Dwight L. Dawson v. Fluor Federal Global Projects, Incorporated (Board decision, June 9, 2020)

Dawson v. Fluor Federal Global Projects (BRB 19-0528): en banc reconsideration denied

Decision type
Board decision
Docket
19-0528
Decided
June 9, 2020
Outcome
Procedural
Precedential status
Unpublished Board decision, not precedent
Checked against source
2026-10-14

Apply this to your situation

This order from 2020 bound only the parties to this case; it isn't precedent. Ask about your situation and see what the current statutes and regulations the Board applies and Board precedent say, with citations.

Currency note: this decision dates from 2020
The statutes and regulations the Board applies may have been amended, and later Board or court decisions may have changed the analysis since then. Treat this page as historical context, not current advice. Verify current law before relying on any specific rule mentioned here.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official BRB release. The full text is the agency's own release.
Read the official release (dol.gov)

BRB final decision. This unpublished order is not precedent. The Board denied en banc reconsideration because a majority of its permanent members did not vote to vacate or modify the earlier decision. A Board decision ordinarily becomes final 60 days after issuance unless a timely petition for judicial review or Board reconsideration is filed under 20 C.F.R. § 802.406. A party may request Board reconsideration within 30 days under 20 C.F.R. § 802.407.

Plain-English summary

Fluor Federal Global Projects and its insurer asked the Benefits Review Board to reconsider en banc an earlier decision in Dwight Dawson's Longshore Act case. Dawson opposed the request. A majority of the Board's permanent members did not vote to vacate or change the earlier decision, so the Board denied reconsideration. The short order does not state the earlier decision's outcome.

Decision snapshot

  • Authority: En banc reconsideration under 33 U.S.C. § 921(b)(5) and 20 C.F.R. § 802.407.
  • Outcome: Employer and carrier's en banc reconsideration request denied.
  • Key point: The request failed to obtain a majority vote among the Board's permanent members.

Full text (DOL BRB public release)

U.S. Department of Labor Benefits Review Board 200 Constitution Ave. NW
Washington, DC 20210-0001

BRB No. 19-0528

DWIGHT L. DAWSON
)
)
Claimant-Petitioner
)
)
v. )
)
FLUOR FEDERAL GLOBAL PROJECTS,
)
INCORPORATED
)
) DATE ISSUED: 06/09/2020
and
)
)
INSURANCE COMPANY OF THE STATE
)
OF PENNSYLVANIA, c/o AIG CLAIMS,
)
INCORPORATED
)
) ORDER on MOTION for
Employer/Carrier-
) RECONSIDERATION
Respondents
) EN BANC

Employer/Carrier has filed a timely motion for reconsideration of the Benefits Review Board’s Decision and Order in the captioned case, Dawson v. Fluor Federal Global Projects, Inc., BRB No. 19-0528 (June 9, 2020) (unpub.), suggesting the appropriateness of en banc review. 33 U.S.C. §921(b)(5); 20 C.F.R. §802.407(a), (b). Claimant responds, urging the Board to deny the motion. As a majority of the permanent members of the Board has not voted to vacate or modify the Board’s decision, Employer’s motion for reconsideration en banc is denied. 20 C.F.R. §§801.301(c), 802.407(d), 802.409.

By Order of the Board:

Thomas O. Shepherd, Jr.
Clerk of the Appellate Boards

What applies to your situation today?

This order bound one employer. Ezel checks the current statutes and regulations the Board applies and Board precedent against your facts, with citations.

Try Ezel Pro free for 7 days. Cancel anytime before the trial ends and you pay nothing.

  • Checks the law as it stands today, not only this page
  • Cites every source it relies on, so you can verify it
  • Chat, drafting and research in one workspace