Norma J. & Frank J. Echevarria d/b/a Echeco Environmental Services
In re Norma J. and Frank J. Echevarria d/b/a Echeco Environmental Services (EAB CAA Appeal No. 94-1): asbestos wetting violations affirmed
Apply this precedent to your situation
This is citable Board precedent from 1994, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.
Plain-English summary
Echeco Environmental Services performed asbestos abatement work at the North Gem School in Bancroft, Idaho. An EPA inspector found that pipe insulation removed during the work was not adequately wet because it was stiff and dry and released dust and fibers when broken. The Environmental Appeals Board held that Echeco's vagueness challenge was not properly available in the enforcement appeal and that the inspector's testimony and supporting evidence established violations of the asbestos work-practice standards. The Board affirmed the Initial Decision and the $9,450 civil penalty.
Decision snapshot
- Cited authorities: 40 C.F.R. §§ 22.24, 22.30(a), 61.141, 61.145(a)(1), 61.145(c)(3), 61.145(c)(6)(i), and 61.150; 42 U.S.C. §§ 7412, 7412(h), 7602(k), and 7607(b).
- Outcome: The Initial Decision was affirmed, including liability for failures to keep asbestos-containing pipe insulation adequately wet during removal and until collection for disposal, and the $9,450 civil penalty.
- Key point: Under the asbestos NESHAP, visible emissions from asbestos-containing material show that the material was not adequately wet, and a trained inspector's credible observations can establish a violation.
Full text (EPA EAB public release)
626 ENVIRONMENTAL ADMINISTRATIVE DECISIONS
IN RE NORMA J. ECHEVARRIA
AND FRANK J. ECHEVARRIA
D/B/A ECHECO ENVIRONMENTAL SERVICES
CAA Appeal No. 94-1
FINAL DECISION
Decided December 21, 1994
Syllabus
Norma J. Echevarria and Frank K. Echevarria, doing business as Echeco Environmental
Services (“Echeco”), appeal the assessment against them of a $9,450.00 civil penalty for
being found in violation of certain work practice standards relating to the removal of asbes-
tos-containing materials. The presiding officer determined that the material removed by
Echeco was not “adequately wet” in accordance with the standards, since dust was emitted
from a block of the material upon inspection by an EPA inspector who found it lying
unbagged on the floor of the removal site. As a threshold matter, Echeco contends that the
work practice standards are unconstitutionally vague and therefore unenforceable. Secondly,
even if the standards are enforceable, Echeco disputes the fact that a violation occurred,
asserting that the presiding officer’s ruling is not supported by a preponderance of the
evidence because it rests solely on the testimony of the EPA inspector, which by itself is not
a sufficient basis upon which to sustain the charges.
Held: The initial decision of the presiding officer is affirmed. Echeco failed to demon-
strate any compelling circumstances justifying review of its claim that the work practice
standards are unconstitutionally vague and unenforceable. Moreover, as a practical matter,
its claim is effectively barred from administrative review as a matter of right by Clean Air Act
§ 307(b), the statutory provision precluding untimely judicial review of duly promulgated
emission and work practice standards. In addition, the presiding officer did not err by
relying on the inspector's testimony, which was unrefuted and not shown to be unreliable.
Before Environmental Appeals Judges Nancy B. Firestone,
Ronald L. McCallum, and Edward E. Reich.
Opinion of the Board by Judge McCallum:
On December 22, 1993, Chief Administrative Law Judge Henry B.
Frazier, III issued an initial decision finding Norma J. Echevarria and
Frank K. Echevarria, doing business as Echeco Environmental Services
(“Echeco”), liable for violating Clean Air Act § 112, 42 U.S.C. § 7412,
and certain regulations appearing at Subpart M (National Emission
Standard for Asbestos) of the National Emission Standards for Hazard-
VOLUME 5
NORMA J. ECHEVARRIA AND FRANK J.ECHEVARRIA 627
ous Air Pollutants (“(NESHAP”), 40 C.F.R. Part 61. Specifically, the pre-
siding officer found that Echeco violated 40 C.F.R. § 61.145(c)(3) and
(c)(6)(i), which are emission standards (more precisely, work practice
standards) for asbestos. These work practice standards require asbes-
tos-containing material to be kept adequately wet while it is being
removed from a facility component and until it is collected for dis-
posal. For these violations, the presiding officer assessed a penalty of
$9,450. Pursuant to the applicable procedural rules, 40 C.F.R. § 22.30(a),
Echeco has appealed the presiding officer’s decision, contending that
the initial decision should be reversed because the liability finding is
not supported by a preponderance of the evidence, and because the
regulations at issue are unconstitutionally vague. For the reasons set
forth below, we uphold the initial decision of the presiding officer.
I. BACKGROUND
Norma J. Echevarria and Frank J. Echevarria are husband and wife
who do business as Echeco Environmental Services. In 1991, Echeco
contracted to perform asbestos abatement work at the North Gem
School in Bancroft, Idaho. In particular, Echeco was hired to remove
asbestos-containing insulation from the boiler and the pipes in the
school’s boiler room.' The surface of the boiler was covered by asbes-
tos-containing magnesium block insulation. The pipes were insulated
with corrugated pipe lagging containing asbestos. The insulation in the
boiler room had been encapsulated in the 1980s with several layers of
cheese cloth and latex paint, resulting in an almost cast-hard
encapsulant on the boiler and the pipes.
Echeco began work on June 3, 1991. Prior to removing any insu-
lation, Echeco established a containment area in the boiler room.?
Echeco utilized an airless sprayer hung near the center of the room to
spray the entire boiler room with amended water during the abate-
ment project. The water was amended with a surfactant to enhance its
absorption by the asbestos-containing materials. Echeco also utilized a
negative air machine to remove airborne asbestos fibers in the boiler
room during the abatement project.
1 Echeco was also hired to remove asbestos-containing insulation from the pipes under
the school’s gymnasium. This portion of Echeco's work, however, is not at issue in this case.
2 Specifically, Echeco installed a double layer of barriers over the windows and doors of
the boiler room, and installed a decontamination unit at the entrance to the contained boiler
room. The decontamination unit consisted of a clean room, a shower room, and a small dirty
room. The drain in the middle of the boiler room floor was sealed so that no water from the
abatement project would enter the wastewater system.
