Pitlick & Wick, Inc. (Commission decision, November 7, 2008)
Pitlick & Wick, Inc. (FMSHRC LAKE 2008-345-M, et al.): Four conclusory reopening requests denied without prejudice
Apply this precedent to your situation
This is citable Commission precedent from 2008, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.
Plain-English summary
Pitlick & Wick missed the contest deadlines for four proposed penalty assessments issued on the same day. Its safety director attributed the failures to mistake, inadvertence, administrative error, and a clerical failure to bring the assessments to his attention. The Secretary did not oppose reopening. The Commission held that these general labels did not explain what actually happened or provide an adequate basis for relief. It denied all four requests without prejudice, permitting Pitlick to submit a more detailed account.
Decision snapshot
- Governing provisions: 29 C.F.R. § 2700.1(b); 30 U.S.C. § 815(a)
- Outcome: The four reopening requests were denied without prejudice.
- Key point: Reopening requires specific facts about the filing failure, not a string of conclusory descriptions such as mistake or clerical error.
Full text (FMSHRC public release)
Federal Mine Safety and Health Review Commission
FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION
601 NEW JERSEY AVENUE, NW
SUITE 9500
WASHINGTON, DC 20001
November 7, 2008
SECRETARY OF LABOR,
MINE SAFETY AND HEALTH
ADMINISTRATION (MSHA)
v.
PITLICK & WICK, INC.
:
:
:
:
:
:
:
:
:
:
:
Docket No. LAKE 2008-345-M
A.C. No. 47-02043-140232
Docket No. LAKE 2008-346-M
A.C. No. 47-02940-140235
Docket No. LAKE 2008-347-M
A.C. No. 47-03245-140241
Docket No. LAKE 2008-348-M
A.C. No. 47-03367-140245
BEFORE: Duffy, Chairman; Jordan, Young, and Cohen, Commissioners
ORDER
BY THE COMMISSION:
This matter arises under the Federal Mine Safety and Health Act of 1977, 30 U.S.C.
§ 801 et seq. (2000) (“Mine Act”). On April 14, 2008, the Commission received from Pitlick & Wick, Inc. (“Pitlick”) motions from counsel seeking to reopen four penalty assessments that had become final orders of the Commission pursuant to section 105(a) of the Mine Act, 30 U.S.C.
§ 815(a).
Under section 105(a) of the Mine Act, an operator who wishes to contest a proposed penalty must notify the Secretary of Labor no later than 30 days after receiving the proposed penalty assessment. If the operator fails to notify the Secretary, the proposed penalty assessment is deemed a final order of the Commission. 30 U.S.C. § 815(a).
On February 13, 2008, the Department of Labor’s Mine Safety and Health Administration (“MSHA”) issued the four proposed penalty assessments at issue to Pitlick. The affidavit of Pitlick’s Safety Director states that Pitlick failed to contest the penalty assessments within the required 30 days “due to mistake and inadvertent administrative error due to clerical error which failed to bring the assessment to [his] attention in a timely fashion.” The Secretary does not oppose the reopening of the assessments.
We have held that in appropriate circumstances, we possess jurisdiction to reopen uncontested assessments that have become final Commission orders under section 105(a). Jim Walter Res., Inc., 15 FMSHRC 782, 786-89 (May 1993) (“JWR”). In evaluating requests to reopen final section 105(a) orders, the Commission has found guidance in Rule 60(b) of the Federal Rules of Civil Procedure under which, for example, a party could be entitled to relief from a final order of the Commission on the basis of inadvertence or mistake. See 29 C.F.R.
§ 2700.1(b) (“the Commission and its Judges shall be guided so far as practicable by the Federal Rules of Civil Procedure”); JWR, 15 FMSHRC at 787. We have also observed that default is a harsh remedy and that, if the defaulting party can make a showing of good cause for a failure to timely respond, the case may be reopened and appropriate proceedings on the merits permitted. See Coal Prep. Servs., Inc., 17 FMSHRC 1529, 1530 (Sept. 1995).
Having reviewed Pitlick’s request and the Secretary’s response, we determine that Pitlick has failed to provide a sufficiently detailed explanation for its failure to timely contest the proposed penalty assessments. Pitlick’s conclusory statement that a clerical error resulted in its failing to timely contest the assessments does not provide the Commission with an adequate basis to justify reopening. Accordingly, we deny without prejudice Pitlick’s request. See Eastern Assoc. Coal, LLC, 30 FMSHRC 392 (May 2008); James Hamilton Construction, 29 FMSHRC 569, 570 (July 2007).
______
Michael F. Duffy, Chairman
______
Mary Lu Jordan, Commissioner
______
Michael G. Young, Commissioner
______
Robert F. Cohen, Jr., Commissioner
Distribution:
Adele L. Abrams, Esq.
Law Office of Adele L. Abrams, P.C.
4740 Corridor Place, Suite D
Beltsville, MD 20705
Myra James, Chief
Office of Civil Penalty Compliance
MSHA
U.S. Department of Labor
1100 Wilson Blvd., 25th Fl.
Arlington, VA 22209-3939
W. Christian Schumann, Esq.
Office of the Solicitor
U.S. Department of Labor
1100 Wilson Blvd., Room 2220
Arlington, VA 22209-2296
Chief Administrative Law Judge Robert J. Lesnick
Federal Mine Safety & Health Review Commission
601 New Jersey Avenue, N.W., Suite 9500
Washington, D.C. 20001-2021
Does this precedent still control your case?
Ezel checks whether it still stands, including any court review since, and applies it to your situation with citations.
Opens in Ezel Pro.
- Checks the law as it stands today, not only this page
- Cites every source it relies on, so you can verify it
- Chat, drafting and research in one workspace