Bailey's Limestone Quarry (ALJ decision, November 7, 1997)

Bailey's Limestone Quarry (FMSHRC CENT 97-116-M): Settlement approval denied pending support

Decision type
ALJ decision
Docket
CENT 97-116-M
Decided
November 7, 1997
Presiding judge
Outcome
Procedural
Precedential status
Interlocutory order, not final
Checked against source
2026-08-12

Apply this to your situation

This order from 1997 bound only the parties to this case; it isn't precedent. Ask about your situation and see what the current MSHA standards and Commission precedent say, with citations.

Currency note: this decision dates from 1997
The MSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Interlocutory ALJ order, not Commission precedent
This order denied approval of a proposed settlement while the civil penalty proceeding continued. It did not dispose of the case or become a final decision under the 40-day rule in 30 U.S.C. § 823(d)(1). It is not Commission precedent. The full text below is from the official FMSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official FMSHRC release. The full text is the agency's own release.
Read the official release (fmshrc.gov)

Plain-English summary

Bailey's Limestone Quarry faced two alleged violations after a laborer was fatally injured at the quarry. One citation concerned an unblocked raised loader bucket, and the other concerned late reporting of the accident to MSHA. The parties proposed reducing the combined penalties from $22,500 to $3,500, but did not explain how the amount would be divided or provide enough evidence to support the operator's claimed debt and cash shortage. Judge David Barbour denied approval and ordered the parties to resubmit the settlement with supporting figures or documents within 15 days.

Decision snapshot

  • Cited standards: 30 C.F.R. §§ 56.14211(b), 50.10, and 100.5; 29 C.F.R. § 2700.31(b)(3)
  • Outcome: The motion to approve the settlement was denied, with a supported resubmission ordered.
  • Key point: A substantial penalty reduction in a Mine Act case must be supported by facts that allow the Judge to assess both the proposed penalty and the public interest.

Full text (FMSHRC public release)

FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION

OFFICE OF A D M INISTRA TIV E LA W JUDGES 2 SK YLINE, 10 th FLOOR
5203 LEESBURG PIK E
FA LLS CHURCH, V IRGINIA 22041

November 7, 1997

SECRETARY OF LABOR, : CIVIL PENALTY PROCEEDING
MINE SAFETY AND HEALTH
:
ADMINISTRATION (MSHA), : Docket No. CENT 97-116-M
Petitioner : A. C. No. 34-01794-05503
v. :
: Bailey=s Limestone Quarry
BAILEY=S LIMESTONE QUARRY,
:
Respondent
:

ORDER DENYING MOTION TO APPROVE SETTLEMENT

This case concerns a proposal for assessment of civil penalty filed pursuant to section 105(d) of the Federal Mine Safety and Health Act of 1977 (30 U.S.C. ' 815(d)), seeking the assessment of two alleged violations of mandatory safety standards found in Part 56, Title 30, Code of Federal Regulations.

The alleged violations arose out of the Secretary=s investigation of a fatal accident that occurred on June 29, 1996, at the Respondent=s limestone quarry. The Secretary alleges, in part, that a laborer was fatally injured when he was crushed between the bucket of a front end loader and the metal frame of the primary crusher=s v-belt drive unit.

Citation No. 4448695 alleges a violation of section 56.14211(b) in that the loader bucket was in a raised position and was not blocked to prevent accidental lowering or provided with a load locking device. In addition, the Secretary alleges the violation was a significant and substantial contribution to a mine safety hazard (S&S violation) and the result of the operator=s unwarrantable failure to comply in that a foreman was working at the site at time of the accident and should have recognized the hazard.

Citation No. 4448696 alleges a violation of section 50.10 because the accident, which occurred on June 29, was not reported to MSHA until July 9, 1996.

The Secretary specially assessed both alleged violations (30 C.F.R. ' 100.5). The violation alleged in Citation No. 4448695 was assessed at $20,000, and the violation alleged in Citation No. 4448696 was assessed at $2,500.

After the matters were scheduled for hearing, the parties settled the case. Accordingly, the hearing was canceled. The parties then moved for approval of the settlement. The motion states, AThe parties propose the settlement of these citations by reducing the penalties to the total amount of $3,500.00. No other changes to the citations are proposed.@ The settlement motion does not indicate how the total amount is to be apportioned


Page 2

between the alleged violations, something both I and the Secretary=s Office of Assessment need to know. In addition, although the motion contains a contention that imposition of the originally proposed penalty will adversely affect the Respondent=s ability to continue in business, it does not provided adequate support for such a finding. The motion states only, AThe Respondent is a small business with substantial debt and currently has a severe cash shortage. In order to avoid the costs of further defending the citations, Respondent is willing to settle his case by paying the penalties as amended rather than asserting the defenses to the citations@ (Motion To Approve Settlement Agreement 2).

A case arising under the Mine Act is primarily C but not entirely C the province of the parties. While, in general, they may try or not try a case as they choose, any settlement they reach must reflect not only their particular interests, but those of the public=s as well (S. Rep. No. 95- 181, 95th Cong., 1st Sess. 45, reprinted in Senate Subcommittee on Labor, Committee on Human Resources, 95th Cong. 2d Sess., Legislative History of the Federal Mine Safety and Health Act of 1977, at 633 (1978). This latter interest is implemented by requiring the administrative law judge to approve the settlement (30 U.S.C. ' 820(k)), based upon A[f]acts in support of the penalty agreed to by the parties@ (29 C.F.R. ' 2700.31(b)(3)).

As noted, this case involves a fatality and the charge that the foreman unwarrantably failed to correct a violative practice that resulted in the death. More than in a normal case, sufficient justification must be provided before the penalties can be reduced. The parties propose a reduction of approximately 84 percent in the total penalty, yet they offer no figures or supporting documents regarding the Respondent=s Asubstantial debt@ and Asevere cash shortage@. While the assertions in this regard may well be true, the public interest requires their confirmation.

Until the parties provide more facts to support the proposed penalty, I cannot approve the settlement.

ORDER

Accordingly, the motion to approve the settlement is DENIED. The parties are ORDERED to resubmit the motion, including supporting figures and/or documents within 15 days of the date of this Order. The resubmitted motion must indicate how to apportion the total proposed penalty. Failure to comply with this order will result in the case immediately being scheduled for hearing.

David Barbour
Administrative Law Judge

2


Page 3

Distribution:

Thomas A. Paige, Esq., Office of the Solicitor, U. S. Department of Labor, 525 Griffin Street, Suite 501, Dallas, TX 75202 (Certified Mail)

Mr. Danny Bailey, Bailey=s Limestone Quarry, P. O. Box 996, Wewuka, OK 74884 (Certified Mail)

dcp

3

What applies to your situation today?

This order bound one employer. Ezel checks the current MSHA standards and Commission precedent against your facts, with citations.

Opens in Ezel Pro.

  • Checks the law as it stands today, not only this page
  • Cites every source it relies on, so you can verify it
  • Chat, drafting and research in one workspace