VOLUME 5
628 ENVIRONMENTAL ADMINISTRATIVE DECISIONS
Brad Browning was the only Echeco employee to remove asbes-
tos-containing insulation from the boiler room. Browning first removed
the insulation from the boiler. On the second day of the project, June 4,
1991, Browning began to strip the insulation from the pipes. Browning
attempted to wet the pipe insulation material as it was being removed
from the pipes by cutting holes in the encapsulant and inserting a
water hose into the holes. The water from the hose did not contain a
surfactant. As Browning removed the pipe insulation, he placed it on
the floor in the boiler room to absorb the water that had collected on
the floor. At the end of the workday, Browning’s practice was to place
the insulation stripped that day in bags with water and seal them with
duct tape. When he left the containment area for lunch on June 4,
Browning left the asbestos-containing insulation that had been re-
moved from the pipes that morning unbagged and on the floor.
Rebecca Goehring is an EPA inspector trained in how to deter-
mine compliance with the asbestos NESHAP requirements. As part of
her training, Goehring was schooled in how to determine if asbestos-
containing material is adequately wet. According to Goehring, one
method of determining compliance with the adequately wet require-
ments “is the hands-on method, to pick up the sample, to break it, to
handle it, to rub your hand across it, to see whether or not it emits any
fibers or dust that you can see.” Tr. at 24. Further, Goehring explained,
she was trained to obtain samples from “piles of materials sitting on
the ground * * * to determine whether or not they were adequately
wet.” Id. at 26.In the course of her employment, Goehring conducted
over 300 asbestos NESHAP inspections. /d.
While Browning and other Echeco employees were at lunch on
June 4, Goehring inspected the work in progress in the boiler room.
The Echeco employees returned from lunch during her inspection, but
did not enter the containment area to observe the inspection. Goehring
remained in the containment area for approximately 20 minutes. Dur-
ing that time, she observed that the boiler had been completely stripped
of its magnesium block insulation, and that all of this insulation was in
bags on the floor. Goehring opened one of the bags and pulled out a
piece of magnesium block. When she broke this sample, it emitted
dust. The inside of the piece between the wet outside layers was dry
and crumbled. Later laboratory testing revealed that this insulation
sample was 35% amosite asbestos.
In contrast to the boiler, the pipes in the boiler room had only
been partially stripped of their insulation at the time of the inspection.
Goehring estimated that one-quarter of the pipe insulation that had
been removed was bagged; the remaining three-quarters of the re-
VOLUME 5
NORMA J. ECHEVARRIA AND FRANK J.ECHEVARRIA 629
moved pipe insulation was lying on the floor unbagged. Goehring
observed that the pile of unbagged pipe insulation was “semi-wet.” Tr.
217-18. However, when she tore a sample of the insulation from this
pile, Goehring found that it was “very stiff, very dry” and that it “emit-
ted fibers, released dust.” Tr. 39. Later laboratory testing revealed that
this sample contained 95% chrysotile asbestos.
Goehring’s observations were recorded in a written inspection
report and in photographs taken in the containment area, all of which
were admitted into evidence in this proceeding. The report indicated
that the exterior of the pipe insulation lying unbagged on the boiler
room floor was:
[W]hite and dusty with approximately fifty percent of
the surface showing darker water spots. The interior
surface of the pipe insulation was dry and white and
showed the darker water spotted areas only near the
end quarter sections of each piece. The paper covering
and corrugated interior of the insulation released dust
when the insulation was handled or torn.
Inspection Report (Compl. Ex. 1) at 4. The photographs of the pile of
pipe insulation conform to the descriptions contained in the inspec-
tion report. Compl. Exs. 9A, 9D.
Based upon the June 4 inspection, U.S. EPA, Region X, filed a
complaint alleging that Echeco’s asbestos abatement activities at the
North Gym School on June 4 violated the NESHAP for asbestos con-
tained in 40 C.F.R. Part 61, Subpart M. Specifically, the complaint al-
leged that based upon the inspector's observations, Echeco violated 40
C.F.R. § 61.145(c)(3) by failing to keep the asbestos-containing insula-
tion from the boiler and the pipes adequately wet while it was being
removed, and 40 C.F.R. § 61.145(c)(6)(i) by failing to make sure that
the removed asbestos-containing insulation from the boiler and the
pipes remained adequately wet until it was collected for disposal. For
these alleged violations, the complaint sought a penalty of $43,400.
Echeco denied the alleged violations, and a hearing was held in
this matter on July 20-22, 1993 in Pocatello, Idaho. At the hearing, the
Region relied primarily upon the inspector's testimony to establish the
alleged violations. In response, Echeco relied primarily upon the tes-
timony of Browning, the Echeco employee assigned the responsibility
of removing the asbestos-containing material in the boiler room, to
contend that the asbestos-containing insulation was adequately wetted
when stripped and until collected for disposal. Echeco also produced
VOLUME 5
630 ENVIRONMENTAL ADMINISTRATIVE DECISIONS
testimony to support its legal claim that the asbestos NESHAP require-
ments were unconstitutionally vague and thus unenforceable. Steve
Harrington, an expert witness on behalf of Echeco, testified as to the
vague and ambiguous nature of the “adequately wet” requirement, the
absence of uniform, objective and quantifiable standards for measur-
ing compliance with the requirement, and the impossibility of prevent-
ing emissions during asbestos removal work. Initial Decision at 21.
The presiding officer issued his initial decision on December 22,
1993, finding Echeco liable for the alleged violations and assessing a
penalty of $9,450. The presiding officer refused to entertain Echeco’s
contention that the pertinent asbestos NESHAP regulations are uncon-
stitutionally vague on the basis that section 307(b) of the Clean Air Act,
42 U.S.C. § 7607(b), bars challenges to the regulations in this enforce-
ment proceeding. That statutory provision provides that challenges to
regulations and requirements promulgated under Clean Air Act § 112,
such as the asbestos NESHAP requirements, can only be raised by a
petition filed in the U.S. Court of Appeals for the District of Columbia
within 60 days of the regulation’s or requirement’s promulgation, Pur-
ther, the statute provides that if a regulation or requirement could have
been challenged in such a fashion, it shall not be subject to judicial
review in civil enforcement actions.*
Proceeding to the violations alleged in the complaint, the presid-
ing officer first rejected Echeco’s contention that the testimony of the
EPA inspector is not credible. The presiding officer found that Goehring’s
testimony that the asbestos-containing insulation was not adequately
wet was not refuted by that of Browning, the only Echeco employee
working in the boiler room, who had acknowledged that “on every job
have ever been on I have seen visible emissions of some type.” Tr. at
- In addition, the presiding officer noted, none of Echeco’s other
witnesses contradicted Goehring’s factual testimony. Goehring’s testi-
3In pertinent part, Clean Air Act § 307(b) provides:
(1) A petition for review of action of the Administrator in pro-
mulgating any ** * emission standard or requirement under sec-
tion 7412 [Clean Air Act § 112] of this title * * * may be filed only
in the United States Court of Appeals for the District of Colum-
bia. * * * Any petition for review under this subsection shall be
filed within sixty days from the date notice of such promulga-
tion, approval, or action appears in the Federal Register ** *.
