OSHRC ALJ decision Docket 98-0098 Decided May 26, 1999 Mixed result Judge Robert A. Yetman

Bast Hatfield, Inc.

Scaffold and ladder items affirmed

Apply this to your situation

This order from 1999 bound only the parties to this case; it isn't precedent. Ezel answers your situation under the current OSHA standards and Commission precedent, with citations.

Currency note: this decision dates from 1999
The OSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Final order, not Commission precedent
This decision by an OSHRC Administrative Law Judge became a final order of the Commission because no Commissioner directed review (29 U.S.C. § 661(j)). It binds the parties but is not binding precedent in other cases. The full text below is from the official OSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official OSHRC release. The full text is the Commission's own document.
Read the official release (oshrc.gov)

Plain-English summary

Bast Hatfield employees performed masonry work from scaffolds at a church construction project in New York. Judge Robert A. Yetman denied Bast's Fourth Amendment challenge because the OSHA inspector observed the work from a parking area that remained open to church visitors and the public. He vacated the silica-training item because the employee's hearing testimony and training records showed that Bast had informed him about silica hazards. Multiple scaffold and ladder items were affirmed because the competent person created or knew of the conditions, and Bast did not prove that it effectively communicated and enforced its scaffold rules. The repeated fall-protection item was also affirmed based on prior final citations for substantially similar violations. A compressed-gas-cylinder item was vacated because the cylinders were still available for intermittent use rather than in storage, and total penalties of $11,200 were assessed.

Decision snapshot

  • Cited standard(s): 29 C.F.R. § 1910.1200(h)(2)(ii); 29 C.F.R. § 1926.451(b)(1); 29 C.F.R. § 1926.452(c)(2); 29 C.F.R. § 1926.1053(b)(1); 29 C.F.R. § 1926.451(b)(4); 29 C.F.R. § 1926.451(b)(5)(i); 29 C.F.R. § 1926.451(e)(1); 29 C.F.R. § 1926.451(g)(1); 29 C.F.R. § 1926.350(j).
  • Outcome: Silica-training and cylinder-storage items vacated; scaffold, access, ladder, and repeated fall-protection items affirmed for $11,200 total.
  • Key point: A designated scaffold competent person's knowledge is attributable to the employer, and a written safety program does not establish employee misconduct without proof that relevant rules were communicated and enforced.

Full text (OSHRC public release)

                           United States of America

OCCUPATIONAL SAFETY AND HEALTH REVIEW COMMISSION
1244 North Speed Boulevard, Room 250
Denver, Colorado 80204-3582

Phone: (303) 844-3409 Fax: (303) 844-3759

SECRETARY OF LABOR,
Complainant,

                             v.                            OSHRC DOCKET NO. 98-0098

BAST HATFIELD, INC.,
Respondent.

APPEARANCES:

      For the Complainant:
               Esther D. Curtwright, Esq., Office of the Solicitor, U.S. Department of Labor, New York, New York

      For the Respondent:
               Harold D. Gordon, Esq., Gordon, Siegel, Mastro, Mullaney, Gordon & Galvin, Schenectady, New York

Before: Administrative Law Judge: Robert A. Yetman

                                           DECISION AND ORDER

      This proceeding arises under the Occupational Safety and Health Act of 1970 (29 U.S.C.

