Secretary of Labor v. Hibbing Taconite Company
Secretary of Labor v. Hibbing Taconite Company (FMSHRC LAKE 2013-231-RM, et al.): Arbitrary abatement deadlines invalidate withdrawal orders
Apply this precedent to your situation
This is citable Commission precedent from 2016, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.
Plain-English summary
MSHA issued four section 104(b) withdrawal orders after Hibbing Taconite did not finish correcting three housekeeping violations and a damaged fan housing by 8:00 a.m. the morning after the citations. The inspector used the same next-morning deadline to prompt quick action even though some conditions needed several days to correct and another needed only minutes. The Commission held that the Mine Act requires an abatement time based on the work reasonably needed for each cited condition. Because the uniform deadlines were arbitrary and reflected a misunderstanding of the law, the Commission reversed the judge and vacated all four withdrawal orders.
Decision snapshot
- Cited standards: 30 C.F.R. §§ 56.14100(b), 56.20003(a), 56.20003(b)
- Outcome: Four section 104(b) failure-to-abate withdrawal orders were vacated.
- Key point: An inspector must set each abatement deadline from the time reasonably required to correct that particular condition, not use a uniform deadline merely to force immediate action.
Full text (FMSHRC public release)
FEDERAL MINE SAFETY AND HEALTH
REVIEW COMMISSION
1331
PENNSYLVANIA AVENUE, NW, SUITE 520N
WASHINGTON,
D.C. 20004-1710
SECRETARY OF LABOR, : Docket Nos. LAKE
2013-231-RM
MINE SAFETY AND HEALTH : LAKE
2013-232-RM
ADMINISTRATION (MSHA) : LAKE
2013-233-RM
: LAKE
2013-234-RM
v. : LAKE
2013-348-M
:
HIBBING
TACONITE COMPANY :
BEFORE: Jordan, Chairman; Young, Cohen, Nakamura, and Althen,
Commissioners
DECISION
BY THE COMMISSION:
In this consolidated contest and civil penalty
proceeding, arising under the Federal Mine Safety and Health Act of 1977, 30
U.S.C. § 801 et seq. (2012) (“Mine Act” or “Act”), a Commission Administrative
Law Judge sustained four orders which were issued to Hibbing Taconite Company pursuant
to section 104(b) of the Mine Act.[1] The orders were issued by
the Department of Labor’s Mine Safety and Health Administration (“MSHA”)
because of Hibbing Taconite’s failure to abate three housekeeping violations
and one violation that alleged a failure to maintain a fan housing. 35 FMSHRC
2535, 2553 (Aug. 2013) (ALJ). Hibbing Taconite asserts that the inspector
abused his discretion in issuing the orders. For the reasons discussed more
fully below, we vacate the failure to abate orders on the basis that the inspector
abused his discretion by setting arbitrary times for abatement of the
underlying citations.
I.
Factual and Procedural Background
Hibbing Taconite operates a large plant in St.
Louis County, Minnesota. The plant produces taconite pellets by filtering
powder material, forming it into small balls, and hardening the balls through
an indurating process.[2] The facility has multiple
levels and sublevels, some of the floors between levels are grates, and the
bottom floor is cement. There is regular spillage, and material from the upper
levels falls to the lower levels, including while the upper levels are hosed
down during the cleaning process. During the week, approximately 50 miners work
at the plant, while during the evenings and weekends, an operating crew of
approximately eight or nine miners works at the plant.
Beginning on December 12, 2012, an MSHA
inspector, Thaddeus Sichmeller, inspected the plant and, over the course of a
few days, issued various citations and the subject orders. As stated more particularly
below, the inspector verbally issued citations each day based on conditions he
observed. On each following day, upon arriving at the mine, the inspector
issued the written version of the citations he had verbally issued the day
before, and reexamined the cited areas.
At approximately 5:30 p.m. on
December 12, Inspector Sichmeller issued a verbal citation for a significant
and substantial (“S&S)[3] violation of 30 C.F.R. §
56.20003(a)[4] for conditions he
observed inside the 505 mandoor of the pellet plant. 35 FMSHRC at 2538; Tr. 99.
Inspector Sichmeller believed that a housekeeping violation existed because
there were pellets, entangled hoses, and slurry in the walkway near a conveyor,
and that those conditions created slip and fall hazards. Tr. 28, 31-32.
