ISP Minerals, Inc. (Commission decision, February 17, 2009)
ISP Minerals, Inc. (FMSHRC CENT 2008-714-M): Reopening request dismissed because the assessment was never served
Apply this precedent to your situation
This is citable Commission precedent from 2009, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.
Plain-English summary
ISP Minerals asked the Commission to reopen a proposed penalty assessment that it believed had become final. The Secretary determined that the assessment had not been served and planned to send it again to the correct address. The Commission held that without service, the assessment never became a final order under section 105(a) of the Mine Act. It dismissed ISP's reopening motion as moot, leaving ISP 30 days after receipt of the re-sent assessment to contest the penalty.
Decision snapshot
- Governing provision: 30 U.S.C. § 815(a)
- Outcome: ISP's motion to reopen was dismissed as moot because no valid final order existed.
- Key point: A proposed assessment does not become a final Commission order when service was never achieved.
Full text (FMSHRC public release)
Federal Mine Safety and Health Review Commission
FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION
601 NEW JERSEY AVENUE, NW
SUITE 9500
WASHINGTON, DC 20001
February 17, 2009
SECRETARY OF LABOR,
MINE SAFETY AND HEALTH
ADMINISTRATION (MSHA)
v.
ISP MINERALS, INC.
:
:
:
:
:
:
:
Docket No. CENT 2008-714-M
A.C. No. 23-00288-117226
BEFORE: Duffy, Chairman; Jordan, Young, and Cohen, Commissioners
ORDER
BY THE COMMISSION:
This matter arises under the Federal Mine Safety and Health Act of 1977, 30 U.S.C.
§ 801 et seq. (2006) (“Mine Act”). On August 21, 2008, the Commission received from ISP Minerals, Inc. (“ISP”) a motion made by counsel to reopen a penalty assessment that had become a final order of the Commission pursuant to section 105(a) of the Mine Act, 30 U.S.C. § 815(a).
Under section 105(a) of the Mine Act, an operator who wishes to contest a proposed penalty must notify the Secretary of Labor no later than 30 days after receiving the proposed penalty assessment. If the operator fails to notify the Secretary, the proposed penalty assessment is deemed a final order of the Commission. 30 U.S.C. § 815(a).
The Secretary states that upon review of the record, she has found that service of the proposed assessment was not achieved, and as a result, the assessment did not become a valid final order. The Secretary plans to re-send the proposed assessment to the correct address and then ISP will have 30 days after receipt to contest the penalty. Accordingly, the Secretary submits that the request to reopen should be dismissed as moot.
Given the circumstances and in the interest of justice, we conclude that service of the proposed assessment was never made, and thus there is no final order under section 105(a) of the Mine Act. Hence, ISP’s motion is moot and the motion is dismissed.
Michael F. Duffy, Chairman
Mary Lu Jordan, Commissioner
Michael G. Young, Commissioner
Robert F. Cohen, Jr., Commissioner
Distribution:
Brent I. Clark, Esq.
Seyfarth Shaw, LLP
131 S. Dearborn St., Suite 2400
Chicago, IL 60603
W. Christian Schumann, Esq.
Office of the Solicitor
U.S. Department of Labor
1100 Wilson Blvd., Room 2220
Arlington, VA 22209-2296
Myra James, Chief
Office of Civil Penalty Compliance
MSHA
U.S. Dept. Of Labor
1100 Wilson Blvd., 25th Floor
Arlington, VA 22209-3939
Chief Administrative Law Judge Robert J. Lesnick
Federal Mine Safety & Health Review Commission
601 New Jersey Avenue, N.W., Suite 9500
Washington, D.C. 20001-2021
Does this precedent still control your case?
Ezel checks whether it still stands, including any court review since, and applies it to your situation with citations.
Opens in Ezel Pro.
- Checks the law as it stands today, not only this page
- Cites every source it relies on, so you can verify it
- Chat, drafting and research in one workspace