Section 651 et seq.; hereafter called the “Act”). Respondent, Bast Hatfield, Inc. (Bast), at all times
relevant to this action maintained a place of business at 73 Midline Road, Ballston Lake, New York,
where it was engaged in construction. Respondent admits it is an employer engaged in a business
affecting commerce and is subject to the requirements of the Act (Tr. 17, 18)..
On September 9, 1997 the Occupational Safety and Health Administration (OSHA) conducted
an inspection of Bast’s Ballston Lake work site. As a result of that inspection, Bast was issued
citations alleging violations of the Act together with proposed penalties. By filing a timely notice of
contest Bast brought this proceeding before the Occupational Safety and Health Review Commission
(Commission). On September 16-18, 1998, a hearing was held in Albany, New York. The parties
have submitted briefs on the issues and this matter is ready for disposition.
Fourth Amendment
As a threshold matter Bast maintains that the September 9, 1997 inspection was conducted
without a warrant, in violation of its right to be free from unreasonable searches and seizures, and asks
that the evidence obtained during that inspection be suppressed. For the reasons set forth below, I find
that Bast had no reasonable expectation of privacy in its worksite. Accordingly, Bast’s motion to
suppress is denied.
The construction site which is the subject of the above captioned action is an addition to an
existing church, Our Lady of Grace (Tr. 404). The church is located in an area heavily wooded to the
rear and to the north and a housing development is located to the south of the church property (Tr. 411,
Exh. R-3). A parking lot accessing the rear of the church, where Respondent was engaged in
construction, was accessible by way of a drive leading from the roadway in front of the church (Tr.
Exh. R-3). Daniel House, Bast’s project manager, testified that unauthorized personnel on the site
could be injured, subjecting Bast to liability; therefore, access to its construction area was restricted
(Tr. 534). A sign, stating: VISITORS MUST REGISTER AT THE JOB TRAILER. THIS IS A
HARD HAT AREA, was posted next to Bast’s job trailer (Tr. 413, 527). The trailer was located at the
side of the driveway leading to the rear parking lot. The church, however, remained in operation
during construction (Tr. 530-31) and parishioners attended weekend services. Mark Salisbury, the
superintendent on site, testified that it was not unusual for people to park in the parking lot (Tr. 470,
478). Moreover, there is no evidence that parishioners or other church visitors were required to report
to Respondent’s trailer prior to attending church services or conducting other business with the church.
On September 9, 1998, OSHA Compliance Officer (CO), Paul Wigger, arrived at the Our Lady
of Grace Church, drove to the rear of the building and parked (Tr. 206). Wigger then took a series of
pictures of a Bast employee standing on a scaffold platform (Tr. 206). Wigger testified that he drove
past Bast’s job trailer to reach the parking lot, but that he did not see a sign (Tr. 353). The parking lot
was not blocked off and, according to Wigger, there were two or three other cars in the parking lot (Tr.
355). When Wigger spoke to Salisbury and House, neither expressed surprise by his presence on the
site and neither asked Wigger to secure a warrant (Tr. 315, 457, 479, 521-22).
It is well settled that the Fourth Amendment’s protection against unreasonable searches must be
premised on a reasonable expectation of privacy. L.R.. Willson & Sons v. OSHRC (Willson), 134 F.3d
1235 (4th Cir. 1998). In Willson, the Court noted that “a person has no ‘reasonable expectation of
privacy’ when he leaves conditions permitting a curious passerby to invade his ‘private space’.” The
Court cited, with approval, a prior Commission case in which the Commission found that “there is no

                                                  2

constitutional violation when an inspector makes observations from areas on commercial premises that
are out of doors and not closed off to the public. . ..” See, Concrete Constr. Co., 15 BNA OSHC 1614,
1992 CCH OSHD ¶29,681 (No. 89-2019, 1992). See also, GEM Industrial, Inc., 17 BNA OSHC 1184
(1995), cited by Bast in its closing brief.
It is clear that Bast had no reasonable expectation of privacy at a construction site located on
church property when the church remained open to parishioners during construction. Though Bast
attempted to restrict access to actual work areas out of concern for liability in the event of a mishap,1 it
made no effort to actually prevent the public from using the Our Lady of Grace drive or parking lot.
Indeed, visitors to the worksite frequently parked in the areas where the compliance officer parked
before reporting to the worksite trailer (Tr. 469). Bast’s signage, indicating that the construction site
was a hard hat area, was neither intended, nor could it reasonably have been understood to exclude use
of the parking lot. Moreover, there is no evidence that the church had authorized Respondent to restrict
access to the parking area. Since the evidence establishes that it was not unusual for the parking lot to
be used by the public, as it was by CO Wigger, without objection from anyone at Bast, the motion to
suppress is denied.
Alleged Violation of §1910.1200(h)(2)(ii)
Serious citation 1, item 1
The citation alleges:
29 CFR 1910.1200(h)(2)(ii): Employee training did not include the physical and health hazards of the
chemicals in the work area: (Construction Reference: 1926.59).2

    (a) West side of the Vestibule, an employee dry cutting concrete block was not aware of the
    health hazards associated with silica.

