Peabody Coal Company
Peabody Coal Company (FMSHRC KENT 91-179-R and KENT 91-185-R): Ventilation-plan citations affirmed
What's the rule today?
This ALJ decision was superseded by the Commission's decision in the same case. Ezel starts from the controlling decision and answers your situation under current law, with citations.
Plain-English summary
Peabody Coal challenged two citations alleging that its Martwick and Camp No. 2 mines were operating without approved ventilation plans. The dispute concerned requirements for extending line brattice and maintaining at least 3,000 cubic feet per minute of air during roof bolting in deep cuts. Judge Gary Melick found that the requirements were mine-specific conditions that could be imposed through the ventilation-plan approval process, rather than general rules requiring notice-and-comment rulemaking. He affirmed the citations and dismissed the contests because Peabody had not negotiated in good faith about the disputed plan provisions.
Decision snapshot
- Cited standard: 30 C.F.R. § 75.316
- Outcome: Both citations were affirmed and the contests were dismissed.
- Key point: Mine-specific ventilation-plan requirements may be enforced through the plan approval process when they are tied to the conditions of the particular mines.
Full text (FMSHRC public release)
Federal Mine Safety and Health Review Commission
Office of Administrative Law Judges
2 Skyline, 10th Floor
5203 Leesburg Pike
Falls Church, Virginia 22041
PEABODY COAL COMPANY, CONTEST PROCEEDINGS
CONTESTANT
v. Docket No. KENT 91-179-R
SECRETARY OF LABOR, Citation No. 3419830; 2/11/91
MINE SAFETY AND HEALTH
ADMINISTRATION (MSHA), Martwick UG Mine
RESPONDENT Mine ID 15-14074
Docket No. KENT 91-185-R
Citation No. 3419831; 2/21/91
Camp No. 2 Mine
Mine ID 15-02705
DECISION
Appearances: David R. Joest, Esq., Peabody Coal Company,
Henderson, Kentucky, for the Contestant;
W. F. Taylor, Esq., Office of the Solicitor, U.S.
Department of Labor, Nashville, Tennessee, for
Respondent.
Before: Judge Melick
These expedited Contest Proceedings were filed by the
Peabody Coal Company (Peabody) pursuant to section 105(d) of the
Federal Mine Safety and Health Act of 1977, 30 U.S.C. 801 et
seq., the "Act," to challenge two citations issued by the
Secretary of Labor alleging violations of the mandatory standard
at 30 C.F.R. 75.316 for operating the cited mines without
approved ventilation plans. (Footnote 1) The citations were taken
to obtain review of the disapproval by the Mine Safety and Health
Administration (MSHA) District Manager of ventilation plans
submitted by Peabody. The underlying dispute involves the
ventilation of "deep cuts" of up to 34 feet during the roof
bolting cycle of the mining process. In particular MSHA is
seeking in these ventilation plans a provision requiring that
during the roof bolting cycle line brattice will be maintained to
the second row of roof bolts located outby the working face and
with a minimum of 3000 c.f.m. of air behind the line brattice. A
diagram of the proposed requirement is displayed in Contestant's
Exhibit Q at pages 23 and 24 and attached hereto as Appendices A
and B respectively. These provisions will hereafter be noted as
the "roof bolting ventilation requirement".
In challenging the citations at bar Peabody has maintained
that the roof bolting ventilation requirement was not mine
specific to the particular conditions of the subject mines but
was of such a general nature and was applied generally to all
mines throughout the MSHA district without consideration of
specific mine conditions so as to be subject to the rulemaking
process of mandatory safety standards, and was therefore
improperly imposed in the ventilation plan approval process.
This issue was decided in a bench decision at bifurcated
hearings in these cases and is set forth below with only
non-substantive changes:
JUDGE MELICK: I am prepared to rule on the issue before
me now. Let me just give some background of the law as
it relates to the ventilation plan approval process.
The institution of a ventilation, methane and dust
control plan through the process of Secretarial
approval and operator adoption is set forth in Section
303 of the Act and under 30 C.F.R. Section 75.316,
which essentially reiterates the provisions of the Act.
The purpose of the approval-adoption procedure is to
provide a plan whose provisions are effective and
suitable to the conditions and mining system of a
particular mine. Once a plan is approved and adopted, the
provisions of the plan are enforceable at the mine
as though they were statutory safety standards. The
authority for that proposition is of course Zeigler
Coal Company v. Kleppe, 536 F.2d 398 (D.C. Cir. 1976).
The bilateral approval-adoption process which
supplements the Act's rulemaking procedures involves
consultation and negotiation between MSHA and only the
affected operator, whereas generally applicable
standards are the product of notice and comment
rulemaking pursuant to Section 101 of the Act. The
scope of a mine-specific plan is restricted to the mine
in which the plan will be implemented, whereas a
rulemaking safety or health standard applies
across-the-board to all affected mines.
In the Zeigler case, the court held that the
approval-adoption procedure is not to be used by the
Government to impose general requirements of a variety
well-suited to all or nearly all coal mines. It upheld
the operator's right to contest MSHA's requirement for
a plan provision that relates not to the particular
circumstances of its mine but, rather, imposes a
provision of a general nature which should be addressed
and formulated in rulemaking proceedings.
In the Carbon County Coal Company decisions of the
Commission, 6 FMSHRC 1123 in 1984, and 7 FMSHRC 1368 in
1985, the Commission found the Zeigler analysis to be
"persuasive and compelling" and held that the
provisions of 30 C.F.R. Section 75.316 do not permit
MSHA to impose, as a condition of approving an
operator's ventilation plan, a general rule applicable
to all mines.
