Secretary of Labor v. Bayer Construction Company, Inc. (Commission decision, November 13, 2009)

Secretary of Labor v. Bayer Construction Company, Inc. (FMSHRC CENT 2009-716-M): Timely cover-letter contest recognized

Decision type
Commission decision
Docket
CENT 2009-716-M
Decided
November 13, 2009
Outcome
Procedural
Precedential status
Citable Commission precedent
Checked against source
2026-08-08

Apply this precedent to your situation

This is citable Commission precedent from 2009, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.

Currency note: this decision dates from 2009
The MSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Decision of the Commission
This is a decision of the Federal Mine Safety and Health Review Commission, the highest level of agency review, citable as Commission precedent. It may have been appealed to a U.S. Court of Appeals after issuance under 30 U.S.C. § 816; check subsequent history before relying on it. The full text below is from the official FMSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official FMSHRC release. The full text is the agency's own release.
Read the official release (fmshrc.gov)

Plain-English summary

Bayer Construction asked to reopen penalties it believed had become final. The Secretary's record review showed that Bayer had timely contested the penalties in a cover letter accompanying payment for other penalties, even though it omitted the assessment form. MSHA corrected its records and treated the contest as timely. Because the assessment had never become final, the Commission found reopening moot and directed the penalty case to proceed.

Decision snapshot

  • Governing provision: 30 U.S.C. § 815(a)
  • Outcome: The reopening request was dismissed as moot, and the Secretary was directed to file a penalty petition if necessary.
  • Key point: A timely cover letter can preserve a penalty contest even when the operator omits the proposed assessment form.

Full text (FMSHRC public release)

Federal Mine Safety and Health Review Commission

FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION

601 NEW JERSEY AVENUE, NW

SUITE 9500

WASHINGTON, DC 20001

November 13, 2009

SECRETARY OF LABOR,

MINE SAFETY AND HEALTH

ADMINISTRATION (MSHA)

v.

BAYER CONSTRUCTION COMPANY, INC.

:

:

:

:

:

:

:

:

Docket No. CENT 2009-716-M

A.C. No. 14-01456-183840

BEFORE: Jordan, Chairman; Duffy, Young, and Cohen, Commissioners

ORDER

BY THE COMMISSION:

This matter arises under the Federal Mine Safety and Health Act of 1977, 30 U.S.C.
§ 801 et seq. (2006) (“Mine Act”). On August 11, 2009, the Commission received from Bayer Construction Company (“Bayer”) a letter seeking to reopen a penalty assessment that may have become a final order of the Commission pursuant to section 105(a) of the Mine Act, 30 U.S.C.

§ 815(a).

Under section 105(a) of the Mine Act, an operator who wishes to contest a proposed penalty must notify the Secretary of Labor no later than 30 days after receiving the proposed penalty assessment. If the operator fails to notify the Secretary, the proposed penalty assessment is deemed a final order of the Commission. 30 U.S.C. § 815(a).

The Secretary submits that upon reviewing the records in this proceeding, she has discovered that the proposed penalty was timely contested. The operator made its contest of the penalties at issue in a cover letter that also contained the payment check for some other penalties and did not include the proposed assessment form. The Secretary asserts that she has corrected her records and the agency is treating the matter as having been timely filed.

Having reviewed Bayer’s request and the Secretary’s response, we find the request to reopen to be moot. Bayer has timely contested the proposed penalty assessment, and therefore it did not become a final order of the Commission. The Secretary shall file a penalty petition within 45 days of the date of this order, if she has not done so already. This case shall proceed pursuant to the Mine Act and the Commission’s Procedural Rules, 29 C.F.R. Part 2700.


Mary Lu Jordan, Chairman


Michael F. Duffy, Commissioner


Michael G. Young, Commissioner


Robert F. Cohen, Jr., Commissioner

Distribution

Stan Hambright, Safety Manager

Bayer Construction Co., Inc.

P.O. Box 889

Manhattan, KS 66505-0889

W. Christian Schumann, Esq.

Office of the Solicitor

U.S. Department of Labor

1100 Wilson Blvd., Room 2220

Arlington, VA 22209-2296

Myra James, Chief

Office of Civil Penalty Compliance

MSHA

U.S. Dept. of Labor

1100 Wilson Blvd., 25th Floor

Arlington, VA 22209-3939

Chief Administrative Law Judge Robert J. Lesnick

Federal Mine Safety & Health Review Commission

601 New Jersey Avenue, N.W., Suite 9500

Washington, D.C. 20001-2021

Does this precedent still control your case?

Ezel checks whether it still stands, including any court review since, and applies it to your situation with citations.

Opens in Ezel Pro.

  • Checks the law as it stands today, not only this page
  • Cites every source it relies on, so you can verify it
  • Chat, drafting and research in one workspace