Facts
On September 9, 1997 CO Wigger observed and photographed Ron Kaneg, a Bast employee
standing on a scaffold platform 13 feet above the ground [scaffold No. 1], cutting concrete block with a
masonry saw without wearing a respirator, (Tr. 28, 206; Exh. C-3, C-4, C-5). Wigger testified that
Kaneg was exposed to a cloud of silica dust while cutting the blocks (Tr. 217). When he asked Kaneg

        1
           In Willson, supra., the Court found no legitimate expectation of privacy where the employer had made no

efforts to protect its construction site from observation from vantages outside its control; in that case the roof of a
nearby hotel. In this case, Bast made no efforts to screen its activities from the housing development to the south.
2
The cited standard §1910.1200(h)(2)(ii) provides:
Information. Employees shall be informed of. . . . (ii) Any operations in their work area where
hazardous chemicals are present; (emphasis supplied).

                                                         3

if he was aware of the health hazards associated with silica (Tr. 209), the employee responded “no”
(Tr. 210). Wigger then asked Kaneg if he knew that silica could be as dangerous as asbestos; Kaneg
again said no (Tr. 211). Wigger testified that Bast supplied him with training documents signed by
Ron Kaneg, indicating that he had received training in hazard communication; however, the
compliance officer was not sure whether that training included information specific to silica (Tr. 321-
24).
Employee Kaneg testified that he had been instructed to cut cement block only in properly
ventilated areas, to use water to wet down the block and to use a respirator when cutting (Tr. 61).
Although Kaneg was wearing a bandana around his face at the time of the inspection because his
respirator had become clogged with dust, (Tr. 40-41) he admitted that he had been warned that silica
can cause silicosis and had seen the safety sheet on silica (Tr. 62). The employee also testified that
when he was first hired by Respondent he was shown a film which included information relating to
chemicals to be found in the work area, including silica dust, and he attended a weekly safety meeting
on silica (Tr. 73-74). Moreover, Kaneg identified his signature on a weekly safety meeting sign in
sheet dealing with silica dated April 4, 1997 (Tr. 75; Exh. R-1). Kaneg also testified, without
contradiction, that he was instructed by Respondent about the hazardous chemicals to be found in his
work area, including silica dust, a by-product of concrete cutting and sawing. Complainant, however,
argues that the evidence shows that Kaneg was, nonetheless, inadequately trained as to the hazards
posed by silica exposure, pointing to gaps in his knowledge, and his failure to use adequate respiratory
protection.
It is undisputed by Respondent that silica dust created by cutting concrete blocks presents
hazards to employees exposed to that substance (See Exh. C-8 and C-9) (Respondent’s brief pg. 33).
However, Respondent vigorously argues that all of its employees, including the exposed employee
herein, Ronald Kaneg, received mandatory safety training which included the hazards of silica dust via
video tape and weekly safety meetings. Specifically, Respondent points to exhibits R-1, a sign-in sheet
for a weekly safety meeting dated April 4, 1997 at which time hazards of silica dust were discussed.
Employee Ronald Kaneg signed the sheet to verify his attendance (See also Exh. R-5). Moreover, the
material safety data sheet setting forth hazards of silica dust was maintained in Respondent’s trailer at
the jobsite. Finally, employee Kaneg testified that he received training in the hazards of silica dust by
video tape and weekly safety meetings (Tr. 75-76) and was aware that the medical safety data sheet for
silica dust was located in the job trailer Tr. 77).

                                                  4

The evidence offered by the Secretary in support of this alleged violation are the statements
made by employee Kaneg at the jobsite to the compliance officer that he (Kaneg) was not aware of the
hazards of silica dust and he was not aware that silica dust is as hazardous as asbestos. Kaneg
contradicted these responses at the hearing and testified that Respondent had informed him of silica
dust hazards. Thus, the statements made by Mr. Kaneg as related by the compliance officer, which
constitute the only support for the alleged violation, are refuted by the person making the statement.
Under these circumstances the statements made by Kaneg and his testimony at the trial are worthy of
little, if any, weight.
To establish a violation, the Secretary must convince the trier of fact by a preponderance of the
evidence that the violative event or conduct occurred. The Commission has defined this burden as
“that quantum of evidence which is sufficient to convince the trier of fact that the facts asserted by a
proponent are more probably true than false” Ultimate Distrib. Systems, Inc. 10 OSHD 1569, 1570
(1982). Based upon this record, there is no creditable evidence in support of the alleged violation. The
conclusion reached by the compliance officer based upon an employee’s statement has been
undermined by the same employee at the hearing. Moreover, the sign-in sheet indicating that the
employee attended a safety meeting concerning the hazards of silica dust supports the conclusion that
the Respondent did inform its employees of the hazards associated with silica dust. Thus, this item
must be vacated because of a failure of proof.
Citation 1 Item 2

29 CFR 1926.451(b)(1): Each platform on all working levels of scaffolds were not fully planked or
decked between the front uprights and the guardrail supports:

  (a)        West side of the Vestibule, an employee was cutting concrete block while standing on a
             scaffold platform 13' above the ground that measured approx. 28" wide. The scaffold
             frame measured 60" wide, and 14' long.

