The American Coal Company (Commission decision, September 27, 2007)
The American Coal Company (FMSHRC LAKE 2007-197): Late penalty contest sent back for good-cause review
Apply this precedent to your situation
This is citable Commission precedent from 2007, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.
Plain-English summary
American Coal failed to contest a proposed penalty assessment within the Mine Act's 30-day deadline, so the assessment became a final Commission order. The company said the failure was a mistake but did not explain it. The Secretary did not oppose reopening because the company's safety director had transferred positions and another person was temporarily filling the role during the contest period. The Commission remanded the case for the Chief ALJ to determine whether good cause existed and whether relief from the final order should be granted.
Decision snapshot
- Governing provisions: 29 C.F.R. § 2700.1(b); 30 U.S.C. § 815(a)
- Outcome: The reopening request was remanded for a good-cause determination.
- Key point: A late penalty contest may be reopened for mistake or inadvertence, but the operator must establish good cause.
Full text (FMSHRC public release)
Federal Mine Safety and Health Review Commission
FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION
601 NEW JERSEY AVENUE, NW
SUITE 9500
WASHINGTON, DC 20001
September 27, 2007
SECRETARY OF LABOR,
MINE SAFETY AND HEALTH
ADMINISTRATION (MSHA)
v.
THE AMERICAN COAL COMPANY
:
:
:
:
:
:
:
Docket No. LAKE 2007-197
A.C. No. 11-02751-116758
BEFORE: Duffy, Chairman; Jordan and Young, Commissioners
ORDER
BY THE COMMISSION:
This matter arises under the Federal Mine Safety and Health Act of 1977, 30 U.S.C.
§ 801 et seq. (2000) (“Mine Act”). On August 23, 2007, the Commission received from American Coal Company (“American”) a motion made by counsel to reopen a penalty assessment that had become a final order of the Commission pursuant to section 105(a) of the Mine Act, 30 U.S.C. § 815(a).
Under section 105(a) of the Mine Act, an operator who wishes to contest a proposed penalty must notify the Secretary of Labor no later than 30 days after receiving the proposed penalty assessment. If the operator fails to notify the Secretary, the proposed penalty assessment is deemed a final order of the Commission. 30 U.S.C. § 815(a).
On April 27, 2007, the Department of Labor’s Mine Safety and Health Administration issued assessment No. 000116758 to American, proposing penalties for two citations that previously had been issued to it. American states that it intended to contest the assessment, but mistakenly failed to do so. American fails to provide any explanation for the mistake. However, the Secretary responds that she does not oppose American’s request to reopen the proposed penalty assessment because of her understanding that, during the time American had to contest the assessment, its safety director was transferred to another position and another individual was temporarily filling that position.
We have held that in appropriate circumstances, we possess jurisdiction to reopen uncontested assessments that have become final Commission orders under section 105(a). Jim Walter Res., Inc., 15 FMSHRC 782, 786-89 (May 1993) (“JWR”). In evaluating requests to reopen final section 105(a) orders, the Commission has found guidance in Rule 60(b) of the Federal Rules of Civil Procedure under which, for example, a party could be entitled to relief from a final order of the Commission on the basis of inadvertence or mistake. See 29 C.F.R.
§ 2700.1(b) (“the Commission and its Judges shall be guided so far as practicable by the Federal Rules of Civil Procedure”); JWR, 15 FMSHRC at 787. We have also observed that default is a harsh remedy and that, if the defaulting party can make a showing of good cause for a failure to timely respond, the case may be reopened and appropriate proceedings on the merits permitted. See Coal Prep. Servs., Inc., 17 FMSHRC 1529, 1530 (Sept. 1995).
Having reviewed American’s motion, in the interests of justice, we remand this matter to the Chief Administrative Law Judge for a determination of whether good cause exists for American’s failure to timely contest the penalty proposal and whether relief from the final order should be granted. If it is determined that such relief is appropriate, this case shall proceed pursuant to the Mine Act and the Commission’s Procedural Rules, 29 C.F.R. Part 2700.
______
Michael F. Duffy, Chairman
______
Mary Lu Jordan, Commissioner
______
Michael G. Young, Commissioner
Distribution
Noelle Holladay True, Esq.
Rajkovich, Williams, Kilpatrick & True, PLLC.
2333 Alumni Park Plaza, Suite 310
Lexington, KY 40517
W. Christian Schumann, Esq.
Office of the Solicitor
U.S. Department of Labor
1100 Wilson Blvd., Room 2220
Arlington, VA 22209-2296
Chief Administrative Law Judge Robert J. Lesnick
Federal Mine Safety & Health Review Commission
601 New Jersey Avenue, N.W., Suite 9500
Washington, D.C. 20001-2021
Does this precedent still control your case?
Ezel checks whether it still stands, including any court review since, and applies it to your situation with citations.
Opens in Ezel Pro.
- Checks the law as it stands today, not only this page
- Cites every source it relies on, so you can verify it
- Chat, drafting and research in one workspace