(2) Action of the Administrator with respect to which review
could have been obtained under paragraph (1) shall not be sub-
ject to judicial review in civil or criminal proceedings for en-
forcement.
42 U.S.C. § 7607(b).
VOLUME 5
NORMA J. ECHEVARRIA AND FRANK J.ECHEVARRIA 631
mony, the presiding officer concluded, indicated that the pipe insula-
tion laying unbagged on the boiler room floor “emitted fibers and
released dust when the EPA inspector broke it,” and therefore was not
adequately wet. The presiding officer relied upon this testimony to
find that Echeco violated both 40 C.F.R. § 61.145(c)(3) and (c)(6)(i).
Specifically, the presiding officer concluded that Echeco “failed to
comply with the NESHAP work practices to adequately wet the [asbes-
tos-containing pipe insulation] during the stripping operation from the
pipe in the boiler room and to adequately wet the {asbestos-containing
insulation] stripped from the pipe and ensure that it remained wet
until collected and contained or treated in preparation for disposal.”
Initial Decision at 30. However, concerning the insulation removed
from the boiler, the presiding officer concluded that the requirements
of § 61.145 did not apply to those materials because they had been
collected for disposal, i.e., bagged, and therefore Echeco did not vio-
late the adequately wet requirements with respect to the insulation
removed from the boiler.‘ For the violations found, the presiding of-
ficer assessed a penalty of $9,450.°
Echeco promptly appealed the presiding officer's decision. Echeco
contends that the vagueness of 40 C.F.R. § 61.145(c)(3) and (c)(6)(i)
renders the regulation unconstitutionally void and unenforceable. In
addition, Echeco contends that the presiding officer’s finding that
Echeco violated 40 C.F.R. § 61.145(c)(3) and (c)(6)(i) is not supported
by a preponderance of the evidence.
Il. ANALYSIS
The complaint alleges violations of Clean Air Act § 112, 42 U.S.C.
§ 7412, and its implementing regulations. Section 112(b)() lists pollut-
ants that Congress has determined present, or may present, a threat of
adverse human health or environmental effects; asbestos is on that list.
The statute also requires EPA to promulgate emission standards for
point sources of pollutants on the list, known as the National Emission
Standards for Hazardous Air Pollutants or “NESHAP.” Clean Air Act
§ 112(d), 42 U.S.C. § 7412(d). However, Congress recognized that in
some instances, emission standards applicable to point sources alone
would not be effective in controlling emissions of hazardous air pol-
‘The Region disagrees with this portion of the presiding officer's initial decision, Appellee EPA.
Region 10's Reply to Appellants’ Notice of Appeal and Brief at 7-8 n.2. “However, since the Presid-
ing Officer found liability for each violation based upon the unbagged pipe insulation * * *, Region
10 elected not to appeal the finding and conclusion concerning the magnesium block” insulation
removed from the boiler. 1d.
‘The Region has not appealed the presiding officer's penalty assessment.
VOLUME 5
632 ENVIRONMENTAL ADMINISTRATIVE DECISIONS
lutants to a safe level. For example, Congress explained that the emis-
sion of asbestos fibers during construction or demolition could not be
controlled by focusing on a point source. Therefore, Congress autho-
rized EPA to promulgate work practice standards under Clean Air Act
§ 112 to meet the statute’s objectives. Clean Air Act § 112(h).’
The NESHAP for asbestos consists of the work practice standards
set forth in 40 C.F.R. Part 61 Subpart M. Involved here are the work
practice standards set forth in § 61.145(c)(3) and (c)(6)(i). In pertinent
part, § 61.145(c) provides:
(¢) Each owner or operator of a demolition or renovation
activity * * * shall comply with the following procedures:
-
- & & & #
(3) When RACM [regulated asbestos containing ma-
terial] is stripped from a facility component while it
remains in place in the facility, adequately wet the
RACM during the stripping operation.
se * e & & # #
® Specifically, Congress said:
Generally, the requirements of section 112 of the Clean Air Act
- © * are implemented by the promulgation of numerical emis-
sion standards applicable to point sources of release * * * from
stationary sources of the listed pollutants. However, in some
cases regulation in this form would not be effective or appro-
priate for significant source categories. For instance, emissions
of asbestos fibers from construction or demolition sites cannot
be controlled or even measured by focusing on a point source
of emissions. To assure that adequate control is, nevertheless,
achieved, it is in some cases possible to prescribe the use of
specific equipment or procedures in the design of a facility or
conduct of an activity. In the 1977 amendments to the Clean Air
Act * * * the Congress authorized the use of other regulatory
requirements including design, equipment, work practice or
operational standards as an alternative to emission standards to
carry out the objectives of section 112.
S. Rep. No. 101-228, 101st Cong., 2d Sess. (1990) Geprinted in 1990 U.S.C.C.A.N. 3385, 3567) (em-
phasis added).
7 This section of the Clean Air Act provides:
For purposes of this section, if it is not feasible in the judgment
of the Administrator to prescribe or enforce an emission stan-
dard for control of a hazardous air pollutant or pollutants, the
Administrator may, in lieu thereof, promulgate a design, equip-
ment, work practice, or operational standard, or combination
thereof * **.
42 U.S.C, § 7412(h)) (emphasis added).
VOLUME 5
NORMA J. ECHEVARRIA AND FRANK J.ECHEVARRIA 633
(6 For all RACM, including material that has been
removed or stripped:
(@® Adequately wet the material and ensure that it remains
wet until collected and contained or treated in prepara-
tion for disposal in accordance with § 61.1501]
In essence, these work practice standards require a person engaged in
the removal of asbestos-containing material to keep such material
adequately wet during the removal process and until it is collected for
disposal. “Adequately wet” means:
[Slufficiently mix or penetrate with liquid to prevent
the release of particulates. If visible emissions are
observed coming from asbestos-containing material,
then that material has not been adequately wetted.
However, the absence of visible emissions is not
sufficient evidence of being adequately wet.