Citation 1 Item 3

29 CFR 1926.452(c)(2): Frames and panels were not braced by cross, horizontal, or diagonal braces, or
combination thereof, which secure vertical members together laterally:

    (a)      East and west side of the Vestibule west wall, two separate scaffold systems, each of
             which had two missing cross braces.




                                                 5

Citation 1 Item 5a

29 CFR 1926.451(b)(4): Scaffold planks that were not cleated, were not extended over their end
supports at least 6 inches:

   (a)          East side of the west Vestibule wall, planking did not extend 6" over the end supports.

Citation 1 Item 5b

29 CFR 1926.51(b)(5)(i): Platforms less than 10 feet were extended greater than 12 inches over their
end supports where they were not so designed and installed so that the cantilevered portion of the
platform is able to support employees and for materials without tipping, or has guardrails which block
employee access to the cantilevered end:

(a) East side of the west Vestibule wall, planking that extended greater than l2" over the end
supports.

Citation 2 Item 13

29 CFR 1926.451(e)(1): Employees working on scaffold platforms more than 2 feet above or below a
point of access were not provided with portable ladders, hook-on ladders, attachable ladders, stair
towers, stairway-type ladders, ramps, walkways, integral prefabricated scaffold access, or direct access
from another scaffold, or personnel hoist:

   (a)          East side of the west wall in the Vestibule, an employee climbed the scaffold frame to
                gain access and egress to a platform 13’ above a concrete floor.

Citation 2 Item 2 (Repeat)

CFR 1926.451(g)(1): Each employee on a scaffold more than 10 feet (3.1m) above a lower level was
not protected from falling to that lower level by either a guardrail system or a personal fall arrest
system:

   (a)          West side of the Vestibule, an employee was cutting concrete block while standing on a
                scaffold platform 13’ above the ground without any fall protection.

The Bast Hatfield Inc. was previously cited for a violation of this Occupational Safety and Health
Standard or in equivalent standard, 1926.451(d)(10), which was contained in OSHA Inspection
Number 122248990, Citation Number 1, Item Number 2, issued on 5/19/95, also Bast Hatfield Inc. was
cited for violation of this Occupational Safety and Health Standard or its equivalent standard,
1926.451(y)(11) which was contained in OSHA Inspection Number 122245798, Citation Number 1,
Item Number 4, issued on 3/9/95.

         3
             Complainant’s motion to amend this item to a "serious" violation was granted.

                                                          6

The facts underlying the aforesaid violations are not disputed by Respondent. Thus,
Respondent agrees that the violative conditions observed by the compliance officer as described above
existed at Respondent’s worksite, (Respondent’s brief p. 13). Upon his arrival at the worksite, the
compliance officer parked his vehicle facing the work area and observed three scaffolds being used by
Respondent’s employees. These scaffolds were designated as scaffolds 1, 2 and 3 at the hearing.
According to the compliance officer, the scaffolds were approximately 13 feet high (Tr. 206) and were
composed of two six-foot sections (Tr. 215). The compliance officer observed employee Ronald
Kaneg standing at the 13 foot level of scaffold 1 without full planking (Citation 1, item 2). With
respect to Citation 1, item 3, the compliance officer observed missing cross braces on scaffolds 1 and