The following morning, December 13, the
inspector returned to the mine to continue the inspection. He was accompanied
by the operator’s safety representative of the pellet plant, Tiara Marcus. The
inspector then issued the written versions of the verbal citations he had
issued on December 12, including Citation No. 8665946 for the violation of
section 56.20003(a). Citation No. 8665946 set forth an abatement time of 8:00
a.m. that morning. Upon re-inspecting the cited area, the inspector verbally
issued an extension to abate the citation because he observed miners cleaning
the area and progress had been made. Tr. 37.
At approximately 10:30 or 11:00 the
following morning, Friday, December 14, the inspector arrived and met with safety
representative Marcus, and Tim Angelo, the pellet plant’s operations manager,
among others. Tr. 116. At that meeting, the operator received the written
extension for Citation No. 8665946, which had an abatement time of 8:00 a.m. In
addition, they discussed the citation and Angelo’s concerns about the abatement
times set by the inspector. Tr. 116. Inspector Sichmeller explained that he was
setting short abatement times in order to get immediate corrective action. Tr.
70.
The inspector continued his
inspection, and traveled to the cited area. Upon re-inspecting the area, the
inspector verbally issued another extension of time to abate the condition
because, although progress had been made, more corrective action needed to be taken.
Tr. 38.
In addition, the inspector issued
other verbal citations. As relevant to this proceeding, on December 14, the
inspector issued a verbal citation (later written as Citation No. 8665957) alleging
a housekeeping violation of section 56.20003(b)[5] because he observed an
accumulation of wet slurry and taconite pellets on the north walkway of the
scrubber pump area. The inspector considered the violation to be non-S&S
because the scrubber pump was down for maintenance and the condition did not
extend the entire width of the walkway.
That same day, Inspector Sichmeller
issued another verbal citation for a housekeeping violation of section
56.20003(a) (later written as Citation No. 8665959) because he observed an
accumulation of taconite pellets in an area that was about 8x8 feet and 3 to 4
inches deep in front of an electrical disconnect. He believed the condition was
not S&S because miners were not in the area.
The inspector also verbally issued
a citation (later written as Citation No. 8665960) alleging a violation of 30
C.F.R. § 56.14100(b)[6] because he observed that the
metal housing of an exhaust fan was not being properly maintained. The
inspector believed that the condition was not S&S because there was little access
by miners to the area.
At approximately 3:00 p.m. later that
day, all of the mine’s crew except for the operating crew of eight to nine
miners left for the weekend. At the end of the inspection day on December 14,
there were 12 open enforcement actions.
On the following day, Saturday, December 15, at
approximately 11:45 a.m., the inspector issued the written version of eight citations
that had been verbally issued on December 14, including Citation Nos. 8665957,
8665959, 8665960, and some extensions, including the extension for Citation No.
8665946. The time listed for abatement on each of the enforcement actions was
8:00 a.m. Tr. 133.
The inspector then re-inspected the areas that
were the subject of Citation Nos. 8665946, 8665957, 8665959, and 8665960. The
inspector noted that there were no miners working on the cited conditions in
the areas, the conditions had not been abated, there were no posted barricades
or warnings, and he found no mitigating circumstances. Tr. 40-41, 51, 57, 65. The
operator explained that the plant was being cleaned from top to bottom, which
impacted some of the cited areas. Tr. 140, 150, 215.
Pursuant to section 104(b) of the
Act, Inspector Sichmeller issued Orders Nos. 8665965, 8665970, 8665968, and
8665969 for the operator’s failure to abate Citation Nos. 8665946, 8665957,
8665959, and 8665960, respectively. At the end of that inspection day,
Sichmeller indicated in a close-out conference that, going forward, Hibbing Taconite
should assume that abatement times would be set for 8:00 a.m. the following
day. Tr. 152, 163, 215-16.
The operator challenged the failure
to abate orders, and the matter proceeded to hearing before the Judge.
The Judge sustained the four section 104(b) orders.
She found that the inspector did not abuse his discretion in issuing the orders
and that, in refusing to grant the extensions, the inspector had a clear
understanding of the law and that his primary concern was the safety of miners.
