Secretary of Labor (MSHA) v. Rushton Mining Company (ALJ decision, August 20, 1981)
Rushton Mining Company (FMSHRC PENN 81-24): Five roof control matters settled for $22,000
Apply this to your situation
This order from 1981 bound only the parties to this case; it isn't precedent. Ask about your situation and see what the current MSHA standards and Commission precedent say, with citations.
Plain-English summary
MSHA and Rushton Mining Company settled four roof control orders and a citation arising from conditions at the Rushton Mine, including matters examined after a fatal roof fall. The judge approved a total of $22,000 in penalties, reduced from MSHA's initial $35,000 assessment. The parties said two roadway width orders overlapped and that those widths did not contribute to the fatality. MSHA also cited lower negligence estimates for the other matters, including the operator's response to state inspector instructions and its roof support work. The judge ordered payment of the agreed amount within 30 days.
Decision snapshot
- Cited standards: 30 C.F.R. §§ 75.201-1(b), 75.200, and 75.201, roof control requirements.
- Outcome: Settlement approved for five violations; $22,000 total penalty.
- Key point: The judge accepted reduced penalties based on overlapping orders and the circumstances described in the parties' settlement.
Full text (FMSHRC public release)
FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION OFFICE OF ADMINISTRATIVE LAW JUDGES
2 SKYLINE, 10th FLOOR
5203 LEESBURG PIKE
FALLS CHURCH, VIRGINIA 22041
AUG 20 1981
SECRETARY OF LABOR,
: Civil Penalty Proceeding
MINE SAFETY AND HEALTH
:
ADMINISTRATION (MSHA),
: Docket No. PENN 81-24
Petitioner : A.C. No. 36-00856-03037F
v. :
: Rushton Mine
RUSHTON MINING COMPANY,
:
Respondent :
DECISION APPROVING SETTLEMENT
The parties have reached a settlement of the five violations involved in the above docket in the total sum of $22,000. MSHA's initial assessment therefor was $35,000. The terms of the settlement are as follows:
Citation/Order Number Original Assessment Compromised Settlement
615758 $ 2,000 $ 750
802229 10,000 6,500
802230 10,000 6,500
802228 10,000 7,000
802232 3,000 1,250
$35,000
$22,000
The reductions from the original assessment appear warranted.
1. Order No. 615758 was issued for a violation of 30 C.F.R. § 75.201-1(b) and originally involved a penalty assessment by MSHA of $2,000. In conjunc- tion with this order, section 104(d)(2) Order No. 802229 was issued for a vio- lation of 30 C.F.R. § 75.200 for which Respondent was initially assessed a penalty of $10,000. These two orders were both assessed for excessive roof- control widths. The first order was issued because no additional support was provided as required by the regulation. The inspector observed that for 350 to 400 feet, the width of the area was 21 to 24 feet instead of 20 feet as required by the regulation. The second violation, of drawings 7, 8, and 9 of the approved roof-control plan, was issued because the plan requires the roadway to be limited to 16 feet in width. These two violations were issued for the same length of roadway. Therefore, they duplicate each other. Accordingly, it is appropriate to reduce these penalties. Although these orders were issued in the course of a fatality investigation, it is conceded
1948
by MSHA that the excessive widths did not contribute to the fatality. The fatality occurred during pillaring operations. This area had been developed many years before. When it was developed, the widths did not have to be nar- rowed as currently required. The Respondent mine operator was in the process of adding additional support to this roadway. The operator had not yet started pillaring the area. The approved roof-control plan provides, in relevant part, that roadways must be narrowed to 16 feet where pillaring is being done. How- ever, as stated above, pillaring was not yet being performed. Rather, the operator was adding additional support to the entries surrounding the pillars and MSHA concedes that the operator was not unreasonable in interpreting the plan to allow additional support to be installed prior to narrowing the road- way. Additionally, MSHA indicates that the operator did intend to narrow the roadway after adding the additional support. Accordingly, because the two orders duplicate each other, because MSHA concedes it initially overevaluated the operator's negligence, and since this violation did not contribute to the fatality which occurred, penalties of $750 and $6,500, respectively, as agreed upon by the parties, are approved.
