject rock
was specifically examined.


Page 8

~1085
In essence, it was the testimony of both Harold Altmire and Jay
Altmire that they were aware of the existence of the rock prior
to May 15. Harold Altmire even saw the rock when he made his
preshift examination on May 15, 1985. Accordingly, I conclude
based, on the testimony of Hill, that a close examination of the
rock by either of Respondent's witnesses, as performed by Hill,
would have revealed a crack in the rock and the fact that the
rock was hanging over the highwall. Thus, I conclude that the
violation herein resulted from Respondent's "unwarrantable
failure."

                               V

 Having considered the criteria in section 110 of the Act,

supra, and considering the Respondent's high degree of negligence
and the seriousness of the violation, I conclude that the penalty
of $500, as proposed by Petitioner, is appropriate.

                             ORDER

 It is ORDERED that Respondent pay the sum of $500, within 30

days of the date of this decision, as a civil penalty for the
violation found herein.

                              Avram Weisberger
                              Administrative Law Judge

Get today's answer for your situation

You just read what one judge decided for one employer in 1987, and it binds only those parties. Ezel checks the current MSHA standards and Commission precedent and answers your specific situation, with citations.

Opens in Ezel Pro. Every answer cites the authority it relies on.