35 FMSHRC at 2542-43, 2546, 2548, 2551. In so holding, the Judge credited the
inspector’s testimony regarding the condition of the cited areas and lack of abatement
efforts. Id.
Hibbing Taconite filed a petition for
discretionary review challenging the Judge’s decision. The operator argues in
part that the inspector arbitrarily set abatement times and that the
inspector’s refusal to extend the abatement times was unreasonable given
various circumstances relevant to the citations underlying the orders. We
granted the petition and heard oral argument.
II.
Disposition
Under section 104(b) of the Mine
Act, it is the operator’s duty to abate the “violation described in [the]
citation issued pursuant to [section 104(a)].” 30 U.S.C. § 814(b). When issuing
a section 104(a) citation, the inspector must “describe with particularity the
nature of the violation” as well as “fix a reasonable time for the abatement of
the violation.” 30 U.S.C.
§ 814(a). Section 104(b) provides that an inspector shall
issue a failure to abate order when a cited violation has not been “totally
abated” within the abatement time originally fixed or as subsequently extended,
and if he determines “that the period of time . . . should not be further
extended.” See n.1, supra.
The Commission has held that it is
the Secretary, as the proponent of a section 104(b) order, who bears the burden
of proving that the violation has not been abated within the time period
originally fixed or as subsequently extended. Mid-Continent Res., Inc.,
11 FMSHRC 505, 509 (Apr. 1989). The Secretary establishes a prima facie case
that a section 104(b) order is valid by proving by a preponderance of the
evidence that the violation described in the underlying section 104(a) citation
existed at the time the section 104(b) withdrawal order was issued. The
operator may rebut the prima facie case by showing, for example, that the
violative condition described in the citation had been abated within the time
period fixed in the citation, but had recurred. Id.
In contesting a section 104(b)
order, an operator may challenge the reasonableness of the time set for
abatement or the Secretary’s failure to extend that time. Clinchfield Coal
Co.., 11 FMSHRC 2120, 2128 (Nov. 1989). The Commission has applied an “abuse
of discretion” standard in reviewing an inspector’s issuance of a failure to
abate order.[7] See Energy West,
18 FMSHRC at 569 (applying an abuse of discretion standard in reviewing
Secretary’s failure to extend abatement time). An abuse of discretion has been
found when “there is no evidence to support the decision or if the decision is
based on an improper understanding of the law.” Id. (citations omitted).
Here, Hibbing Taconite challenges both
the reasonableness of the times set for abatement in the underlying section
104(a) citations and the Secretary’s failure to extend those times. Because we
conclude that the inspector set arbitrary abatement times, we need not reach
Hibbing Taconite’s remaining arguments.
When considering an operator’s challenge
to a section 104(b) order, the Commission has clarified that “in fixing a
reasonable time for abatement, the inspector must necessarily specify the
violative conditions found and determine the time reasonably required for the
abatement of the specified conditions.” Mid-Continent, 11 FMSHRC at 510.
We conclude that the record reveals that the inspector failed to set abatement
times that were based upon those times reasonably required for the abatement of
the cited conditions.
Rather, Inspector Sichmeller testified that he universally
set abatement times of 8:00 a.m. the morning after he verbally issued citations
in order to prompt the operator to quickly abate the violations. Tr. 70. The
inspector explained that, for instance, he did not want to give an abatement
time of three days and have the operator not take any action on abating the
condition until the third day.[8] Tr. 89.
On December 14, the inspector verbally issued eight
citations and set an abatement time of 8:00 a.m. on December 15 for each of the
eight citations. Tr. 133. The inspector’s field notes set forth the explanation
that he gave Angelo for setting the abatement times:
Tim [Angelo] has
brought up issues about termination times & extensions. Discussed that due
to past experiences that when given extended termination time I’ve found
conditions are not being tended to within allotted time frame so the basis of
short termination times is to ensure that items are being addressed.
[D]iscussed that I understood that sometimes that all conditions may not be
taken care of in that time & if finding appropriate action is being done
have no reason for not extending citation at that time.
Gov’t Ex. P13 at pp. 30-31. Thus,
the inspector conceded that the cited conditions may not be capable of being
abated within the abatement times that he set.