  1. With respect to Citation 1, items 5(a) and 5(b), the compliance officer measured the 5 or 6 planks at
    the top level of scaffold No. 2 and found one plank extended less than six inches over its support (Tr.
    248-49) and another plank extended 2 feet six inches over its end support (Tr. 214, 247-49). The
    compliance officer also testified that the scaffold did not have guard rails which would have prevented
    an employee from stepping on the cantilevered portion of the plank (Tr. 250) (Citation 2, item 2).
    Moreover, employee Kaneg conceded that the aforesaid planks were not guarded or cleated to keep
    them from sliding back and forth on the scaffold frame (Tr. 67-68, 103). Finally, the compliance
    officer observed that the scaffold upon which employee Kaneg was working did not have an access
    ladder (Tr. 254) (Citation 2, item 1).
    After talking with employees Kaneg and Bourdeau, compliance officer Wigger went to the
    construction trailer and introduced himself to superintendent Salisbury. Mr. Salisbury was the job
    supervisor and Mr. Bourdeau was designated as a labor foreman and the competent person for purposes
    of scaffold erection (Tr. 31, 214, 230, 231, 405). It appears, however, for this job, Mr. Bourdeau had
    no supervisory authority and Mr. Kaneg was designated as “lead man” (Tr. 431-435, 475) without
    supervisory authority (Tr. 433). Mr. Salisbury telephoned Respondent’s safety coordinator, Daniel
    House, to come to the jobsite. Upon Mr. House’s arrival, compliance officer Wigger walked him
    through the jobsite. Mr. House testified as follows:
    When I was called to the site that morning, and [10] when I had my meeting with Mr.
    Wigger, and he brought me around and, and showed me what violations had occurred, I was, I
    was outraged, and I couldn’t believe that I had seen and I, and I couldn’t, for the life of me,
    understand how this could possibly happen (Tr. 519).

    Based upon this record, there is sufficient evidence to support the conclusion that the violative
    conditions alleged above existed at Respondent’s worksite.

                                                7
    

    As its defense to the aforesaid violations, Respondent asserts that the Secretary failed to
    establish that it (Respondent) knew or with the exercise of reasonable diligence, could have known of
    the violation. Closely related to the employee knowledge issue, Respondent argues as a second defense
    that the violations were the result of unpredictable and unpreventable employee misconduct. In
    essence, Respondent argues that it was “unrealistic” to provide on site supervision for the work being
    performed because the employees were experienced and well qualified; therefore, the violations could
    not be anticipated nor prevented.
    In order to establish that Respondent failed to comply with the aforesaid standards, the
    Secretary must prove that (1) the standards apply (2) the employer failed to comply with the terms of
    the standards (3) employees had access to the cited conditions and (4) the Respondent knew, or with
    the exercise of reasonable diligence, could have known of the violative conditions, Astra
    Pharmaceutical Products, Inc. 1981 CCH OSHC ¶25,578, aff’d 681 F.2d 69 (1st Cir 1982); Secretary
    of Labor v. Gary Concrete Products, 15 BNA OSHC 1051, 1052, 1991 OSHD ¶29,344 (1991) Carlisle
    Equip. Co., v. Secretary of Labor 24 F.3d 790 (1994). Respondent acknowledges that the Secretary has
    met her burden for the first three elements (Respondent’s brief pg. 25). Respondent insists, however,
    as stated above, that Complainant failed to establish that it knew, or with the exercise of reasonable
    diligence, could have known of the violative conditions. Respondent argues that the violations
    occurred “over a short period of time through the renegade actions of principally one employee” ibid.
    The record reveals that four of Respondent’s employees were at the jobsite at the time
    compliance officer Wigger arrived to conduct his inspection. After reviewing the work to be
    performed that day with the work crew, Superintendent Mark Salisbury walked across the parking lot
    to the job trailer. Once inside the trailer, Salisbury could not see the work activities of the other
    employees, Lynn Bourdeau, Ronald Kaneg and Roger Caldwell. Although Mr. Bourdeau had been
    designated as a laborer foreman with supervisory authority at other jobsites; Respondent asserts that he
    had no supervisory authority at this site. Ronald Kaneg was performing as a mason and had been
    designated as "lead man" on the day of the inspection. However, Kaneg had no supervisory authority.
    Ronald Caldwell likewise was a laborer with no supervisory authority. Thus, the only person at the
    site having supervisory authority was Mark Salisbury.
    Mr. Kaneg was assigned the task of completing the erection of a concrete block wall. He
    performed this task from while standing on a scaffold (scaffold 2) which had been placed at the interior
    of the enclosure being constructed. Another scaffold had been placed at another location in the
    inclosure (scaffold 3) and employee Caldwell was working from that scaffold. Upon completion of the

