Five Star Mining, Inc. (Commission decision, November 6, 2008)

Five Star Mining, Inc. (FMSHRC LAKE 2008-447): Misread assessment remanded for good-cause finding

Decision type
Commission decision
Docket
LAKE 2008-447
Decided
November 6, 2008
Outcome
Remanded
Precedential status
Citable Commission precedent
Checked against source
2026-08-08

Apply this precedent to your situation

This is citable Commission precedent from 2008, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.

Currency note: this decision dates from 2008
The MSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Decision of the Commission
This is a decision of the Federal Mine Safety and Health Review Commission, the highest level of agency review, citable as Commission precedent. It may have been appealed to a U.S. Court of Appeals after issuance under 30 U.S.C. § 816; check subsequent history before relying on it. The full text below is from the official FMSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official FMSHRC release. The full text is the agency's own release.
Read the official release (fmshrc.gov)

Plain-English summary

Five Star's counsel filed an untimely contest after misreading the proposed assessment and calculating the deadline incorrectly. A later delinquency letter went to the company's accounting department, while the safety manager and counsel believed the citation had been contested. Counsel learned of the problem after the Treasury Department contacted the accounting department, and the Secretary ultimately did not oppose reopening. The Commission remanded for the Chief ALJ to determine whether good cause existed for the late contest and whether relief from the final order should be granted.

Decision snapshot

  • Governing provisions: 29 C.F.R. § 2700.1(b); 30 U.S.C. § 815(a)
  • Outcome: The reopening request was remanded for a determination of good cause and entitlement to relief.
  • Key point: Counsel's mistaken deadline calculation and the company's handling of the delinquency notice required a factual good-cause determination.

Full text (FMSHRC public release)

Federal Mine Safety and Health Review Commission

FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION

601 NEW JERSEY AVENUE, NW

SUITE 9500

WASHINGTON, DC 20001

November 6, 2008

SECRETARY OF LABOR,

MINE SAFETY AND HEALTH

ADMINISTRATION (MSHA)

v.

FIVE STAR MINING, INC.

:

:

:

:

:

:

:

:

Docket No. LAKE 2008-447

A.C. No. 12-02249-129078

BEFORE: Duffy, Chairman; Jordan, Young, and Cohen, Commissioners

ORDER

BY THE COMMISSION:

This matter arises under the Federal Mine Safety and Health Act of 1977, 30 U.S.C.
§ 801 et seq. (2000) (“Mine Act”). On May 30, 2008, the Commission received from Five Star Mining, Inc. (“Five Star”) a motion made by counsel to reopen a penalty assessment that had become a final order of the Commission pursuant to section 105(a) of the Mine Act, 30 U.S.C.
§ 815(a).

Under section 105(a) of the Mine Act, an operator who wishes to contest a proposed penalty must notify the Secretary of Labor no later than 30 days after receiving the proposed penalty assessment. If the operator fails to notify the Secretary, the proposed penalty assessment is deemed a final order of the Commission. 30 U.S.C. § 815(a).

On October 15, 2007, the Department of Labor’s Mine Safety and Health Administration (“MSHA”) issued Proposed Assessment No. 000129078 to Five Star, proposing penalties for a citation and two orders that had been issued to the company in February and March of 2007. Five Star states that its counsel received the proposed penalty assessment from it on November 14, 2007, and that an e-mail in counsel’s file indicates that he initially believed that Five Star had already contested Citation No. 6668861 and that the proposed assessment had not been issued until November 13, 2007. Five Star further states that its counsel thereafter filed a notice of contest regarding the proposed assessment for that citation on November 27, 2007, which was untimely.

The Secretary initially responded to the motion by noting that it merely states that a mistake was made, without explaining why the mistake was made or why it should be excused. The Secretary also pointed out that the operator had failed to address why it did not file its motion until four and one-half months after MSHA had notified it in January 2008 that it was delinquent in paying the assessment for the citation and two orders. The Secretary requested that we not rule on the motion until Five Star had the opportunity to supply the missing information.

Five Star thereafter filed a reply in which it explains that the late filing was due to counsel misreading the assessment he had received from the operator and consequently erroneously calculating the deadline for contest. Further, Five Star explains that the delinquency letter from MSHA went to its accounting department, and not to either the mine safety manager or counsel, who each believed that the citation in question had been contested. According to Five Star, it was not until late April 2008, when the Treasury Department contacted its accounting department regarding the unpaid assessment, that counsel was alerted to the fact that the contest he filed might not have been timely. The Secretary thereafter filed a letter stating that, in light of Five Star’s reply, she does not oppose the motion to reopen.

We have held that in appropriate circumstances, we possess jurisdiction to reopen uncontested assessments that have become final Commission orders under section 105(a). Jim Walter Res., Inc., 15 FMSHRC 782, 786-89 (May 1993) (“JWR”). In evaluating requests to reopen final section 105(a) orders, the Commission has found guidance in Rule 60(b) of the Federal Rules of Civil Procedure under which, for example, a party could be entitled to relief from a final order of the Commission on the basis of inadvertence or mistake. See 29 C.F.R.
§ 2700.1(b) (“the Commission and its Judges shall be guided so far as practicable by the Federal Rules of Civil Procedure”); JWR, 15 FMSHRC at 787. We have also observed that default is a harsh remedy and that, if the defaulting party can make a showing of good cause for a failure to timely respond, the case may be reopened and appropriate proceedings on the merits permitted. See Coal Prep. Servs., Inc., 17 FMSHRC 1529, 1530 (Sept. 1995).

Having reviewed Five Star’s motion and reply and the Secretary’s responses, in the interests of justice, we remand this matter to the Chief Administrative Law Judge for a determination of whether good cause exists for Five Star’s failure to timely contest the penalty proposal and whether relief from the final order should be granted.

If it is determined that such
relief is appropriate, this case shall proceed pursuant to the Mine Act and the Commission’s Procedural Rules, 29 C.F.R. Part 2700.

______

Michael F. Duffy, Chairman

______

Mary Lu Jordan, Commissioner

______

Michael G. Young, Commissioner

______

Robert F. Cohen, Jr., Commissioner

Distribution:

Scott D. Matthews, Esq.

Ice Miller, LLP

One American Square, Suite 3100

Indianapolis, IN 46282-0200

W. Christian Schumann, Esq.

Office of the Solicitor

U.S. Department of Labor

1100 Wilson Blvd., Room 2220

Arlington, VA 22209-2296

Myra James, Chief

Office of Civil Penalty Compliance

U.S. Department of Labor

1100 Wilson Blvd., 25th Fl.

Arlington, VA 22209-3939

Chief Administrative Law Judge Robert J. Lesnick

Federal Mine Safety & Health Review Commission

601 New Jersey Avenue, N.W., Suite 9500

Washington, D.C. 20001-2021

Does this precedent still control your case?

Ezel checks whether it still stands, including any court review since, and applies it to your situation with citations.

Opens in Ezel Pro.

  • Checks the law as it stands today, not only this page
  • Cites every source it relies on, so you can verify it
  • Chat, drafting and research in one workspace