Bledsoe Coal Corporation (Commission decision, October 15, 2008)
Bledsoe Coal Corporation (FMSHRC KENT 2008-808): Clerical filing error sent for a good-cause determination
Apply this precedent to your situation
This is citable Commission precedent from 2008, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.
Plain-English summary
MSHA proposed $118,538 in penalties for six violations, and Bledsoe Coal intended to contest all of them. The company's safety director said he marked the assessment and sent it to clerical staff, who misunderstood his notation and did not mail the contest within 30 days. The Secretary did not oppose reopening. The Commission remanded the matter for the Chief Administrative Law Judge to decide whether the clerical error established good cause and whether relief from the final assessment order should be granted.
Decision snapshot
- Governing provisions: 29 C.F.R. § 2700.1(b); 30 U.S.C. § 815(a)
- Outcome: The reopening request was remanded for a determination of good cause and entitlement to relief.
- Key point: Evidence that an operator timely decided to contest an assessment but clerical staff failed to send it can support a good-cause inquiry.
Full text (FMSHRC public release)
Federal Mine Safety and Health Review Commission
FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION
601 NEW JERSEY AVENUE, NW
SUITE 9500
WASHINGTON, DC 20001
October 15, 2008
SECRETARY OF LABOR,
MINE SAFETY AND HEALTH
ADMINISTRATION (MSHA)
v.
BLEDSOE COAL CORPORATION
:
:
:
:
:
:
:
:
:
Docket No. KENT 2008-808
A.C. No. 15-11065-133242
BEFORE: Duffy, Chairman; Jordan, Young and Cohen, Commissioners
ORDER
BY THE COMMISSION:
This matter arises under the Federal Mine Safety and Health Act of 1977, 30 U.S.C.
§ 801 et seq. (2000) (“Mine Act”). On April 8, 2008, the Commission received from Bledsoe Coal Corporation (“Bledsoe”) a motion made by counsel to reopen a penalty assessment that had become a final order of the Commission pursuant to section 105(a) of the Mine Act, 30 U.S.C.
§ 815(a).
Under section 105(a) of the Mine Act, an operator who wishes to contest a proposed penalty must notify the Secretary of Labor no later than 30 days after receiving the proposed penalty assessment. If the operator fails to notify the Secretary, the proposed penalty assessment is deemed a final order of the Commission. 30 U.S.C. § 815(a).
On December 5, 2007, the Department of Labor’s Mine Safety and Health Administration (“MSHA”) issued Proposed Assessment No. 000133242 to Bledsoe, proposing penalties for six violations totaling $118,538. In the motion, counsel states that Bledsoe intended to contest the penalties but by mistake erroneously failed to do so. Counsel explains that the company’s safety director marked the assessment sheet to contest all the proposed assessments and made a contemporaneous notation on the first page, but due to clerical error the assessment was not timely submitted to MSHA. In the safety director’s affidavit attached to the motion, he attests that he marked the proposed assessment and forwarded the sheet to clerical personnel in his office, who misunderstood his notation and did not mail the assessment to MSHA within 30 days of receipt. The Secretary states that she does not oppose Bledsoe’s request to reopen.
We have held that in appropriate circumstances, we possess jurisdiction to reopen uncontested assessments that have become final Commission orders under section 105(a). Jim Walter Res., Inc., 15 FMSHRC 782, 786-89 (May 1993) (“JWR”). In evaluating requests to reopen final section 105(a) orders, the Commission has found guidance in Rule 60(b) of the Federal Rules of Civil Procedure under which, for example, a party could be entitled to relief from a final order of the Commission on the basis of inadvertence or mistake. See 29 C.F.R.
§ 2700.1(b) (“the Commission and its Judges shall be guided so far as practicable by the Federal Rules of Civil Procedure”); JWR, 15 FMSHRC at 787. We have also observed that default is a harsh remedy and that, if the defaulting party can make a showing of good cause for a failure to timely respond, the case may be reopened and appropriate proceedings on the merits permitted. See Coal Prep. Servs., Inc., 17 FMSHRC 1529, 1530 (Sept. 1995).
Having reviewed Bledsoe’s motion, in the interests of justice, we remand this matter to the Chief Administrative Law Judge for a determination of whether good cause exists for Bledsoe’s failure to timely contest the penalty proposal and whether relief from the final order should be granted. If it is determined that such relief is appropriate, this case shall proceed pursuant to the Mine Act and the Commission’s Procedural Rules, 29 C.F.R. Part 2700.
______
Michael F. Duffy, Chairman
______
Mary Lu Jordan, Commissioner
______
Michael G. Young, Commissioner
______
Robert F. Cohen, Jr., Commissioner
Distribution:
John M. Williams, Esq.
Rajkovich, Williams, Kilpatrick & True, PLLC
2333 Alumni Park Plaza, Suite 310
Lexington, KY 40517
W. Christian Schumann, Esq.
Office of the Solicitor
U.S. Department of Labor
1100 Wilson Blvd., Room 2220
Arlington, VA 22209-2296
Myra James, Chief
Office of Civil Penalty Compliance, MSHA
U.S. Department of Labor
1100 Wilson Blvd., 25th Floor West
Arlington, VA 22209-3939
Chief Administrative Law Judge Robert J. Lesnick
Federal Mine Safety & Health Review Commission
601 New Jersey Avenue, N.W., Suite 9500
Washington, D.C. 20001-2021
Does this precedent still control your case?
Ezel checks whether it still stands, including any court review since, and applies it to your situation with citations.
Opens in Ezel Pro.
- Checks the law as it stands today, not only this page
- Cites every source it relies on, so you can verify it
- Chat, drafting and research in one workspace