Secretary of Labor v. Trent Coal, Inc. (ALJ decision, January 3, 1985)

Secretary of Labor v. Trent Coal, Inc. (FMSHRC PENN 84-192): $6,000 roof control settlement approved

Decision type
ALJ decision
Docket
PENN 84-192
Decided
January 3, 1985
Presiding judge
Outcome
Settled
Precedential status
Final order, not precedent
Checked against source
2026-10-20
Cited standards

Apply this to your situation

This order from 1985 bound only the parties to this case; it isn't precedent. Ask about your situation and see what the current MSHA standards and Commission precedent say, with citations.

Currency note: this decision dates from 1985
The MSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Final ALJ decision, not Commission precedent
This decision became final under the 40-day rule in 30 U.S.C. § 823(d)(1) because no later Commission review appears in the official index for this docket. It binds the parties but is not Commission precedent. The full text below is from the official FMSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official FMSHRC release. The full text is the agency's own release.
Read the official release (fmshrc.gov)

Plain-English summary

MSHA cited Trent Coal at its Hritz Mine for failing to follow an approved roof control plan while preparing to extract a pillar. A long crack had been found in the roof; a roof fall in the cited area killed two miners. Chief Judge Paul Merlin found the violation extremely serious and the company highly negligent, while also considering its small size, prior violation history, and prompt correction. He approved a $6,000 settlement, the same amount MSHA originally assessed. Because Trent had already paid, the judge dismissed the case.

Decision snapshot

  • Cited standard: 30 C.F.R. § 75.200, compliance with the approved roof control plan.
  • Outcome: $6,000 settlement approved and paid; case dismissed.
  • Key point: The judge upheld a substantial settlement amount while weighing the serious roof control violation against the operator's size and history.

Full text (FMSHRC public release)

CCASE:
SOL (MSHA) V. TRENT COAL
DDATE:
19850103
TTEXT:
~5
Federal Mine Safety and Health Review Commission Office of Administrative Law Judges

SECRETARY OF LABOR,
CIVIL PENALTY PROCEEDING
MINE SAFETY AND HEALTH
ADMINISTRATION (MSHA),
Docket No. PENN 84-192
PETITIONER
A.C. No. 36-01471-03513

v. Hritz Mine
TRENT COAL, INC.,
RESPONDENT

DECISION APPROVING SETTLEMENT

Before: Judge Merlin

The Solicitor has filed a motion to approve a settlement for the one violation involved. The originally assessed amount was $6,000 and the proposed settlement is for $6,000.

The citation was issued for a violation of 30 C.F.R.
75.200 because the operator had not complied with the approved roof control plan which provides that before splitting is started on any pillar, all safely accessible roof and its entire perimeter shall be examined, and that if any roof defect is found at any place within the perimeter, full overhead support shall be installed as mining progresses. In this case a crack was detected at the pillar which was to be extracted. The crack extended for approximately 160 feet. The operator did not consider the crack to be a defect since the area was roof bolted, although not fully bolted. A roof fall occurred in the cited area resulting in two fatalities.

Based upon the foregoing information in the Solicitor's motion, I find the violation was of the utmost gravity and that the operator was highly negligent.

The Solicitor further advises that the operator had 16 assessed violations during the 24 month period preceding issuance of the subject citation. The period included 100 inspection days. Thus, the operator had a violation per inspection day ratio of 0.16 which according to the Solicitor represents a relatively favorable history of previous violations.
~6
The Solicitor also states the operator and the mine had an annual production tonnage of 45,144, which indicates that the mine is relatively small and that the controlling entity is extremely small. The operator demonstrated good faith by achieving rapid compliance after notification of the violation. The cited area was abandoned and mining operations were begun one row of pillars inby the cited area. Employees were reinstructed concerning the approved roof control plan. Finally, the operator has paid the proposed penalty and continued its operations.

After a careful review of this matter I approve the settlement as appropriate under the six statutory criteria set forth in section 110(i) of the Act. Gravity and negligence call for a most substantial penalty. But the operator's small size and good history must be taken into account. The proposed settlement which is a high penalty for this operator represents a proper weighing of the statutory elements.

Accordingly the proposed settlement is Approved and the operator having paid this case is Dismissed.

Paul Merlin
Chief Administrative Law Judge

What applies to your situation today?

This order bound one employer. Ezel checks the current MSHA standards and Commission precedent against your facts, with citations.