OSHRC Commission decision Docket 99-0686 Decided October 20, 2000 Settled

G. Porter and Company

Commission approves a settlement and sets aside the ALJ scaffold decision to the extent inconsistent

Apply this precedent to your situation

This is citable Commission precedent from 2000, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.

Currency note: this decision dates from 2000
The OSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Decision of the Commission
This is a decision of the Occupational Safety and Health Review Commission, the highest level of agency review, citable as Commission precedent. It may have been appealed to a U.S. Court of Appeals after issuance; check subsequent history before relying on it. The full text below is from the official OSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official OSHRC release. The full text is the Commission's own document.
Read the official release (oshrc.gov)

Plain-English summary

G. Porter and Company is a masonry subcontractor. OSHA inspected a Chicago-area construction site in February 1999 and cited Porter for a serious scaffolding violation: employees were working on a scaffold that lacked the required guardrails, exposing them to falls of roughly 18 to 20 feet. After an E-Z Trial hearing, Chief Judge Irving Sommer affirmed the citation and assessed the proposed $1,500 penalty, rejecting the company's argument that the scaffold was being dismantled and that the workers were not exposed to the unguarded edges. A Commissioner then directed the case for review. While the case was before the full Commission, the parties filed a Stipulation and Settlement Agreement. The Commission reviewed the record, found no issues warranting further review, approved the settlement, incorporated its terms into the order, and set aside the ALJ's decision to the extent it was inconsistent with the settlement. This is the final order of the Commission. The appended ALJ decision is reproduced in full below.

Decision snapshot

  • Cited standard(s): 29 C.F.R. § 1926.451(g)(4)(i) (scaffold guardrail systems on open sides and ends of platforms)
  • Outcome: Settled. The Commission approved the parties' Stipulation and Settlement Agreement, incorporated its terms, and set aside the ALJ's decision to the extent inconsistent with the settlement.
  • Key point: When parties settle after a case is directed for Commission review, the Commission may approve the settlement and set aside the underlying ALJ decision to the extent it conflicts with the agreed terms.

