Secretary of Labor, Mine Safety and Health Administration (MSHA) v. Black Beauty Coal Company (ALJ decision, October 24, 2016)

Secretary of Labor v. Black Beauty Coal Company (FMSHRC LAKE 2009-412, et al.): Settlement resolves S&S and unwarrantable failure questions sent back by the Commission

Decision type
ALJ decision
Dockets
LAKE 2009-412, LAKE 2009-413, LAKE 2009-414
Decided
October 24, 2016
Presiding judge
Outcome
Settled
Precedential status
Final order, not precedent
Checked against source
2026-08-01

Apply this to your situation

This order from 2016 bound only the parties to this case; it isn't precedent. Ask about your situation and see what the current MSHA standards and Commission precedent say, with citations.

Currency note: this decision dates from 2016
The MSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Final ALJ decision under the Mine Act's 40-day rule
This administrative law judge decision became a final decision of the Commission because no Commissioner directed review within 40 days, under 30 U.S.C. § 823(d)(1). It is binding on the parties but is not Commission precedent. The full text below is from the official FMSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official FMSHRC release. The full text is the agency's own release.
Read the official release (fmshrc.gov)

Plain-English summary

This settlement closes out four violations at two Black Beauty coal operations, the Riola Mine Complex-Vermillion Grove and the Air Quality #1 Mine. After a 2014 hearing, Judge Manning had thrown out the inspectors' "significant and substantial" findings on all four and the unwarrantable failure findings on two. The Commission reviewed that ruling in June 2016 and sent the questions back, saying the judge may have leaned on redundant safety measures when deciding the violations were not S&S, and that this may in turn have colored his unwarrantable failure findings. Rather than relitigate, the parties settled, and the outcome differs item by item. On the ventilation citation the company accepted the inspector's original S&S wording and the full proposed penalty of $3,996. On the mantrip accumulation citation the S&S finding was dropped, based on evidence that engine and transmission surfaces stayed below the flash point of oil and coal dust. Two float coal dust orders were reduced from section 104(d)(2) orders to section 104(a) citations, dropping the unwarrantable failure findings, with the S&S finding also removed from one. Black Beauty had already paid $30,000 after the original decision, so only the $1,996 difference remained due.

Decision snapshot

  • Cited standard(s): 30 C.F.R. § 75.400 and 30 C.F.R. § 75.370(a)(1)
  • Outcome: Settlement approved on remand; one citation restored to its original S&S terms at the full proposed penalty, one S&S finding deleted, and two 104(d)(2) orders reduced to 104(a) citations, with $1,996 left to pay.
  • Key point: A remand on S&S and unwarrantable failure does not have to end in another ruling, and a settlement can move individual citations in opposite directions where the evidence on each one differs.

Full text (FMSHRC public release)

FEDERAL MINE SAFETY AND HEALTH REVIEW
COMMISSION

OFFICE OF
ADMINISTRATIVE LAW JUDGES

721 19th STREET, SUITE
443

DENVER, CO 80202-2536

303-844-3577/FAX
303-844-5268

October 24, 2016

SECRETARY OF LABOR

MINE SAFETY AND HEALTH   

ADMINISTRATION (MSHA),

Petitioner

v.

BLACK BEAUTY COAL COMPANY,

Respondent

CIVIL PENALTY PROCEEDINGS

Docket No. LAKE 2009-412

A.C. No. 11-03060-179547-02

Riola Mine Complex-Vermillion Grove

Docket No. LAKE 2009-413

A.C. No. 12-02010-179550-01

Docket No. LAKE 2009-414

A.C. No. 12-02010-179550-02

Air Quality #1 Mine

DECISION
APPROVING SETTLEMENT UPON REMAND

Before:             Judge Manning

On March 10, 2014, I issued a decision after hearing in the above dockets. [1] Black Beauty Coal Co. , 36 FMSHRC 1821 (Mar. 2014 published July 2014) (ALJ). The Commission granted cross- petitions for discretionary review and issued its decision on June 16, 2016. 38 FMSHRC 1307 (June 2016). In its decision, the Commission remanded several issues to me in light of its decision. These issues are: (1) whether the violations set forth in Citation Nos. 8414910
& 6680994 and Order Nos. 8414938 & 8414939 significantly and substantially contributed to the cause and effect of a coal mine safety or health hazard (S&S); and (2) whether the violations set forth in Order Nos. 8414938 & 8414939 were the result of Black Beauty’s unwarrantable failure to comply with section 75.400.