The specific issue then before me at this time is
whether the ventilation plan provisions that are now at
issue regarding the ventilation of deep cuts at the
Martwick and Camp Number 2 Mines are specific to the
particular conditions of the subject mines, or whether
those provisions are of such a general nature as to be
subject to the rulemaking process of mandatory safety
standards and therefore ought not to be imposed through
the ventilation plan approval process. I am persuaded
by the evidence in this case presented today that MSHA's
insistence upon the inclusion of these particular
ventilation requirements, that is the extension of line
brattice and a certain minimum ventilating air in areas
of deep cuts during the roof bolting cycle at the
Martwick and the Camp Number 2 Mines is not a general
requirement subject to the rulemaking procedures but
rather is mine specific. The testimony of all the MSHA
witnesses as well as the testimony of Martwick mine
superintendent, Mr. Jernigan, supports this position.
The relevant MSHA witnesses detailed a number of
specific criteria that were in fact, and presumably
will continue to be, examined on a mine-by-mine basis
to resolve whether or not these particular requirements
are going to be needed in a ventilation plan. I find
Mr. Jernigan's corroborating testimony particularly
compelling in this case that he was told by Mr. Casteel
[MSHA Chief of Engineering Services] and Mr. Stanley
[MSHA Ventilation Specialist] that the reason for the
new requirements implemented at the Martwick Mine was
its high methane liberation and that mines with deep
cuts were being examined on a mine-by-mine basis. This
conclusion that this is a mine-specific requirement is
further supported by the evidence that two mines within
MSHA District 10 having comparatively low methane
liberation have not been required to incorporate in
their plans the new provisions that have been required
at the Martwick and Camp No. 2 Mines in these cases, and
they apparently will not be required to incorporate those
provisions in their current plans now under review.
So within the framework of that evidence I have no
difficulty concluding that the provisions at issue here
are mine-specific and not generally applicable to all
mines either in MSHA District 10 or generally
applicable to all other mines. I would comment with
respect to the number of operator witnesses who
testified of having no recollection or having a
different construction or other interpretation of what
may have been said at the MSHA-Peabody meetings but I
discount that testimony in light of Mr. Jernigan's
testimony in particular. Apparently there may have been
semantical problems, maybe people heard what they
wanted to hear and did not hear what was actually
spoken. There may not have been as clear an
understanding during these meetings but I have no
difficulty concluding as I have concluded.
Now, I would like the parties to meet further to try to
resolve this problem either tonight and/or before
commencing trial tomorrow. I don't believe that,
particularly based upon the preliminary discussions this
morning and what counsel came back to me with, that
Peabody has really been seriously forthcoming with
negotiations on resolution of this problem. Maybe now
based upon this preliminary ruling a more serious
consideration can be given to this. I will certainly
consider that in evaluating whether there have been good
faith negotiations which will be the next issue to be
reached tomorrow morning. So I would ask counsel to get
together and arrange for continuing discussions. We will
commence back here at least initially in this courtroom.
We may get another courtroom with better ventilation, but
we'll initially meet here at 9 o'clock tomorrow morning.
So that concludes today's proceedings.
Under the Carbon County Coal Company, 7 FMSHRC 1367 (1985),
decision, MSHA and the mine operator are under a duty to
"negotiate in good faith and for a reasonable period concerning a
disputed provision" in a ventilation plan. The Secretary
maintains in this regard that not only did Peabody fail to
negotiate in good faith but that Peabody failed to negotiate at
all.
It is clear from this record that Peabody has maintained
from the beginning of this controversy that the proposed changes
could not be imposed by the ventilation plan approval process
without an applicable mandatory standard. I believe that this
position was based upon good faith reliance on a decision of a
Commission Administrative Law Judge holding that similar proposed
provisions in a ventilation plan were, under the circumstances of
that case, not proven to be mine specific but rather were shown
to have been generally applicable and were therefore subject to
the rulemaking process of mandatory standards. See Peabody Coal
Company v. Secretary, 10 FMSHRC 12 (1988).
However good faith reliance on a colorable legal position
must be distinguished from good faith negotiations. From the
record in this case thus far it is apparent that Peabody has been
relying upon this position as a basis for not negotiating
regarding the specific underlying safety issue. It is therefore
clearly premature for the Commission to intervene in the
approval-adoption process. See Carbon County Coal Company,
supra.; Secretary of Labor v. Penn Allegh Coal Company, 3 FMSHRC
2767 (1981); and Bishop Coal Company, 5 IBMA 231, 1 MSHC 1367
(1975). The citations at bar must accordingly be affirmed and the
Contests of those citations dismissed.
Gary Melick
Administrative Law Judge
Footnote starts here:
1. Citation No. 3419830 reads as follows:
The mine is presently operating without an approved
ventilation plan. Plans which were submitted December 28, 1990,
January 10, 1991, and February 7, 1991, were considered to be not
suitable for approval. Written notification from the District
Manager of MSHA District 10 was mailed to the operator stating the
changes needed in the plan. These were mailed January 10, 1991,
and January 30, 1991. As of this time a suitable plan has not been
submitted.
Citation No. 3419831 reads as follows:
The mine is presently operating without an approved
ventilation plan. Plans which were submitted November 31, 1990,
January 4, 1991, February 1, 1991 and February 19, 1991, were
considered to be not suitable for approval. Written notification
from the District Manager of MSHA District 10 was mailed to the
operator stating the changes needed in the plan. These were mailed
December 1990, January 14, 1991, February 2, 1991, and telephone
conversations were held with the operator's agents as a meeting
concerning the plan was held in the MSHA office February 19, 1990.
APPENDIX A
APPENDIX B
Find out what applies today
This decision wasn't the final word: the Commission reviewed the case, and its decision is the one that controls. Ezel starts from the controlling decision and answers your specific situation under current law, with citations.
Opens in Ezel Pro. Every answer cites the authority it relies on.