Secretary of Labor v. South Dakota Cement Plant (ALJ decision, October 16, 1980)
South Dakota Cement Plant (FMSHRC CENT 80-297-M): One citation withdrawn and one settled
Apply this to your situation
This order from 1980 bound only the parties to this case; it isn't precedent. Ask about your situation and see what the current MSHA standards and Commission precedent say, with citations.
Plain-English summary
MSHA sought penalties against South Dakota Cement Plant on two citations. The Secretary moved to withdraw Citation No. 329618 because its alleged violation had not occurred. The operator agreed to pay the proposed $78 penalty on Citation No. 330611 and withdrew its contest. Judge Joseph B. Kennedy treated the latter motion as a settlement request requiring approval, granted both motions, and ordered the $78 payment. He dismissed the case subject to payment; the decision does not identify either cited safety standard.
Decision snapshot
- Cited standards: Not identified in the decision.
- Outcome: Citation No. 329618 withdrawn; Citation No. 330611 settled for $78; case dismissed subject to payment.
- Key point: Withdrawing a contest while agreeing to pay a proposed penalty required the judge to approve a settlement.
Full text (FMSHRC public release)
CCASE:
SOL (MSHA) V. SOUTH DAKOTA CEMENT PLANT DDATE: 19801016 TTEXT:
~2928
Federal Mine Safety and Health Review Commission Office of Administrative Law Judges
SECRETARY OF LABOR,
Civil Penalty Proceeding
MINE SAFETY AND HEALTH
ADMINISTRATION (MSHA),
Docket No. CENT 80-297-M
PETITIONER
A.O. No. 39-00967-05011
v. South Dakota Cement Plant
SOUTH DAKOTA CEMENT PLANT,
RESPONDENT
DECISION AND ORDER
The Secretary moves to withdraw and dismiss his proposal for penalty as to citation 329618 on the ground the violation charged did not, in fact, occur. This I construe as a motion to withdraw a pleading and to vacate and proposed penalty ab initio pursuant to Rule 11 and not as a motion to approve settlement under Rule
-
See, Pomerleau Bros. Inc., WILK 79-4-PM (February 13, 1979).
Concurrently, the operator moves to withdraw its notice of
contest as to citation 330611 and to pay the proposed penalty of
$78. It has long been held that the requirements of Rule 30 and section 110(k) of the Act may not be circumvented by resort to Rule 11 through the withdrawal of a notice of contest since this involves approval of the penalty proposed and therefore approval of a settlement. See Pomerleau, supra. The operator's motion will therefore be considered as a motion to approve settlement.Based on an independent evaluation and de novo review of the
circumstances, I conclude both motions should be granted. Accordingly, it is ORDERED that the motion to withdraw and the motion to approve settlement be, and hereby are, GRANTED. It is FURTHER ORDERED the operator pay the amount of the penalty agreed upon, $78.00, on or before Monday, November 3, 1980 and that subject to payment the captioned matter be DISMISSED.Joseph B. Kennedy Administrative Law Judge
What applies to your situation today?
This order bound one employer. Ezel checks the current MSHA standards and Commission precedent against your facts, with citations.
Opens in Ezel Pro.
- Checks the law as it stands today, not only this page
- Cites every source it relies on, so you can verify it
- Chat, drafting and research in one workspace