40 C.F.R. § 61.141. Wetting to prevent the release of particulates is the
primary method of controlling asbestos emissions during demolition
or renovation work.®
The asbestos NESHAP imposes a standard of strict liability for
violating any of the work practice standards. United States v. Sealtite
Corp., 739 F. Supp. 464, 468 (E.D. Ark. 1990); United States v. Ben’s
Truck and Equipment, Inc., 25 ERC 1295, 1298 (E.D. Cal. 1986). To
impose liability under the asbestos NESHAP, the Agency must make a
two-fold showing: first, the Agency must show that the NESHAP re-
quirements apply, and second, that the work practice standards of the
NESHAP have not been satisfied. United States v. MPM Contractors,
Inc., 767 F. Supp. 231, 233 (D. Kan. 1990). Here, Echeco admits that
the asbestos NESHAP work practice standards applied to its work at
the North Gem School.’ As to the second prong, Echeco contends that
these work practice standards are unconstitutionally vague, and that
even if the standards are enforceable, the conclusion that Echeco vio-
lated the standards is not supported by a preponderance of the evi-
dence. Each of these contentions will be addressed in turn.
SEPA, Asbestos/NESHAP Adequately Wet Guidance at 1 (Dec. 1990).
°The asbestos work practice standards are applicable if the requirements found in 40 C.F.R.§
61.145(a)(1) are met. That particular regulatory provision provides that the asbestos work practice
standards apply to “owners or operators” of a “demolition or renovation activity” if the combined
amount of asbestos-containing material to be stripped and removed is at least 260 linear feet on
pipes or 160 square feet on other facility components. In its answer to the complaint, Echeco admit-
ted that it was the owner or operator of a renovation activity at the North Gem School involving the
requisite amount of asbestos-containing material. Answer at 2.
VOLUME 5
634 ENVIRONMENTAL ADMINISTRATIVE DECISIONS
A. Vagueness of the Work Practice Standards
In this appeal, Echeco contends that the work practice standards
are “void and constitutionally unenforceable on grounds of vague-
ness.” Appellants’ Brief in Support of Alternative Findings of Fact, Al-
ternative Conclusions of Law and Order at 16 (“Appellants’ Brief”).
Echeco asserts that Clean Air Act § 307(b), 42 U.S.C. § 7607(b), does
not apply here to preclude review of Echeco’s constitutional challenge
to the work practice regulations. According to Echeco, § 307(b) pre-
cludes only judicial review; there is no statutory provision precluding
administrative review. Also, Echeco argues, relying upon Adamo Wreck-
ing Co. v. United States, 434 U.S. 275 (1978), § 307(b) precludes only
review of emission standards, not work practice standards. Alterna-
tively, Echeco argues that if the statute does preclude review of Echeco’s
constitutional challenges to the work practice standards, the statute is
itself unconstitutional.
We are not persuaded by Echeco’s arguments. In our opinion, the
presiding officer was correct, for the reasons stated below, in refusing to
entertain Echeco’s challenge to the constitutional validity of the appli-
cable work practice standards. As a “general rule * * * challenges to
rulemaking are rarely entertained in an administrative enforcement pro-
ceeding.” In re American Ecological Recycle Research Corp., RCRA (3008)
Appeal No. 83-3, at 5-6 (CJO, July 18, 1985) (citing In re Transportation,
Inc., Docket No. CAA(211)-27, et al., at 8 n.8 (CJO, Feb. 15, 1982) and In
re Dow Chemical Co., Docket No. TSCA(6(a))-1, at 17 n. 19 (CJO, July
28, 1982)). This general rule applies even when a party asserts that a rule
is unconstitutionally vague. In re South Coast Chemical, Inc., FIFRA Ap-
peal No. 84-4, at 10 (CJO, Mar. 11, 1986). The decision to entertain such
challenges is at best discretionary, and review of a regulation will not be
granted absent the most compelling circumstances. Id. at 10, American
Ecological Recycle Research Corp. at 6.
This presumption against challenges to the validity of a regulation in
enforcement proceedings is a rule of practicality. While it is true, as Echeco
asserts, that Clean Air Act § 307(b) only makes direct reference to preclu-
sion of judicial review, not administrative review, the effect of this statu-
tory provision is to make it unnecessary for an administrative agency to
entertain as a matter of right a party’s challenge to a rule subject to this
statutory provision. Thus, ordinarily, the only way for a regulation that is
subject to a preclusive review provision to be invalidated is by a court in
accordance with the terms of the preclusive review provision. In the case
Specifically, Echeco asserts that the asbestos NESHAP regulations provide “no practical or
objective quantifiable or qualitative standard or measure of what is adequately wet.” Respondents’
Brief in Support of Proposed Findings of Fact and Conclusions of Law at 8.
VOLUME 5
NORMA J. ECHEVARRIA AND FRANK J.ECHEVARRIA 635
of the Clean Air Act, § 307(b)(1) provides inter alia that challenges to any
regulation or requirement promulgated under Clean Air Act § 112 must be
brought within 60 days of promulgation by a suit in the United States
Court of Appeals for the District of Columbia. Manifestly, neither Echeco
nor anyone else has succeeded in having a court invalidate the asbestos
work practice standard at issue in this case. Therefore, the rule is no
longer subject to judicial challenge, and the Agency, for reasons of admin-
istrative efficiency, is obviously not interested in reexamining such a rule
in an administrative proceeding. Once the rule is no longer subject to
court challenge by reason of the statutory preclusive review provision,
the Agency is entitled to close the book on the rule insofar as its validity
is concerned."! RSR Corp. v. Donovan, 747 F.2d 294, 301 (th Cir. 1984)
(“An agency has an interest in finality and conservation of its resources.
It should not be compelled to defend the same regulation against identi-
cal attacks in successive enforcement actions, when those challenges
could and should have been asserted in the period before pre-enforce-
ment review.”). The Agency retains the power, however, to repeal or
amend the rule if the rule no longer serves its intended purposes. Simi-
larly, citizens may petition the Agency to repeal or amend a rule if it is not
to their liking."? In both instances, however, the means of repealing or
amending the rule are carried out in the context of a rulemaking forum,
not an enforcement proceeding. Gf, SEC v. Chenery, 332 U.S. 194, 203
(1947) (“the choice made between proceeding by general rule or by
individual ad boc litigation is one that lies primarily in the informed
discretion of the administrative agency.”).
The presumption against entertaining a challenge to the validity of a
regulation is thus an especially strong presumption," which, for the rea-
sons set forth below, operates to bar Echeco’s challenge to the validity of
‘In this connection, the Board's refusal to entertain a challenge to a regulation's validity is not
itself reviewable in any subsequent appeal to the court. For a party to seek judicial review of the
regulation in that manner, i.c., under the guise of having the court review the Board's refusal, would
amount to nothing more than a transparent attempt to evade the very thing that § 307(b) seeks to
prevent, ie., untimely judicial review of duly promulgated regulations.
