Buck Creek Coal Inc. (Commission decision, March 15, 1995)

Buck Creek Coal Inc. (FMSHRC LAKE 94-72): Interlocutory petition held in abeyance

Decision type
Commission decision
Docket
LAKE 94-72
Decided
March 15, 1995
Outcome
Procedural
Precedential status
Citable Commission precedent
Checked against source
2026-08-13
Cited standards

Apply this precedent to your situation

This is citable Commission precedent from 1995, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.

Currency note: this decision dates from 1995
The MSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Decision of the Commission
This is an interlocutory order in a pending Federal Mine Safety and Health Review Commission proceeding. It does not finally resolve the case or provide a final Commission decision for judicial review under 30 U.S.C. § 816. The full text below is from the official FMSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official FMSHRC release. The full text is the agency's own release.
Read the official release (fmshrc.gov)

Plain-English summary

Buck Creek Coal asked the Commission to review an ALJ order continuing a stay in proceedings involving hundreds of citations and orders while a criminal prosecution was pending. The Secretary argued that interlocutory review was unavailable because the judge had not certified the ruling and had not denied a certification motion. The Commission held its ruling in abeyance until the judge decided Buck Creek's pending certification motion. The order did not decide the underlying citations or the merits of the stay.

Decision snapshot

  • Cited authority: 29 C.F.R. § 2700.76(a)(1)
  • Outcome: The Commission held Buck Creek's interlocutory-review petition in abeyance pending the ALJ's determination on certification.
  • Key point: Commission interlocutory review requires the procedural conditions in Rule 76 to be met before the Commission rules on the petition.

Full text (FMSHRC public release)

FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION 1730 K STREET N.W., 6TH FLOOR
WASHINGTON, D.C. 20006

March 15, 1995

SECRETARY OF LABOR,
:
MINE SAFETY AND HEALTH
:
ADMINISTRATION (MSHA)
:
:
v. : Docket Nos. LAKE 94-72, etc.
:
BUCK CREEK COAL INC.
:

ORDER

On February 17, 1994, Buck Creek Coal Inc. (ABuck Creek@) filed with the Commission a petition for interlocutory review of Administrative Law Judge T. Todd Hodgdon=s February 15, 1995, Order Continuing Stay (the AStay Order@). The judge had previously stayed proceedings for ninety days or until the United States Attorney made a determination regarding the criminal prosecution of Buck Creek. See Buck Creek Coal Inc., 17 FMSHRC
(February 1995) (Operator=s petition for interlocutory review of the previous stay dismissed as moot). The Stay Order continues the stay until May 16, 1995, and directs the parties to attend a status conference on that date for the purpose of deciding whether and under what conditions the stay should be continued. Stay Order at 5.

Buck Creek urges the Commission to grant interlocutory review and relief from the Stay Order so that it can begin to defend itself against the 554 citations and orders in these consolidated dockets. Pet. at 4. The Secretary responds that Commission Procedural Rule 76(a)(1), 29 C.F.R. ' 2700.76(a)(1),1 precludes our granting interlocutory review because the

1
Rule 76 states in part:

(a) Procedure. Interlocutory review by the Commission shall not be a matter of right but of the sound discretion of the Commission.
(1) Review cannot be granted unless;
(i) The Judge has certified, upon his own motion or the motion of a party, that his interlocutory ruling involves a controlling question of law and that in his opinion immediate review will materially advance the final disposition of the proceeding; or

(ii) The Judge has denied a party=s motion for certification of the interlocutory ruling to the Commission, and the party files with the Commission a petition for interlocutory review within 30


Page 2

judge has not certified his ruling, nor has he denied Buck Creek=s motion for certification. Opp=n at 3-4. In reply, Buck Creek urges the Commission to construe the Stay Order as an ongoing denial of Buck Creek=s previously-filed petition for interlocutory review. Reply at 2. Buck Creek asserts in the alternative that application to the judge for certification would be futile and therefore should not be required. Buck Creek notes that it has now filed a motion for certification with the judge. Id. at 2-3 & n.2.

Rule 76 provides that interlocutory review cannot be granted unless the judge has certified his interlocutory ruling to the Commission or has denied a party=s motion for certification. We conclude that it would be inappropriate to rule on the Secretary=s procedural argument in advance of the judge=s determination of Buck Creek=s pending motion.

Accordingly, we hold in abeyance our ruling on Buck Creek=s petition pending the judge=s determination of the motion for certification. Cf. Emery Mining Corp., 11 FMSHRC 1, 3 (January 1989).

Mary Lu Jordan, Chairman

Joyce A. Doyle, Commissioner

Arlene Holen, Commissioner

Marc Lincoln Marks, Commissioner

days of the Judge=s denial of such motion for certification.

2

Does this precedent still control your case?

Ezel checks whether it still stands, including any court review since, and applies it to your situation with citations.

Opens in Ezel Pro.

  • Checks the law as it stands today, not only this page
  • Cites every source it relies on, so you can verify it
  • Chat, drafting and research in one workspace