2. Order No. 802230 was issued for a violation of 30 C.F.R. § 75.201.
MSHA originally assessed a penalty of $10,000., MSHA has submitted the fatality investigation report relevant to this order. As MSHA points out, this report has in it a sketch of a mine map showing the section as it appeared when the fatality occurred. The Respondent operator was in the course of pillar recovery. It had begun pillaring in sequence along one row. Thereafter, it left several blocks of coal unmined due to bad roof surrounding the area. It then continued mining this same row of pillars. Upon completion of this row, the operator moved one row outby and began pillaring across the entries. At this point, the operator did not intend to go back inby to remove the pillars it had omitted. MSHA concedes that this is an acceptable mining method, i.e., where the operator believes that it is unsafe to mine certain pillars, the operator may omit those pillars provided it continues in sequence from that point. However, the state mine safety and health inspectors disagree with the Federal Government's position. The day prior to the fatality, the state inspectors were in the mine. They told the operator that it was neces- sary to return inby to the three pillars that had been omitted. Thus, the operator was required to add additional support throughout the area going toward the pillars that had orginally been omitted. These particular pillars are designated as Nos. 6, 7, and 8 on the sketch provided by MSHA. By mining in this fashion, that is, going partially through one row then going outby another row and then returning inby, the operator failed to maintain a uniform pillar line. This is a violation of 30 C.F.R. § 75.201 and exposed miners to unusual dangers because it is, according to MSHA, a faulty pillar recovery method. This contributed to the accident as it caused excessive heaviness in an area of already poor roof. Accordingly, because the operator was following the instructions of the state inspector, MSHA concedes that the operator's negligence was initially overevaluated. MSHA also indicates that if this matter was to proceed to hearing, an expert witness for Respondent would testify that mining in this fashion does not create pillar points and is not less safe then mining straight across. Accordingly, the reduction to $6,500 is approved.
1949
3. Order No. 802228 was originally assessed at $10,000. It involved a fatality. The operator was adding additional support to a developed entry in the course of pillaring operations. Respondent's old roof-control plan did not require 4-foot centers nor as extensive a bolting pattern as required by the current plan. The victim, who was a bolter helper, and the bolter himself were in the process of installing additional supports in accordance with the new plan when the fall occurred. MSHA indicates that there is a dispute as to whether this was spot bolting or rebolting. In either case, MSHA concedes the operator was acting in good faith. MSHA also concedes that the operator was taking extensive measures to make sure that this potentially dangerous area was given care. It is also significant to note that during this additional bolting stage, the section foreman told the bolters to be sure to make the roof safe by doing whatever was necessary. At first, 6-foot bolts were being used. When it was determined that this may not be sufficient, 8-foot bolts and metal straps were used. One of these straps was already in and more were to be inserted when the accident occurred. For these reasons, MSHA concedes that the degree of the operator's negligence was not high. The reduction to $7,000 appears appropriate and is approved.
4. Citation No. 802232 was issued for a violation of 30 C.F.R. § 75.200.
The citation charges the operator with not adequately training its bolting per- sonnel in compliance with safety precaution No. 2 of the plan. MSHA indicates that the object of this citation was to charge the operator with not properly instructing its bolters on "rebolting" requirements. However, the bolter felt, and the operator agreed, that "spot" bolting was being conducted. MSHA con- cedes that this discrepancy does not indicate inadequate training, but rather the inherent conflict between what spot bolting and rebolting actually are. MSHA concedes the operator's negligence is lower than initially evaluated. The agreed-on penalty of $1,250 is approved.
ORDER
Respondent, if it has not previously done so, is ORDERED to pay the stipulated penalties totaling $22,000 to the Secretary of Labor within 30 days from the issuance date of this decision.
Michael A. Lasher, Jr., Judge
Distribution:
Barbara K. Kaufmann, Esq., Office of the Solicitor, U.S. Department of Labor, 3535 Market Street, Room 14480, Philadelphia, PA 19104 (Certified Mail)
Timothy M. Biddle, Esq., Crowell & Moring, 1100 Connecticut Avenue, N.W., Washington, DC 20036 (Certified Mail)
1950
What applies to your situation today?
This order bound one employer. Ezel checks the current MSHA standards and Commission precedent against your facts, with citations.
Opens in Ezel Pro.
- Checks the law as it stands today, not only this page
- Cites every source it relies on, so you can verify it
- Chat, drafting and research in one workspace