22 See In re Petroleum Management, Inc., UIC Appeal No. 87-5, at n. 10 (Adm’r, Sept. 15, 1988)
(petitioner could have raised challenge toa rule by seeking a repeal or amendment of rule pursuant
105 U.S.C. §553(e)); American Ecological Recycle Research Corp. at n.3 (repeal of a rule is a form of
rulemaking).
3But as a rule of practicality, some recognition must be given to the possibility of an excep-
tional case. Thus, if an extremely compelling argument were made as to a rule’s invalidity (for
example, where it has been held invalid in an intervening court decision), the Board could rely on
it to dismiss the complaint. See, e.g., In re Transportation, Inc., supra (administrative hearing pro-
cess for enforcing violations of CAA § 211(d) ruled invalid as being contrary to statute); In re 170
Alaska Placer Mines, More or Less, NPDES Appeal No. 79-1, at 17 (Adm’r, Mar. 10, 1980) (super-
seded rule that improperly shifted the burden of persuasion “must be regarded as a nullity, since it
is tantamount to a revision of the statutory scheme and is, therefore, beyond the agency's
Continued
VOLUME 5
636 ENVIRONMENTAL ADMINISTRATIVE DECISIONS
the asbestos work practice standards. Turning first to Echeco’s assertion
that Clean Air Act § 307(b) applies only to emission standards, not work
practice standards, we are convinced that there is no merit to the asser-
tion. Echeco relies upon Adamo Wrecking Co., which held that the then-
applicable version of § 307(b) applied only to emission standards. In
Adamo Wrecking Co., the Court concluded that a work practice standard
is not an emission standard, and therefore that § 307(b) did not apply to
work practice standards. That case is not helpful here, however, because
the version of the Clean Air Act applicable to Echeco is different than the
version interpreted in Adamo Wrecking Co. The version of § 307(b) at
issue in Adamo Wrecking Co. applied to “any emission standard [promul-
gated] under [Clean Air Act] section 112.” Before the final decision in
Adamo Wrecking Co., Congress amended § 307(b) to cover “any emission
standard or requirement under section 112.” See Adamo Wrecking Co. at
286 n.4 (emphasis added). It is the amended version of § 307(b) that
controls here. Plainly, a work practice standard promulgated under § 112
is a requirement of § 112 for the purposes of § 307(b).'* Further, after the
decision in Adamo Wrecking Co., Congress again amended the Clean Air
Act, this time providing that for the purposes of § 307(b), an “emission
standard” is defined to include any work practice standard. Clean Air Act
§ 302(k), 42 U.S.C. § 7602(k). Thus, as either an “emission standard” or a
“requirement” under § 112, a work practice standard is plainly now cov-
ered by § 307(b). See U.S. v. Walsh, 8 F.3d 659 (th Cir. 1993) (constitu-
tional challenge to the asbestos NESHAP work practice standards pre-
cluded by § 307(b)).
authority to promulgate.”). In such circumstances, it would be ridiculous for the Board to uphold.
charges in a complaint that are based on an invalid rule merely because the rule remained on the
books, i.e., had not been repealed or amended in a rulemaking proceeding. The act of repealing the
rule can always be undertaken at a later date independently of the enforcement action. See 51 Fed.
Reg. 25253 (July 11, 1986) (“As a result of the administrative opinion in the case, Jn re: Transporta-
tion, Inc., Docket No. CAA (211) - 27, [supral, EPA ceased its administrative hearing process for
enforcing the regulations under Part 80, and in 1982 adopted new procedures to implement 211(d)
of the [Clean Air] Act.”); 45 Fed. Reg. 33415 (May 19, 1980) (rule conforming to interpretation in J
re 170 Placer Mines, More or Less, supra). In addition, rather than having the Board dismiss the
complaint outright, the option of staying the enforcement proceeding to allow a rulemaking pro-
ceeding to mun its course would also be available.
¥ See Clean Air Act § 112(h), 42 U.S.C. § 7412(h), which authorizes the Agency to promulgate
work practice standards in lieu of emission standards when emission standards cannot feasibly be
prescribed or enforced.
5 As Echeco notes, the Walsh court relied upon a provision in the Clean Air Act that “any
work practice * * * standard * * * shall be treated as an emission standard for purposes of the provi-
sions of this chapter.” 659 F.2d at 661. This provision, as a result of amendments adopted in 1990, is
no longer a part of the Clean Air Act, and therefore, Echeco asserts, Walsh is not persuasive on this
issue. What Echeco overlooks, and we find significant, is that the very same amendments expanded
the definition of “emission standard” in § 302(k) to include work practice standards. In our opinion,
this expanded definition has the same effect as the language relied upon in Walsh, and therefore
Echeco’s assertion that Walsh is not persuasive lacks merit.
VOLUME 5
NORMA J. ECHEVARRIA AND FRANK J.ECHEVARRIA 637
Given that § 307(b) applies to the asbestos work practice stan-
dards, nothing Echeco has argued persuades us that there is a compel-
ling basis for entertaining a challenge to the validity of the standards.
Although Echeco asserts that “{ilt is difficult to imagine a more compel-
ling question than whether a United States agency can enforce regula-
tions and impose severe penalties, where the regulations on their face
and as applied’ are constitutionally void for vagueness,” Appellants’
Brief at 17, the mere assertion of a constitutional claim alone does not
amount to a compelling circumstance justifying a deviation from the
general rule against reviewing the validity of regulations in administra-
tive enforcement actions. Moreover, nothing that Echeco has said per-
suades us that the regulation is impermissibly vague. As defined, the
term “adequately wet” means that the asbestos-containing material is
sufficiently wet to “prevent the release of particulates.” 40 C.F.R. § 61.141.
This definition provides a person of ordinary intelligence a reasonable
opportunity to know what conduct is prohibited, or conversely, what
conduct is required. See Grayned v. City of Rockford, 408 U.S. 109 (1972)
(a regulation will be declared unconstitutionally vague only if it does not
provide a person of ordinary intelligence reasonable notice of the prohib-
ited conduct). Here, Inspector Goehring’s testimony demonstrates that
visible particulates were present, thus providing objective and ascertainable
proof that the pipe insulation was not adequately wet.
Lastly, Echeco argues that if § 307(b) precludes constitutional chal-
lenges to regulations within its ambit we should hold § 307(b) itself un-
constitutional. As discussed above, the board has concluded that § 307(b)
establishes a presumption of nonreviewability that Echeco has not over-
come. More importantly, however, this issue is clearly beyond this Board’s
purview. Mathews v. Diaz, 426 U.S. 67, 76 (1976) (constitutionality of a
statute is beyond an agency’s competence); Johnson v. Robison, 415 U.S.