Full text (OSHRC public release)

```
SECRETARY OF LABOR,

            Complainant,

            v.

G. PORTER AND COMPANY,

            Respondent.

OSHRC Docket No. 99-0686
ORDER

     This matter is before the Commission on a Direction for Review entered by

Commissioner Gary L. Visscher on March 31, 2000. The parties have now filed a Stipulation and
Settlement Agreement.
Having reviewed the record, and based upon the representations appearing in the
Stipulation and Settlement Agreement, we conclude that this case raises no matters warranting
further review by the Commission. Accordingly, the Stipulation and Settlement Agreement is
approved.
We incorporate the terms of the Stipulation and Settlement Agreement into this Order and
we set aside the Administrative Law Judge’s Decision and Order to the extent that it is inconsistent
with the Stipulation and Settlement Agreement. This is the final order of the Commission.
Date: October 20, 2000
/Signed/

                                                Thomasina V. Rogers
                                                Chairman

                                                /Signed/

                                                Gary L. Visscher
                                                Commissioner

                                                /Signed/

                                                Stuart E. Weisberg
                                                Commissioner

                                                                      2001 OSHRC No. 37

United States of America
OCCUPATIONAL SAFETY AND HEALTH REVIEW COMMISSION
1120 20th Street, N.W., Ninth Floor
Washington, DC 20036-3419

SECRETARY OF LABOR,

             Complainant,

     v.

G. PORTER & COMPANY,

             Respondent.

OSHRC DOCKET NO. 99-0686

Appearances:

Helen J. Schuitmaker, Esquire
Chicago, Illinois
For the Complainant.

Peter Cucuz
St. Charles, Illinois
For the Respondent.

Before: Chief Judge Irving Sommer

                                   DECISION AND ORDER

     This is a proceeding pursuant to section 10(c) of the Occupational Safety and Health Act of 1970,

29 U.S.C. § 651 et seq. (“the Act”) to review a citation and notification of penalty issued by the Secretary
of Labor (“the Secretary”) pursuant to section 10(a) of the Act.
On February 4, 1999, the Occupational Safety and Health Administration (“OSHA”) conducted
an inspection of a construction site where employees of Respondent, G. Porter & Company (“Porter”),
were engaged in masonry work. As a result of the inspection, OSHA issued Porter a serious citation
alleging a violation of 29 C.F.R. § 1926.451(g)(4)(i). Respondent timely contested the citation, the case
was designated for E-Z Trial pursuant to Commission Rule 203, and the hearing in this matter was held
in Chicago, Illinois, on December 14, 1999. Neither of the parties has submitted a post-hearing brief.
The OSHA Inspection
Anthony Smith, the OSHA compliance officer (“CO”) who conducted the inspection, testified that
he went to the site pursuant to a complaint that employees were working on an unsafe scaffold. When
he arrived, he saw a building under construction with scaffolding along the south and east sides. The
scaffolding on the south side was three tiers high, four employees were working on top of the second
tier, and while the scaffolding had both front and back cross bracing it did not have guardrails as
required to prevent falls off the ends and front; the scaffolding also had clear plastic tarp over part
of it, but the section where the employees were working was not covered. The CO drew R-1, a
sketch of the building, and then met with Tim Glen, the general contractor’s superintendent, who told
him the scaffolding was that of Porter, the masonry subcontractor; the CO next met with James
Reitmayer, Porter’s foreman, and he went inside the building with Glen and Reitmayer, who, after
observing the scaffolding from a second floor window, agreed with the CO and told him they would
put up guardrails.1 CO Smith stated that the employees had been exposed to falls of 18 to 20 feet,
which could have caused serious injury or death. (Tr. 5-24).
Discussion
The cited standard provides as follows:
Guardrail systems shall be installed along all open sides and ends of platforms.
Guardrail systems shall be installed before the scaffold is released for use by
employees other than erection/dismantling crews.
The Secretary’s evidence, as set out above, establishes a prima facie violation of the cited
standard. In defense of this item, Porter presented the testimony of James Reitmayer, its job site
foreman, and Thomas Gradowski, the sub-foreman at the site. Taken together, their testimony was
that Porter’s safety policy was to put up guardrails before employees got up on scaffolding and to
remove them only during dismantling or when materials were placed on or taken off the scaffolding
platform; their further testimony was that the masons were just completing their brick work in the
cited area when the CO was there, that Gradowski was touching up the finished brick work, and that
cleanup and dismantling work was also taking place. Reitmayer identified C-1-2 as photos he took
on February 5, 1999, showing the scaffolding and Porter’s loading equipment, and he stated that the
two employees in C-2 were located where the CO had seen the employees the day before and that
the section to the right of the employees in C-2 was the “loading port.” He also stated, as did
Gradowski, that the two employees in C-2 were dismantling the scaffolding, as evidenced by the

   1
    The CO tried to video his observations but, due to the very cold weather that day, his

video equipment would not operate. (Tr. 16).
stacked planks to their left and by the fact that the plastic had been removed.2 Reitmayer and
Gradowski said that the only unguarded area on the scaffolding had been the loading port shown in
C-2, that that guardrail had been taken down so material could be removed during dismantling, and
that neither Gradowski nor the other masons had been exposed to a fall hazard because they worked
next to the building and the scaffolding platform was 7.5-feet deep. (Tr. 33-87).
Based on the record, Porter has failed to rebut the Secretary’s evidence. First, although
Reitmayer and Gradowski indicated that only the “loading port” was unguarded, the CO indicated
that none of the scaffolding in the area in which he saw employees working had guardrails, including
the ends. (Tr. 7-9; 31; 41; 49-52; 59; 77-78; 82-83). Second, the CO said the scaffolding was not
being dismantled when he saw it, and while Reitmayer said the scaffolding was “history” an hour after
the CO left, he and Gradowski described C-2, which was taken the next day, as showing the
dismantling of that same scaffolding.3 (Tr. 9; 52-59; 86-87). Third, Reitmayer’s testimony that he
agreed with the CO at the time of the inspection because he did not know until later that the wall was
finished was not persuasive, since he could simply have gone outside to look at the wall. (Tr. 63-67).
In view of the evidence as a whole, the testimony of Reitmayer and Gradowski is not credited to the
extent it conflicts with that of CO Smith. I find as fact that employees were performing masonry
duties at the time of the inspection and that the scaffolding did not have guardrails as required.
I also find that employees were exposed to the cited hazard. Reitmayer and Gradowski
testified that the masons worked near the wall and not near the sides of the scaffolding platform,
where bricks and other work materials were placed. (Tr. 38-40; 67-70; 79-82). However, it is clear
that the masons would have been exposed to the unguarded sides of the scaffolding, both to get
materials during bricklaying and to place leftover materials near the sides so they could be removed
prior to dismantling. (Tr. 39-40; 80-82). Further, Gradowski testified that he was working near one
of the ends of the scaffolding, which, as the CO indicated, were also unguarded. (Tr. 7-9; 31; 79).
Finally, I have considered and rejected Porter’s suggestion that the cross bracing and plastic tarp
served as fall protection. (Tr. 21; 63-64). As noted above, Reitmayer agreed at the time of the
inspection that guardrails should have been up, and the CO testified that due to the height of the cross

   2
    Reitmayer testified that the plastic served to protect the masonry from the cold. (Tr. 42).
   3
    C-2 clearly shows that the subject scaffolding was still intact, although some planking and

cross bracing had been removed.
bracing and the size of the openings on the scaffolding, employees were exposed to falls from the
sides; the CO also testified that there was no plastic over the specific area where he saw the
employees working and that the plastic in any case would not have afforded fall protection. (Tr. 9-11;
17; 23-24; 29-33). This citation item is affirmed as a serious violation.
The Secretary has proposed a penalty of $1,500.00, which, as the CO indicated, took into
account the gravity of the violation as well as the company’s size, history and good faith. (Tr. 12-13).
I conclude that the proposed penalty is appropriate, and it is accordingly assessed.
Conclusions of Law
1. Respondent, G. Porter & Company, is engaged in a business affecting commerce and has
employees within the meaning of section 3(5) of the Act. The Commission has jurisdiction of the
parties and of the subject matter of the proceeding.
2. Respondent was in serious violation of 29 C.F.R. 1926.451(g)(4)(i).
Order
On the basis of the foregoing Findings of Fact and Conclusions of Law, it is ordered that:
1. Item of Citation 1 is AFFIRMED, and a penalty of $1,500.00 is assessed.

                                                      /s/


                                                      Irving Sommer
                                                      Chief Judge

Date: 28 FEB 2000
```

Get today's answer for your situation

You just read Commission precedent from 2000. Ezel checks whether it still stands, including any court review since, and answers your specific situation, with citations.

Opens in Ezel Pro. Every answer cites the authority it relies on.