With respect to the citations that
led to three of the subject orders, the record reveals that the inspector was
aware that setting an abatement time of 8:00 a.m. the next morning would not
have provided the operator with sufficient time to correct conditions. For
instance, Inspector Sichmeller verbally issued Citation No. 8665946 at
approximately 5:30 p.m. on December 12, set an abatement time of 8:00 a.m. on
December 13, and thereafter extended the abatement time until 8:00 a.m. on Dec.
14 and until 8:00 a.m. on December 15. Tr. 36-39, 99, 113, 117; Gov’t Exs.
P1-3, P1-4, P1-5 at p. 5. In his notes for December 12, the inspector acknowledged
“[t]his is a vast area affected due to the multiple conditions present.” Gov’t
Ex. P1-5. The inspector also testified that it took the operator from December
15, the date the order was issued, until December 18 to abate the order due to
the “extensiveness” of the cleanup required. Tr. 68. He stated that he was
“surprised they got it done in three days as extensive as it was.” Tr. 68. Safety
Representative Marcus also described the condition as “obviously a pretty
massive project.” Tr. 113.
Similarly, the inspector verbally issued
Citation No. 8665957 for pellets and slurry in the walkway of the scrubber pump
area on December 14 at approximately 1:30 p.m., and set an abatement time of
December 15 at 8:00 a.m. Gov’t Ex. P3-1. The inspector testified that after the
order was issued on December 15, it “took them to the 17th to get this done
because of the extensiveness of the conditions.” Tr. 53.
Inspector Sichmeller verbally
issued Citation No. 8665960 for the deteriorated condition of the fan housing at
approximately 2:15 p.m. on December 14, and set the abatement time for 8:00
a.m. on December 15. Gov’t Ex. P7-1. The inspector explained that the operator
“had to get some manlifts and stuff in there” and grind down the rough edges of
the fan housing, and that the order was terminated on December 17. Tr. 66-67;
Gov’t Ex. P8-3.
Inspector Sichmeller also failed to
set an abatement time that reflected the time reasonably required for the
abatement of the conditions cited in Citation No. 8665959 involving the 8x8
feet accumulation of pellets in the walkway by the electrical disconnect. The
inspector verbally issued the citation at approximately 2:00 p.m. on December
14, and set an abatement time of 8:00 a.m. on December 15. Gov’t Exs. P5-1,
P5-2 at p. 104. Sichmeller acknowledged, however, that the cited conditions
would only take about five minutes to clean up. Tr. 57, 60. The inspector conceded
that “sometimes [the] eight o’clock termination time is way too long based on
the conditions and the hazard that’s presented.” Tr. 71.
We conclude that the inspector did
not fix the abatement times based upon “the time reasonably required for abatement
of the specified conditions,” as he is required to do by the Mine Act and
Commission precedent. Mid-Continent, 11 FMSHRC at 510. The record
indicates that the inspector did not base the abatement times on such factors
as the extent of the violative conditions, the availability of miners to
undertake cleaning work, and competing safety concerns. Rather, the inspector
set an arbitrary abatement time of 8:00 a.m. the next morning, regardless of
the amount of time that the conditions required for abatement.[9]
The inspector’s issuance of the failure to abate orders was based upon a misunderstanding
of the law, and amounted to an abuse of discretion.
While the inspector’s concern with
exacting immediate corrective action from the operator in order to keep miners
safe is a laudable and important concern, the Mine Act sets forth a scheme in
sections 104(a) and (b) by which to achieve that end. The inspector must take
enforcement action consistent with those provisions. For instance, the
inspector must set an abatement time based upon the amount of time necessary to
fully abate a violation. Thereafter, if the operator does not fully abate within
that time, the inspector must determine whether an extension in abatement time
is warranted or whether he should issue a section 104(b) order. In making that determination,
the inspector may consider information such as whether the operator delayed
beginning the abatement process and whether any delay was justified, giving
priority to the safety of miners exposed to the unabated condition. Thus –
responsive to Inspector Sichmeller’s concern about delaying commencement of
abatement – if, for example, the conditions reasonably require three days to
complete abatement, and the operator unjustifiably fails to begin the process
until the third day, an inspector may determine that further extension of the
abatement time is not warranted, and instead issue a section 104(b) order.