The Commission held that “the Judge’s determination that the violations in these [citations and] orders were not S&S may have been flawed due to consideration of redundant safety measures.” 38 FMSHRC at 1315. It further concluded that “the Judge’s non-S&S findings might have influenced his view of the degree of danger, and consequently his unwarrantable failure determinations for these orders.” Id. (footnote omitted). The Commission then remanded “the Judge’s S&S and unwarrantable failure findings at issue for reconsideration in light of [its] decision.” 38 FMSHRC at 1316.

I encouraged the parties to settle the S&S and unwarrantable failure issues in a manner that was consistent with the Commission’s decision. The parties reached a settlement and filed a motion to approve settlement on October 20, 2016. The terms of the settlement are as follows:

1. Citation No. 8414910, LAKE 2009-414 .

This citation, issued under section 104(a) of the Mine Act, states that the approved ventilation plan was not being complied with in the No. 1 active section in violation of section 75.370(a)(1). Specifically, the citation states that a Joy continuous mining machine being operated in the No. 7 entry was not being supplied with adequate ventilation to dilute, render harmless, and carry away flammable and explosive gasses, dust, and fumes while mining. The plan required 7,000 CFM of air and the velocity at the inby end of the wing curtain was about 4,982 CFM. The issuing inspector determined that an injury or illness was reasonably likely as a result of the violation and that permanently disabling injuries could reasonably be expected. He determined that the violation was S&S, that four people would be affected, and that the violation was the result of the operator’s moderate negligence. The Secretary proposed a penalty of $3,996. In my decision I affirmed the violation but reduced the gravity, vacated the S&S determination, and assessed a penalty of $2,000. 36 FMSHRC at 1850-51.

Black Beauty has agreed to accept this citation as originally written by the MSHA inspector and will accept the Secretary’s proposed penalty of $3,996.

2. Citation No. 6680994, LAKE 2009-412 .

This citation, issued under section 104(a) of the Mine Act, states that oil, oil saturated coal fines, and brake fluid were present on a mantrip on Unit #1 in violation of section 75.400. The citation states that the accumulations were in the transmission compartment, brake caliper compartment, and the muffler compartment. The issuing inspector determined that an injury or illness was reasonably likely as a result of the violation and that lost workdays or restricted duty could reasonably be expected. He determined that the violation was S&S, that 14 people would be affected, and that the violation was the result of the operator’s moderate negligence. The Secretary proposed a penalty of $23,229. In my decision, I affirmed the violation but vacated the S&S determination and assessed a penalty of
$12,000. 36 FMSHRC at 1826-28.

The parties propose to modify the citation to delete the inspector’s S&S determination. The proposed settlement is based, in part, upon the representation that the temperature of the engine and transmission housing does not exceed 215 degrees Fahrenheit but the flash point for oil and coal dust was significantly higher than 300 degrees Fahrenheit. As a consequence, the violation was unlikely to contribute to an injury or illness. The parties agree that I should assess a penalty of $12,000 for this violation.

