United States Department of the Army, Corps of Engineers, U.S. Army Engineer Research Development Center, Vicksburg, Mississippi (Agency/Petitioner) and American Federation of Government Employees, Local 3310, AFL-CIO (Labor Organization/Incumbent Intervenor) and National Federation of Federal Employees, Federal District 1, Iamaw, AFL-CIO (Labor Organization/Incumbent Intervenor) and International Federation of Professional and Technical Engineers, Local 4, Chapter 1, AFL-CIO, Clc (Labor Organization/Incumbent Intervenor) and International Federation of Professional and Technical Engineers, Local 1017, AFL-CIO, Clc (Labor Organization/Incumbent Intervenor) (Authority decision, December 17, 2001)
Army Engineer Research Development Center and unions (FLRA AT-RP-00038, WA-RP-00080): Review granted after mail quarantine
Apply this precedent to your situation
This is citable Authority precedent from 2001, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.
FLRA representation decision. The Federal Labor Relations Authority grants review of the Regional Director's decision under 5 C.F.R. § 2422.31(c) but does not decide the underlying representation dispute. Further Authority review remains pending. This interlocutory order does not start the judicial-review period for a final order; 5 U.S.C. § 7123(a)(2) excludes appropriate-unit determinations under § 7112 from judicial review.
Plain-English summary
NFFE sought review of a regional director's decision involving the Army Engineer Research Development Center and several unions. Its timely mailed application reached the Authority weeks later because mail was quarantined at the Postal Service's Brentwood facility. The Authority obtained the agency's opposition by fax after confirming its earlier mailing. It granted review to allow adequate time to discharge its statutory responsibilities in these unprecedented circumstances. This order does not resolve the underlying representation issues.
Decision snapshot
- Authority: 5 C.F.R. § 2422.31(c).
- Outcome: Review granted; merits remain pending.
- Key point: A mail quarantine delayed receipt of the pleadings and prompted an interim grant of review.
Full text (FLRA public release)
[ v57 p655 ]
57 FLRA No. 127
UNITED STATES DEPARTMENT OF THE ARMY
CORPS OF ENGINEERS
U.S. ARMY ENGINEER RESEARCH
DEVELOPMENT CENTER
VICKSBURG, MISSISSIPPI
(Agency/Petitioner)
and
AMERICAN FEDERATION OF GOVERNMENT
EMPLOYEES, LOCAL 3310, AFL-CIO
(Labor Organization/Incumbent Intervenor)
and
NATIONAL FEDERATION OF FEDERAL
EMPLOYEES, FEDERAL DISTRICT 1
IAMAW, AFL-CIO
(Labor Organization/Incumbent Intervenor)
and
INTERNATIONAL FEDERATION OF
PROFESSIONAL AND TECHNICAL ENGINEERS
LOCAL 4, CHAPTER 1, AFL-CIO, CLC
(Labor Organization/Incumbent Intervenor)
and
INTERNATIONAL FEDERATION OF
PROFESSIONAL AND TECHNICAL ENGINEERS
LOCAL 1017, AFL-CIO, CLC
(Labor Organization/Incumbent Intervenor)
ORDER GRANTING APPLICATION FOR REVIEW
_____
AT-RP-00038
WA-RP-00080
December 17, 2001
_____
Before the Authority: Dale Cabaniss, Chairman and
Carol Waller Pope and Tony Armendariz, Members
I. Statement of the Case
This case is before the Authority on an application for review filed by the National Federation of Federal Employees, Federal District 1, IAMAW, AFL-CIO (NFFE), under § 2422.31(c) of the Authority's Regulations. The Agency filled an opposition.
Under § 2422.31(c), the Authority may grant an application for review when the application demonstrates [ v57 p656 ] that review is warranted on one or more of the following grounds: (1) the decision raises an issue for which there is an absence of precedent; (2) established law or policy warrants reconsideration; or, (3) there is a genuine issue over whether the Regional Director (RD) has: (i) failed to apply established law; (ii) committed a prejudicial procedural error; (iii) committed a clear and prejudicial error concerning a substantial factual matter. In this case, NFFE contends that established law or policy warrants reconsideration and that there is a genuine issue over whether the RD has failed to comply with established law.
The application for review was filed by NFFE on October 26, 2001, but was not received by the Authority until December 11, 2001. After receiving the application, the Authority contacted the remaining parties and requested that they resubmit, by fax, any pleadings they had filed by mail. The Agency's opposition, along with evidence that it was filed by mail on November 9, 2001, were received by the Authority by fax on December 12, 2001. The delay in delivery was due to the quarantine of the mail in the U.S. Postal Service's Brentwood facility in Washington, D.C., which services the Authority's headquarters. In this unprecedented situation, the Authority is granting the application for review to provide the Authority adequate time to discharge its obligations under the Federal Service Labor-Management Relations Statute.
II. Order
The application for review of the RD's Decision and Order is granted.
Does this precedent still control your case?
Ezel checks whether it still stands, including any court review since, and applies it to your situation with citations.
Try Ezel Pro free for 7 days. Cancel anytime before the trial ends and you pay nothing.
- Checks the law as it stands today, not only this page
- Cites every source it relies on, so you can verify it
- Chat, drafting and research in one workspace