361, 368 (1974) (adjudication of the constitutionality of Congressional
enactments has generally been thought beyond the jurisdiction of admin-
istrative agencies,” quoting Oestereich v. Selective Service System Local
Board, 393 U.S. 233, 242 (1968)); Robinson v. U.S., 718 F.2d 336, 338 (10th
Cir. 1983) (agency may not declare a statute unconstitutional)."” Accord-
ingly, for all of the reasons stated above, we reject Echeco’s efforts to
‘©Nowhere on appeal does Echeco articulate how or why the application of the work practice
standards results in an infringement of any constitutionally protected rights. Our discussion of Echeco’s
various challenges to the application of the regulation appears under the heading “B. Preponder-
ance of the Evidence.”
” See In re Dr. Marshall C. Sasser, CWA Appeal No. 91-1, 13 (GJO, Nov. 21, 1991) (argument
that Clean Water Act § 309(g) unconstitutionally denies the right to a jury trial is beyond the jurisdic-
tion of the EPA), Petroleum Management, inc. at 4 n.5 (Administrator cannot declare a statute un-
constitutional because that authority is exclusive to the courts).
VOLUME 5
638 ENVIRONMENTAL ADMINISTRATIVE DECISIONS
escape liability on the grounds that the standards are unenforceable due
to their alleged vagueness.
B. Preponderance of the Evidence
Pursuant to 40 C.F.R. § 22.24, the presiding officer must make his
factual findings based upon a preponderance of the evidence. The
“preponderance of the evidence” is a standard of proof, and as such is
intended to “instruct the fact finder concerning the degree of confi-
dence society thinks he should have in the correctness of his factual
conclusion.” In re Winship, 397 U.S. 358, 370 (1970). In essence, the
preponderance of the evidence standard means that a fact finder should
believe that his factual conclusion is more likely than not. In re Great
Lakes Division of National Steel Corp., EPCRA Appeal No. 93-3, at 10
n. 20 (EAB, June 29, 1994) (preponderance of the evidence means that
a fact is more probably true than untrue); Jn re City of Detroit Public
Lighting Dept., et al., TSCA Appeal No. 89-5, at 8 (CJO, Feb. 6, 1991)
(the City of Detroit was not responsible for discharges that deposited
PCBs because, inter alia, “lilt is more likely than not that the uncon-
trolled discharges that contaminated the areas * * * occurred before
Detroit took possession of the property”); Koch, Administrative Law
and Practice at 491 (1985).
Here, the presiding officer concluded, after evaluating all of the
testimony and documentary evidence, that a preponderance of the
evidence indicated that Echeco failed to keep the pipe insulation ad-
equately wet while it was being stripped and until it was collected for
disposal. In finding that the pipe insulation was not kept adequately
wet in accordance with the regulations, the presiding officer relied
upon the inspector's testimony that “when she tore a piece of ‘semi-
wet’ air cell pipe insulation lying on the floor of the boiler room, she
discovered that it was very stiff and very dry and that when torn, it
emitted fibers and released dust.” Initial Decision at 28-29. The
inspector’s handling and tearing of the pipe insulation was consistent
with her training to determine violations of the adequately wet re-
quirements, as detailed above. The regulatory definition of “adequately
wet” provides that “lilf visible emissions are observed coming from
asbestos-containing material, then that material has not been adequately
wetted.” 40 C.F.R. § 61.141. Therefore, the presiding officer concluded,
“{slince the piece of air cell pipe insulation which had been stripped from
facility components and which was lying on the floor of the boiler room
emitted fibers and released dust when the EPA inspector broke it, I con-
clude that the material was not adequately wet.” Initial Decision at 29.
VOLUME 5
NORMA J. ECHEVARRIA AND FRANK J.ECHEVARRIA 639
In sum, Echeco disagrees with the factual conclusions made by
the presiding officer. The presiding officer acknowledged that the tes-
timony of the witnesses for both parties was convincing. Tr. at 697.
Despite the perceived closeness of the case, the presiding officer ulti-
mately found that a preponderance of the evidence showed that Echeco
violated the adequately wet requirements. Because the presiding of-
ficer had the opportunity to observe the witnesses testify and to evalu-
ate their credibility, his factual findings are entitled to considerable
deference here. Great Lakes Division of National Steel Corp. at 22; In
re Port of Oakland and Great Lakes Dredge and Dock Company,
MPRSA Appeal No. 91-1, at 28 n.59 (EAB, Aug. 5, 1992). While Echeco
has expressed its disagreement with the presiding officer's determina-
tions, it has not demonstrated that any of the factual findings made by the
presiding officer are not supported by a preponderance of the evidence.
Echeco makes several arguments that the presiding officer’s con-
clusion is not supported by a preponderance of the evidence. First,
Echeco contends that “an asbestos inspector’s observations are insuf-
ficient alone to establish NESHAP violations.” Appellants’ Brief at 9. We
disagree. “In cases involving alleged violations of the NESHAP for as-
bestos, courts have routinely relied on the observations of inspectors
to determine whether asbestos was adequately wetted.” MPM Contrac-
tors at 233 (emphasis added). The court’s statement in MPM Contrac-
tors is consistent with the approach the Agency has advised the regu-
lated community it will take in enforcing the adequately wet require-
ments. In an Agency guidance document entitled “Asbestos/NESHAP
Adequately Wet Guidance” (Dec. 1990), the Agency informed the regu-
lated community that “[dleterminations of whether asbestos materials
are adequately wetted are made by EPA inspectors on site.” /d. at 1.In
the same document, the Agency again stated that “[tlhe determination
of whether [asbestos-containing material] has been adequately wetted
is generally based on observations made by the inspector at the time
of the inspection.” Even a witness for Echeco testified that the “only
way to tell if something is adequately wet is to physically be there, and
*** to handle the material,” or, in other words, to inspect the material.
Tr. at 602. It is difficult to imagine how the asbestos NESHAP enforce-
ment program, or many of the other enforcement programs conducted
by the Agency, could be of any effect if an inspector’s credible obser-
vations were not probative evidence of a violation.’® When an inspec-
tor trained to determine compliance with the applicable regulations
18 See In re Celotex Corp., TSCA Appeal No. 91-3 (CJO, Dec. 16, 1991) (presence of unmarked
PCB capacitors established by an inspector's testimony describing her observations), J re Elwin G.