3. Order No. 8414938, LAKE 2009-413 .

This order, issued under section 104(d)(2) of the Mine Act, states that combustible material was allowed to accumulate in the last three crosscuts of the south slope belt in violation of section 75.400. The order further states that the accumulations consisted of float coal dust deposited on rock dusted surfaces from rib to rib. The accumulations were distinctively black in color and ranged from a thin coating to approximately one quarter inch in depth. This dust was also found on timbers and belt structure. The issuing inspector determined that an injury or illness was reasonably likely as a result of the violation and that lost workdays or restricted duty could reasonably be expected. He determined that the violation was S&S, that two people would be affected, and that the violation was the result of the operator’s high negligence. The Secretary proposed a penalty of
$10,705. In my decision, I affirmed the violation but vacated the S&S and unwarrantable failure determinations and assessed a penalty of $8,000. 36 FMSHRC at 1832-35.

The parties propose to modify this order to a section 104(a) citation, thereby removing the unwarrantable failure determination made by the MSHA inspector. The MSHA inspector’s S&S and high negligence determinations remain. The proposed settlement is based, in part, upon the representation that significant accumulations were not present during the previous examination conducted by the operator. As a consequence, the violation was not caused by an unwarrantable failure of the operator to comply with the safety standard. The parties agree that I should assess a penalty of $8,000 for this violation.

4. Order No. 8414939, LAKE 2009-413 .

This order, issued under section 104(d)(2) of the Mine Act, states that combustible material was allowed to accumulate upon the energized main south belt from head to tail in violation of section 75.400. The order further states that the accumulations consisted of a thin coating of float coal dust on rock dusted surfaces that was distinctively black in color. The accumulations also extended into two crosscuts. The issuing inspector determined that an injury or illness was reasonably likely as a result of the violation and that lost workdays or restricted duty could reasonably be expected. He determined that the violation was S&S, that two people would be affected, and that the violation was the result of the operator’s high negligence. The Secretary proposed a penalty of $10,705. In my decision, I affirmed the violation but vacated the S&S and unwarrantable failure determinations and assessed a penalty of $8,000. 36 FMSHRC at 1836-38.

The parties propose to modify this order to a section 104(a) non-S&S citation. Thus, they are proposing to remove both the unwarrantable failure and S&S determinations made by the MSHA inspector. The MSHA inspector’s high negligence determination remains unchanged but the likelihood that the violation would contribute to an injury or illness is reduced to “unlikely.” The proposed settlement is based, in part, upon a representation that the accumulations were not as extensive as set forth in the inspector’s order and the rollers for the belt were not hot. As a consequence, the violation was unlikely to contribute to an injury or illness and it was not caused by an unwarrantable failure of the operator to comply with the safety standard. The parties agree that I should assess a penalty of $8,000 for this violation.

ORDER

I have considered
the representations and documentation submitted and I conclude that the proposed settlement is appropriate under the criteria set forth in section 110(i) of the Act. The motion to approve the settlement of the remanded citations and orders is GRANTED and Black Beauty Coal Company or its successor is ORDERED TO PAY the Secretary of Labor the sum of $1,996 within 30 days of the date of this decision. [2]

/s/ Richard W.
Manning

Richard W. Manning

Administrative Law Judge

Distribution:

Emily L.B. Hays, Esq., Office of the Solicitor, U.S. Department of Labor, 1244 Speer Blvd., Suite 216, Denver, CO 80204-3598

Arthur Wolfson, Esq., Jackson Kelly, 3 Gateway Center, Suite 1500, 401 Liberty Ave., Pittsburgh, PA 15222-1009

RWM

[1]
My decision also included dockets LAKE 2009-410
and LAKE 2009-415 which are not at issue on remand.

[2]
Following my March 10, 2014, decision on the
merits, Black Beauty paid the $30,000 penalty I assessed for the four violations. (Motion to Approve Settlement at 2). The $1,996 due now reflects the difference between the total owed by Black Beauty in this Decision Approving Settlement on Remand and the amount previously paid. Payment should be sent to the Mine Safety and Health Administration, U.S. Department of Labor, Payment Office, P.O. Box 790390, St. Louis, MO 63179-0390.

What applies to your situation today?

This order bound one employer. Ezel checks the current MSHA standards and Commission precedent against your facts, with citations.