Tigue Construction Co., Inc. (Commission decision, January 19, 1999)

Tigue Construction Co., Inc. (FMSHRC CENT 99-91-M): Penalty assessments reopened after missed contest deadline

Decision type
Commission decision
Docket
CENT 99-91-M
Decided
January 19, 1999
Outcome
Procedural
Precedential status
Citable Commission precedent
Checked against source
2026-08-11

Apply this precedent to your situation

This is citable Commission precedent from 1999, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.

Currency note: this decision dates from 1999
The MSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Decision of the Commission
This is a decision of the Federal Mine Safety and Health Review Commission, the highest level of agency review, citable as Commission precedent. It may have been appealed to a U.S. Court of Appeals after issuance under 30 U.S.C. § 816; check subsequent history before relying on it. The full text below is from the official FMSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official FMSHRC release. The full text is the agency's own release.
Read the official release (fmshrc.gov)

Plain-English summary

Tigue Construction asked the Commission to reopen penalty assessments that had become final because the company did not timely request a hearing. The company said its vice-president became seriously ill, underwent quadruple bypass surgery, and was expected to respond to the charges, while the company president did not learn that the hearing request had not been sent until after the deadline. The Commission majority found that the failure to file qualified as inadvertence or mistake under Federal Rule of Civil Procedure 60(b)(1), and reopened the assessments. Chairman Jordan dissented, stating that a judge should first assess the reliability of the company's evidence.

Decision snapshot

  • Governing authority: 30 U.S.C. §§ 801 and 815(a)
  • Outcome: The Commission granted Tigue's unopposed request for relief and reopened the penalty assessments.
  • Key point: A serious illness that caused an operator to miss the deadline for requesting a hearing may support reopening penalty assessments that became final by operation of the Mine Act.

Full text (FMSHRC public release)

FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION 1730 K STREET NW, 6TH FLOOR
WASHINGTON, D.C. 20006

January 19, 1999

SECRETARY OF LABOR,
:
MINE SAFETY AND HEALTH
:
ADMINISTRATION (MSHA)
:
:
: Docket No. CENT 99-91-M
: A.C. No. 03-01769-05503
TIGUE CONSTRUCTION CO., INC.
:

BEFORE: Jordan, Chairman; Marks, Riley, Verheggen, and Beatty, Commissioners

ORDER

BY: Marks, Riley, Verheggen and Beatty, Commissioners

This matter arises under the Federal Mine Safety and Health Act of 1977, 30 U.S.C.
§ 801 et seq. (1994) ("Mine Act"). On December 28, 1998, the Commission received from Tigue Construction Company, Inc. ("Tigue") a request to reopen penalty assessments that had become final orders of the Commission pursuant to section 105(a) of the Mine Act, 30 U.S.C.
§ 815(a). It has been administratively determined that the Secretary of Labor does not oppose the motion for relief filed by Tigue.

Under section 105(a) of the Mine Act, an operator has 30 days following receipt of the Secretary of Labor's proposed penalty assessment within which to notify the Secretary that it wishes to contest the proposed penalty. If the operator fails to notify the Secretary, the proposed penalty assessment is deemed a final order of the Commission. 30 U.S.C. § 815(a).

In its request, Tigue asserts that its failure to file a hearing request to contest the proposed penalties was due to the illness of company vice-president Freddy Tigue, who the request alleges "was to answer these charges." Mot. Tigue's request claims that Mr. Tigue felt chest pain and shortness of breath for two weeks prior to December 2, 1998, when he suffered from severe chest pain and was transported to a hospital. Id. The following day, Mr. Tigue underwent quadruple bypass surgery. Id. On December 17, Donny Teague, Mr. Tigue's son and president of the

21 FMSHRC 9


Page 2

company, first learned that the hearing request had not been sent. Id. By that time, however, the proposed assessments had became final orders of the Commission.

We have held that, in appropriate circumstances and pursuant to Fed. R. Civ. P. 60(b), we possess jurisdiction to reopen uncontested assessments that have become final by operation of section 105(a). See, e.g., Rocky Hollow Coal Co., 16 FMSHRC 1931, 1932 (Sept. 1994); Jim Walter Resources, Inc., 15 FMSHRC 782, 786-89 (May 1993). We have also observed that default is a harsh remedy and that, if the defaulting party can make a showing of adequate or good cause for the failure to timely respond, the case may be reopened and appropriate proceedings on the merits permitted. See Coal Preparation Servs., Inc., 17 FMSHRC 1529, 1530 (Sept. 1995). In accordance with Rule 60(b)(1), we have previously afforded a party relief from a final order of the Commission on the basis of inadvertence or mistake. See National Lime & Stone, Inc., 20 FMSHRC 923, 925 (Sept. 1998); Peabody Coal Co., 19 FMSHRC 1613, 1614-15 (Oct. 1997); Stillwater Mining Co., 19 FMSHRC 1021, 1022-23 (June 1996); Kinross DeLamar Mining Co., 18 FMSHRC 1590, 1591-92 (Sept. 1996).

Here, the record indicates that Tigue intended to contest the proposed penalty assessments in this matter and that, but for the serious illness of its vice-president, it would have timely submitted the hearing request and contested the proposed assessments. In these circumstances, Tigue's failure to timely file a hearing request qualifies as "inadvertence" or "mistake" within the meaning of Rule 60(b)(1). See Kenamerican Resources, Inc., 20 FMSHRC 199, 201 (Mar. 1998) (granting operator's motion to reopen when operator's failure to timely file hearing request was due to the recent surgery performed on its safety director); Peabody, 19 FMSHRC at 1614- 15 (granting operator's motion to reopen when operator failed to submit request for hearing to contest proposed penalty due to lack of coordination between counsel and personnel at mine).

21 FMSHRC 10


Page 3

Accordingly, in the interest of justice, we grant Tigue's unopposed request for relief and reopen these penalty assessments that became final Commission orders. This case shall proceed pursuant to the Mine Act and the Commission's Procedural Rules, 29 C.F.R. Part 2700.

Marc Lincoln Marks, Commissioner

James C. Riley, Commissioner

Theodore F. Verheggen, Commissioner

Robert H. Beatty, Jr., Commissioner

21 FMSHRC 11


Page 4

Chairman Jordan, dissenting:

I would remand this case to a judge for the purpose of assessing the reliability of the evidence presented by the operator as to why it did not request a hearing in a timely manner. The operator has presented its explanation to us in the form of a letter. This constitutes hearsay, which admittedly is admissible in Commission proceedings. Mid-Continent Resources, Inc., 6 FMSHRC 1132, 1135 (May 1984). However, the question as to whether hearsay evidence is reliable or probative is a "task . . . reserved to the judge's discretion in the first instance." REB Enterprises, Inc., 20 FMSHRC 203, 206 (Mar. 1998). I am mindful that the operator is pro se, and that the Secretary does not object to its motion. Nonetheless, I would remand to a judge for this initial determination, which is clearly not within the province of a reviewing body.

Mary Lu Jordan, Chairman

Distribution

Donny Tigue, President
Tigue Construction Co., Inc.
P.O. Box 919
Glenwood, AR 71943

Sheila Cronan, Esq.
Office of the Solicitor
U.S. Department of Labor
4015 Wilson Blvd., Suite 400
Arlington, VA 22203

Chief Administrative Law Judge Paul Merlin
Federal Mine Safety & Health Review Commission
1730 K Street, N.W., Suite 600
Washington, D.C. 20006

21 FMSHRC 12

Does this precedent still control your case?

Ezel checks whether it still stands, including any court review since, and applies it to your situation with citations.