Smith Division, Cyclops Corp. RCRA (3008) Appeal No. 86-6 (CJO, Aug. 14, 1990) (violation found
based upon testimony of inspector; presiding officer did not abuse discretion in crediting inspector's
testimony more than respondent's).
VOLUME 5
640 ENVIRONMENTAL ADMINISTRATIVE DECISIONS
reasonably determines that a violation has occurred and provides a
rational basis for that determination, liability should follow, absent
proof that the inspector’s testimony lacks credibility.” Moreover, we
note that here, the inspector's testimony was corroborated by her in-
spection report and photographs, which were admitted into evidence.
Echeco cites no authority, and provides no basis, for its position
that an inspector’s testimony alone is insufficient to establish a viola-
tion of the work practice standards. Instead, Echeco argues that MPM
Contractors is not controlling here because in that case, and in the
cases cited therein, the facts observed by the inspector were undis-
puted. Implicit in this argument is the suggestion that the facts ob-
served by the inspector in this case are in dispute, presumably based
upon Browning’s testimony. Again, we disagree. Nothing in Browning’s
testimony contradicts or otherwise refutes the inspector’s testimony
that when broken, a piece of the insulation that had been removed
from the pipe that morning emitted fibers and dust. The facts relied
upon by the presiding officer have not been refuted, or disputed, or in
any other way shown to be wrong, by Echeco. Although Echeco’s
employees had the opportunity to observe the inspection, none availed
themselves of that opportunity, and in so doing they diminished their
ability to refute the inspector's testimony directly. Only one of Echeco’s
witnesses—Browning—was ever actually in the containment area dur-
ing the removal process, and he was the one removing the insula-
tion.” His testimony nevertheless hardly refutes the inspector’s testi-
mony, for although he attempted to wet the insulation as best as he
could, he conceded that “on every job I have ever been on I have seen
visible emissions of some type.” Tr. at 649. As the presiding officer
noted, presumably “every job” would include the job at the North Gem
School.?!
Echeco also asserts that Browning’s statement that “on every job
I have ever been on I have seen visible emissions of some type,” is not
an admission that he inadequately wetted the pipe insulation here. The
presiding officer did not label Browning’s statement an “admission.”
Instead, he concluded that the statement did not refute the inspector’s
observations. We agree. Browning stated that on every job he has seen
‘° Indeed, counsel for the respondents acknowledged that the inspector's testimony “is either
going to win or lose this case.” Tr. at 99.
Three of Echeco’s five witness were never in the containment area, One was in the area only
for a few moments, and was not there after Browning began removing the pipe insulation.
21 Steve Harrington, an expert witness who testified on behalf of Echeco, and who was never in
the containment area at the North Gem School, also testified that he had never been on an asbestos
abatement project where fibers were not released. Tr. at 595, 600.
VOLUME 5
NORMA J. ECHEVARRIA AND FRANK J.ECHEVARRIA 641
visible emissions of some type. He did not exclude this particular job.
Visible emissions from asbestos-containing material indicate that the
material is not adequately wet under the applicable regulations. 40
C.F.R. § 61.141. Thus, Browning’s testimony provides no reason for
concluding that this job is different from any other on which he has
worked. In this way, his testimony supports the conclusion that de-
spite his efforts to wet the pipe insulation as best as he could, visible
emissions nevertheless occurred. If Echeco is arguing that compliance
with the adequately wet requirements is impossible because, as Brown-
ing explained, visible emissions are present on every job, we construe
the argument as a challenge to the validity of the regulations. As pre-
viously explained, this is not the proper forum to entertain such a
challenge.
According to Echeco, in order to find a violation of the adequately
wet requirements there must be evidence that the emissions observed
by the inspector contain asbestos. Because such evidence is lacking
here, Echeco contends, a preponderance of the evidence does not
show a violation. This argument lacks merit. Under the clear language
of the applicable regulations, visible emissions from asbestos-contain-
ing material demonstrate that the material is not adequately wet. 40
C.F.R. § 61.141. The visible emissions do not have to be visible asbestos
emissions. Section 61.141 defines “visible emissions” as any emissions
from asbestos-containing material. Thus, the regulations themselves
contradict Echeco’s assertion that a violation of the adequately wet
requirements depends upon proof that the observed visible emissions
were asbestos emissions. Further, to establish a violation of the ad-
equately wet requirements, it is not essential for the Agency to prove
that emissions occurred. MPM Contractors at 233; Ben’s Truck and
Equipment, Inc. at 1299. “It is the failure to follow the work practice to
wet adequately rather than the release of visible emissions which cre-
ates liability.” Jd. Obviously, if it is not essential for the government to
prove a release of visible emissions to show a violation of the ad-
equately wet requirements, it need not prove a release of visible as-
bestos emissions.
In any event, we note that later laboratory testing of the sample
torn by the inspector revealed that the pipe insulation contained 95%
asbestos, thus making it more likely than not that the emissions ob-
served by the inspector did in fact contain asbestos.” With respect to
this laboratory test, Echeco argues that the sample of pipe insulation
torn by the inspector was wet when it was received at the laboratory,
In contrast, there is nothing in the record to support Echeco’s suggestion that the fibers
released were attributable only to the encapsulant on the insulation rather than the asbestos.
VOLUME 5
642 ENVIRONMENTAL ADMINISTRATIVE DECISIONS
and consequently the presiding officer could not conclude that Echeco
violated the adequately wet requirements. The Region, however, did
not allege that Echeco failed to wet the pipe insulation. Instead, the
Region alleged that Echeco failed to keep the pipe insulation ad-
equately wet. As noted above, adequately wet means wet enough to
prevent the release of visible emissions. Even though Echeco wetted
the pipe insulation, its efforts did not make the pipe insulation ad-
equately wet as that term is defined in the applicable regulations.
According to Echeco, there is no evidence to support the presid-
ing officer’s conclusion that the piece of insulation torn by inspector
Goehring was actually removed from the pipe by Echeco. Echeco re-
lies upon Browning’s testimony that some pipe insulation would fall
from the pipes without his effort in trying to strip that piece of insula-
tion. Echeco maintains that the requirement to keep asbestos-contain-
ing material adequately wet during removal applies only to the mate-
rial it is intentionally removing, and not to pieces that fall without any
intentional effort on its part. Because the piece of pipe insulation torn
by the inspector could have been one of the pieces that fell without
Browning’s effort, Echeco asserts that there is insufficient evidence to
find that it violated this requirement.
