Smithville Sand & Gravel (Commission decision, March 23, 2007)
Smithville Sand & Gravel (FMSHRC CENT 2007-120-M and CENT 2007-121-M): Reopening requests sent for detailed good-cause review
Apply this precedent to your situation
This is citable Commission precedent from 2007, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.
Plain-English summary
Smithville Sand & Gravel did not timely contest two MSHA penalty assessments and later received delinquency notices. The company's general manager asked to reopen the assessments, saying Smithville was a new company, did not understand the rules, and had been misdirected. The Secretary asked for a more detailed explanation before taking a position on relief. The Commission remanded the requests for a judge to decide whether Smithville had good cause for missing the deadlines and instructed the company to explain its circumstances in greater detail.
Decision snapshot
- Governing provisions: 29 C.F.R. § 2700.1(b); 30 U.S.C. § 815(a)
- Outcome: Both reopening requests were remanded for a determination of good cause and possible proceedings on the merits.
- Key point: A general claim of unfamiliarity with the rules requires a detailed factual explanation before a final penalty assessment may be reopened.
Full text (FMSHRC public release)
Federal Mine Safety and Health Review Commission
FEDERAL MINE SAFETY AND HEALTH REVIEW COMMISSION
601 NEW JERSEY AVENUE, NW
SUITE 9500
WASHINGTON, DC 20001
March 23, 2007
SECRETARY OF LABOR,
MINE SAFETY AND HEALTH
ADMINISTRATION (MSHA)
v.
SMITHVILLE SAND & GRAVEL
:
:
:
:
:
:
:
:
:
Docket No. CENT 2007-120-M
A.C. No. 41-04614-99988
Docket No. CENT 2007-121-M
A.C. No. 41-04614-102470
BEFORE: Duffy, Chairman; Jordan and Young, Commissioners
ORDER
BY THE COMMISSION:
This matter arises under the Federal Mine Safety and Health Act of 1977, 30 U.S.C.
§ 801 et seq. (2000) (“Mine Act”).
On February 6, 2007, the Commission received from
Smithville Sand & Gravel (“Smithville”) requests from its general manager seeking to reopen penalty assessments that had become final orders of the Commission pursuant to section 105(a) of the Mine Act, 30 U.S.C. § 815(a).
Under section 105(a) of the Mine Act, an operator who wishes to contest a proposed penalty must notify the Secretary of Labor no later than 30 days after receiving the proposed penalty assessment. If the operator fails to notify the Secretary, the proposed penalty assessment is deemed a final order of the Commission. 30 U.S.C. § 815(a).
During August 2006, the Department of Labor’s Mine Safety and Health Administration (“MSHA”) issued citations and an order to Smithville. On October 5 and November 2, MSHA issued proposed assessments to which Smithville did not respond. On January 4 and February 1, 2007, MSHA’s Civil Penalty Compliance Office sent Smithville delinquency notices regarding the penalties that had become final orders. In its requests, Smithville states that it is a “new company,” was “ignorant of the rules,” and was “misdirected.” In her response, the Secretary requests that Smithville provide a detailed explanation as to why it believes that reopening is warranted and that the Secretary will respond further as to whether such relief is warranted.
We have held that in appropriate circumstances, we possess jurisdiction to reopen uncontested assessments that have become final Commission orders under section 105(a). Jim Walter Res., Inc., 15 FMSHRC 782, 786-89 (May 1993) (“JWR”). In evaluating requests to reopen final section 105(a) orders, the Commission has found guidance in Rule 60(b) of the Federal Rules of Civil Procedure under which, for example, a party could be entitled to relief from a final order of the Commission on the basis of inadvertence or mistake. See 29 C.F.R.
§ 2700.1(b) (“the Commission and its Judges shall be guided so far as practicable by the Federal Rules of Civil Procedure”); JWR, 15 FMSHRC at 787. We have also observed that default is a harsh remedy and that, if the defaulting party can make a showing of good cause for a failure to timely respond, the case may be reopened and appropriate proceedings on the merits permitted. See Coal Prep. Servs., Inc., 17 FMSHRC 1529, 1530 (Sept. 1995).
Having reviewed Smithville’s requests, in the interests of justice, we remand this matter to the Chief Administrative Law Judge for a determination of whether good cause exists for Smithville’s failure to timely contest the penalty proposals and whether relief from the final orders should be granted. Before the judge, Smithville should provide a more detailed explanation of whether it is entitled to a reopening of the penalty assessments under the principles noted above. If it is determined that such relief is appropriate, these cases shall proceed pursuant to the Mine Act and the Commission’s Procedural Rules, 29 C.F.R. Part 2700.
______
Michael F. Duffy, Chairman
______
Mary Lu Jordan, Commissioner
______
Michael G. Young, Commissioner
Distribution
Oscar Lopez, General Manager
Smithville Sand & Gravel
10202 Synott Road
Sugar Land, TX 77478
W. Christian Schumann, Esq.
Office of the Solicitor
U.S. Department of Labor
1100 Wilson Blvd., 22nd Floor
Arlington, VA 22209-2296
Chief Administrative Law Judge Robert J. Lesnick
Federal Mine Safety & Health Review Commission
601 New Jersey Avenue, N.W., Suite 9500
Washington, D.C. 20001-2021
Does this precedent still control your case?
Ezel checks whether it still stands, including any court review since, and applies it to your situation with citations.