O-N Minerals (Michigan) Company (Commission decision, March 30, 2011)

O-N Minerals (Michigan) Company (FMSHRC LAKE 2010-941-M): Final assessment reopened and remanded

Decision type
Commission decision
Docket
LAKE 2010-941-M
Decided
March 30, 2011
Outcome
Remanded
Precedential status
Citable Commission precedent
Checked against source
2026-08-04

Apply this precedent to your situation

This is citable Commission precedent from 2011, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.

Currency note: this decision dates from 2011
The MSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Decision of the Commission
This is a decision of the Federal Mine Safety and Health Review Commission, the highest level of agency review, citable as Commission precedent. It may have been appealed to a U.S. Court of Appeals after issuance under 30 U.S.C. § 816; check subsequent history before relying on it. The full text below is from the official FMSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official FMSHRC release. The full text is the agency's own release.
Read the official release (fmshrc.gov)

Plain-English summary

O-N Minerals asked the Commission to reopen a penalty assessment that became final when it was not contested within 30 days. The Secretary did not oppose the request. After reviewing the circumstances, the Commission reopened the assessment and remanded it for further proceedings. The Secretary was directed to file a penalty petition within 45 days.

Decision snapshot

  • Governing provisions: 29 C.F.R. §§ 2700.1(b) and 2700.28; 30 U.S.C. § 815(a)
  • Outcome: The final assessment was reopened and remanded.
  • Key point: A final uncontested assessment may be reopened in appropriate circumstances when the operator seeks relief and the Secretary does not oppose.

Full text (FMSHRC public release)

Federal Mine Safety and Health Review Commission

FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION

601 NEW JERSEY AVENUE, NW

SUITE 9500

WASHINGTON, DC 20001

March 30, 2011

SECRETARY OF LABOR,

MINE SAFETY AND HEALTH

ADMINISTRATION (MSHA)

v.

O-N MINERALS (MICHIGAN) COMPANY

:

:

:

:

:

:

:

Docket No. LAKE 2010-941-M

A.C. No. 20-00985-219861

BEFORE: Jordan, Chairman; Duffy, Young, Cohen, and Nakamura, Commissioners

ORDER

BY THE COMMISSION:

This matter arises under the Federal Mine Safety and Health Act of 1977, 30 U.S.C.
§ 801 et seq. (2006) (“Mine Act”). On August 30, 2010, the Commission received from the O-N Minerals (Michigan) Company a request to reopen a penalty assessment that had become a final order of the Commission pursuant to section 105(a) of the Mine Act, 30 U.S.C.
§ 815(a). On September 23, 2010, the Commission received a response from the Secretary of Labor stating that she does not oppose the request to reopen the assessment.

Under section 105(a) of the Mine Act, an operator who wishes to contest a proposed penalty must notify the Secretary of Labor no later than 30 days after receiving the proposed penalty assessment. If the operator fails to notify the Secretary, the proposed penalty assessment is deemed a final order of the Commission. 30 U.S.C. § 815(a).

We have held, however, that in appropriate circumstances, we possess jurisdiction to reopen uncontested assessments that have become final Commission orders under section 105(a). Jim Walter Res., Inc., 15 FMSHRC 782, 786-89 (May 1993) (“JWR”). In evaluating requests to reopen final section 105(a) orders, the Commission has found guidance in Rule 60(b) of the Federal Rules of Civil Procedure under which, for example, a party could be entitled to relief from a final order of the Commission on the basis of mistake, inadvertence, or excusable neglect. See 29 C.F.R. § 2700.1(b) (“the Commission and its Judges shall be guided so far as practicable by the Federal Rules of Civil Procedure”); JWR, 15 FMSHRC at 787. We have also observed that default is a harsh remedy and that, if the defaulting party can make a showing of good cause for a failure to timely respond, the case may be reopened and appropriate proceedings on the merits permitted. See Coal Prep. Servs., Inc., 17 FMSHRC 1529, 1530 (Sept. 1995).

Having reviewed the facts and circumstances of this case, the operator’s request, and the Secretary’s response, we hereby reopen this matter and remand it to the Chief Administrative Law Judge for further proceedings pursuant to the Mine Act and the Commission’s Procedural Rules, 29 C.F.R. Part 2700. Accordingly, consistent with Rule 28, the Secretary shall file a petition for assessment of penalty within 45 days of the date of this order. See 29 C.F.R. § 2700.28.


Mary Lu Jordan, Chairman


Michael F. Duffy, Commissioner


Michael G. Young, Commissioner


Robert F. Cohen, Jr., Commissioner


Patrick K. Nakamura, Commissioner

Distribution:

Jim Weber, Production Mngr.

Carmeuse Chemicals

County Rd. 432

Gulliver, MI 49840

W. Christian Schumann, Esq.

Office of the Solicitor

U.S. Department of Labor

1100 Wilson Blvd., Room 2220

Arlington, VA 22209-2296

Melanie Garris

Office of Civil Penalty Compliance

MSHA

U.S. Dept. Of Labor

1100 Wilson Blvd., 25th Floor

Arlington, VA 22209-3939

Chief Administrative Law Judge Robert J. Lesnick

Federal Mine Safety & Health Review Commission

601 New Jersey Avenue, N.W., Suite 9500

Washington, D.C. 20001-2021

Does this precedent still control your case?

Ezel checks whether it still stands, including any court review since, and applies it to your situation with citations.

Opens in Ezel Pro.

  • Checks the law as it stands today, not only this page
  • Cites every source it relies on, so you can verify it
  • Chat, drafting and research in one workspace