Accordingly, for the reasons
discussed above, we hold that the inspector abused his discretion in issuing
Orders Nos. 8665965, 8665970, 8665968, and 8665969.
III.
Conclusion
For the foregoing reasons, we hereby
reverse the Judge’s decision and vacate Orders Nos. 8665965, 8665970, 8665968,
and 8665969.
/s/ Mary Lu
Jordan
Mary
Lu Jordan, Chairman
/s/
Michael G. Young
Michael
G. Young, Commissioner
/s/
Robert F. Cohen, Jr.
Robert
F. Cohen, Jr., Commissioner
/s/
Patrick K. Nakamura
Patrick
K. Nakamura, Commissioner
/s/
William I. Althen
William
I. Althen, Commissioner
[1] Section 104 provides in
relevant part:
(a) If, upon inspection or
investigation, the Secretary or his authorized representative believes that an
operator of a coal or other mine . . . has violated . . . any mandatory health
or safety standard, . . . he shall, with reasonable promptness, issue a
citation to the operator. Each citation shall be in writing and shall describe
with particularity the nature of the violation . . . . In addition, the
citation shall fix a reasonable time for the abatement of the violation. . . .
(b) If, upon any follow-up
inspection of a coal or other mine, an authorized representative of the
Secretary finds (1) that a violation described in a citation issued pursuant to
subsection (a) has not been totally abated within the period of time as
originally fixed therein or as subsequently extended, and (2) that the period
of time for the abatement should not be further extended, he shall determine
the extent of the area affected by the violation and shall promptly issue an
order requiring the operator of such mine . . . to immediately cause all
persons . . . to be withdrawn from. . . such area until an authorized representative
of the Secretary determines that such violation has been abated. . . .
30 U.S.C. §
814(a), (b).
[2]
Induration is the “hardening of a rock or rock material by heat, pressure, or
the introduction of cementing material.” American Geological Institute, Dictionary
of Mining, Mineral and Related Terms 279 (2d ed. 1997).
[3]
The S&S terminology is taken from section 104(d)(1) of the Act, which
distinguishes as more serious any violation that “could significantly and
substantially contribute to the cause and effect of a . . . mine safety or
health hazard.” 30 U.S.C § 814(d)(1).
[4]
30 C.F.R. § 56.20003(a) provides that, at all mining operations, “[w]orkplaces,
passageways, store-rooms, and service rooms shall be kept clean and orderly.”
[5] 30 C.F.R. § 56.20003(b)
provides in part that, at all mining operations, “[t]he floor of every
workplace shall be maintained in a clean and, so far as possible, dry
condition.”
[6] 30 C.F.R. § 56.14100(b)
provides that “[d]efects on any equipment, machinery, and tools that affect
safety shall be corrected in a timely manner to prevent the creation of a
hazard to persons.”
[7] The Secretary must prove
by a preponderance of the evidence that the inspector did not abuse his
discretion in issuing the section 104(b) orders. Mid-Continent, 11
FMSHRC at 509; Energy West Mining Co., 18 FMSHRC 565, 569 (Apr. 1996). The
Commission thereafter applies a substantial evidence standard in reviewing the
Judge’s factual determinations. Cf. Island Creek Coal Co., 15 FMSHRC
339, 346 (Mar. 1993). The Judge erroneously applied a substantial evidence
standard in affirming the four failure to abate orders. 35 FMSHRC at 2542-43,
2546, 2548, 2551.
[8] The Secretary referred to
the inspector’s practice of setting an 8:00 a.m. abatement time as the
inspector’s abatement “policy.” S. Br. at 7 n.8; see also Oral Arg. Tr.
at 38.
[9] The arbitrary nature of
the 8:00 a.m. termination time is apparent from Inspector Sichmeller’s statement
during the close-out conference on December 15, which the operator has not
disputed, that the inspector would set an 8:00 a.m. abatement time on all
citations going forward. Tr. 152, 215-16. The inspector could not have known
what conditions would be cited, let alone that 8:00 a.m. the following morning
would be a reasonable time for abatement.
Get today's answer for your situation
You just read Commission precedent from 2016. Ezel checks whether it still stands, including any court review since, and answers your specific situation, with citations.
Opens in Ezel Pro. Every answer cites the authority it relies on.