In essence, Browning testified that the insulation made it from the
pipes to the pile on the boiler room floor in one of two ways: by his
intentional act of removing the insulation, or by his unintentional act
of “bangling al pipe real hard” so that a piece of insulation further
away from the one he was working on would fall.” There is nothing in
the record indicating whether the torn pipe insulation that emitted
fibers was a piece removed by Browning's intentional efforts, or a
piece that fell without Browning’s intentional efforts. Such informa-
tion, however, is not necessary to establish a violation. The intent to
23 Browning’s testimony on this point provides:
Q. During your stripping activities on June 3 and June 4 did you
observe any of the pipe or boiler insulation that became dis-
lodged or fell without you actually trying to strip it from the
components?
A. Yes, sir.
Q. What kind or —
A. Pipe insulation. A lot of times like when you are at Point B
down here or something and you turn around and you don’t
see a pipe or something, you will bang that pipe rea! hard and
with the state of it all being wet and stuff like that, it will just
(indicating) fall right off the pipe.
Tr. at 654-655.
VOLUME 5
NORMA J. ECHEVARRIA AND FRANK J.ECHEVARRIA 643
remove a piece of asbestos-containing material is not an element of
the adequately wet violation because, as explained above, the asbes-
tos NESHAP requirements impose strict liability. As explained in the
proposal to promulgate § 61.145(c), the requirements of that provision
“apply to all asbestos material including materials that have been
stripped or removed. This is intended to clarify that materials that were
not stripped but may have fallen off facility components must be
treated the same as those that were stripped.” 54 Fed. Reg. 917 Jan. 10,
1989) (emphasis added). Thus, all that matters here is that Browning,
an Echeco employee, removed the insulation from the pipes found by
the inspector in the pile on the boiler room floor, and which, when
broken, released dust and emitted fibers.
Echeco also contends that because the inspector did not witness
the stripping and removal of pipe insulation, there is no evidence
showing how wet the pipe insulation was when it was stripped. Thus,
Echeco concludes that there is insufficient evidence to conclude that
it failed to keep the pipe insulation adequately wet while removing it
from the pipes.
It is true that the inspector did not observe the actual pipe insu-
lation stripping activities. There is no requirement, however, that the
inspector observe the removal activities. See Sealtite Corp. (violation
based upon inspector's observations of asbestos-containing waste
materials). If an inspector was required to observe the stripping opera-
tion, regulated entities could effectively halt any enforcement activity
by stopping work whenever an inspector appears on site. Moreover,
the requirement to keep asbestos-containing material adequately wet
until it is collected for disposal implies that the material will remain
adequately wet from the time it is removed from a facility component
until it is collected in bags for disposal. In this case, the pipe insulation
that was torn by the inspector had been removed only a few hours
before the inspection. Had it been adequately wet when removed, it is
unlikely that it would have been, as the inspector described it, “very
stiff [and] very dry’ when she examined it.
Lastly, Echeco contends that the evidence is insufficient to show
that it violated the requirement to keep the pipe insulation adequately
wet until it was collected for disposal. Echeco relies upon the part of
§ 61.145(c)(6)(i) providing that asbestos-containing material removed
from a facility component must remain adequately wet “until collected
and contained or treated in preparation for disposal in accordance
with § 61.150.” Section 61.150 prohibits visible emissions to the outside
air in the disposal of asbestos-containing waste material (asbestos-
containing material that has been removed or stripped). According to
VOLUME 5
644 ENVIRONMENTAL ADMINISTRATIVE DECISIONS
Echeco, because the pipe insulation remained in the boiler room con-
tainment area and released no visible emissions to the air outside that
containment area, Echeco complied with § 61.150 and therefore com-
plied with § 61.145(c)(6)(i).
Echeco has misread the applicable regulations. Echeco is charged
with violating § 61.145(c)(6)(i), which, unlike § 61.150, does not con-
tain any provision prohibiting releases to the outside air. Indeed, such
a requirement was deleted from § 61.145(c)(6)(i) in 1990, before
Echeco’s violations took place. Thus, in order to establish a violation
of § 61.145(c)(6)(G), the Region need not prove any emissions to the
outside air. Walsh at 664 (attempt to sidestep adequately wet require-
ments by arguing that emissions must reach outside air to show viola-
tion is rejected because “[t]he question of emission of an air pollutant
to the ambient air is not relevant. The violation of the work practice
rule violates the statute.”). In other words, compliance with the dis-
posal requirements in § 61.150 does not equate to compliance with the
removal or stripping requirements in § 61.145(c)(6)(i). The require-
ments in § 61.145(c)(6)(i) apply to asbestos-containing material that
has been stripped or removed before it is collected or contained for
disposal. 49 Fed. Reg. 13659 (Apr. 5, 1984). The requirements of §
61.150 apply to the material only after it has been collected or con-
tained for disposal. id. Here, Echeco has been charged with, and a
preponderance of the evidence demonstrates, a violation of
§ 61.145(c)(6)(i)—the failure to keep the insulation removed from the
pipes adequately wet until it is collected for disposal.
WIL. CONCLUSION
Echeco has failed to demonstrate any compelling circumstances
justifying review of its claim that the work practice standards violated
by Echeco are unconstitutionally vague and unenforceable. Moreover,
as a practical matter, its claim is effectively barred from administrative
review as a matter of right by Clean Air Act § 307(b). In addition,
Echeco has failed to demonstrate that the presiding officer’s determi-
nation that Echeco violated the requirements to keep asbestos-con-
taining material adequately wet during the removal process and until
it was collected for disposal is not supported by a preponderance of
the evidence. Accordingly, the initial decision of the presiding officer
is hereby affirmed.
24 See 55 Fed. Reg. 48419 (Nov. 20, 1990). Previously, the predecessor to § 61.145(c)(6)(i) pro-
vided that “lelach owner or operator to whom this section applies shall comply with the following
procedures to prevent emissions of particulate asbestos material to the outside air.” 49 Fed. Reg.
13662 (Apr. 5, 1984).
VOLUME 5
NORMA J. ECHEVARRIA AND FRANK J.ECHEVARRIA 645
Respondents Norma J. Echevarria and Frank J. Echevarria d/b/a
Echeco Environmental Services shall pay a civil penalty to the
United States in the sum of $9,450.00. Payment shall be made by
cashier’s or certified check payable to “Treasurer, United States of
America.” The check shall be sent to the following address within sixty
(60) days of the date of service of this decision:
EPA—Region X
Regional Hearing Clerk
P.O. Box 360903M
Pittsburgh, PA 15251
So ordered.
VOLUME 5
Get today's answer for your situation
You just read Board precedent from 1994. Ezel checks whether it still stands, including any court review since, and answers your specific situation, with citations.
Opens in Ezel Pro. Every answer cites the authority it relies on.