                                                 8
    

    wall, Mr. Kaneg went to the job trailer to receive further instructions from superintendent Salisbury.
    Salisbury told Kaneg to cut a "rake" at the top of the wall; that is, to cut the concrete blocks at an angle
    to receive the roof supports. In order to accomplish this task, it was necessary to cut the concrete
    blocks with a power saw on both sides of the wall. Kaneg could cut one side of the block while
    standing on scaffold 2; however, it was necessary to construct another scaffold to cut the blocks on the
    opposite side. Kaneg asked Lynn Bourdeau, who had been designated ass the competent man for
    scaffold erections, to erect a scaffold on the other side of the wall opposite scaffold 2. Bourdeau had
    partially completed the scaffold when he left the jobsite to obtain coffee for the work crew. CO
    Wigger arrived at the site in his automobile in time to observe Kaneg cross over the wall from scaffold
    2 to scaffold 1 and continue cutting the masonry. Bourdeau returned with the coffee and Wigger
    discussed the violations observed with the crew.
    On these facts Respondent argues that Complainant has failed to carry its burden of proof that
    Respondent knew, or with the exercise of reasonable diligence, could have known of the violations.
    First, Respondent notes that it is not necessary to have one on one supervision at a construction site.
    Respondent cites Brennan v. OSHRC 502 F.2d 946, 949 (3rd cir. 1974) for the proposition that
    "[w]hile close supervision may be required in some cases to avoid accidents, it is unrealistic to expect
    an experienced and well-qualified [worker] to be under constant scrutiny," see also Secretary of Labor
    v. St. Orge Logging and B&B Lumber Co. 7 OSHC BNA 1169. 1170 (1970). Respondent argues that it
    was perfectly proper for superintendent Salisbury to instruct his highly trained and experienced work
    crew at the beginning of the day and leave the worksite confident that the work assignments would be
    accomplished in a safe manner. Furthermore, since none of the employees engaged at the worksite
    were designated as supervisors by Respondent, the knowledge possessed by those employees regarding
    unsafe conditions at the site cannot be imputed to Respondent.
    In order to prevail with this theory, Respondent must establish that the non-supervised
    employees were well trained and qualified to perform their work without supervision. Thus,
    Respondent must establish that its safety training program was sufficient for that purpose. See New
    York State Electric and Gas Corporation v. Secretary of Labor 1995-1997 CCH OSHD 31,099 (1996).
    In the aforesaid matter, the court of appeals for the Second Circuit, the circuit in which this matter
    arose, discussed in detail the burden placed upon the Secretary to establish employer knowledge of the
    violative conditions even where Respondent, as in this case, raises employee misconduct as an
    affirmative defense. That affirmative defense places the employer’s safety program in issue and the
    respondent bears the burden of establishing the adequacy of its safety program. The complexities of

                                                 9
    

    this shifting burden are described in minute detail by the court in New York State, supra, and the
    principles enunciated therein must be applied here if it is established that Respondent’s employees
    were unsupervised at the time the violations were observed by the compliance officer.
    The record in this matter contains conflicting evidence regarding the roles performed and the
    authority exercised, if any, by the various actors involved herein. It is clear that titles have little
    meaning to Respondent. Thus, foreman (Bourdeau) and lead man (Kaneg), in Respondent’s view, do
    not connote the typical authority and supervisory role usually associated with those terms. The
    testimony of the employees involved is contradictory on this point and, based upon the demeanor of
    the witnesses, Bourdeau and Kaneg, is entitled to little, if any, weight. Thus, it cannot be established
    on this record whether Respondent intended any employee, other than Mark Salisbury, to be vested
    with supervisory authority at the worksite.
    The ramifications of the aforesaid conclusions may be avoided, however, by the fact that
    employee Bourdeau was the designated "competent person" on site for purposes of scaffold erection
    (Tr. 213, 405). Even if Bourdeau was specifically told that he had no supervisory authority, his status
    as a competent person for scaffold erection required that he possess a certain level of expertise in
    scaffold erection and the identification of existing and predictable hazards. The term competent person
    for purposes of scaffold erection is defined as 29 C.F.R. 1926.450(b) as follows:
    Competent person means one who is capable of identifying existing and predictable
    hazards in the surroundings or working conditions which are unsanitary, hazardous, or
    dangerous to employees, and who has authorization to take prompt corrective measures
    to eliminate them.

    Thus, Bourdeau, as the competent person on site for scaffold erection, was required to identify
    

    hazards relating to scaffolds and had authority to correct or eliminate those hazards. Since Bourdeau
    created the hazards associated with scaffolds 1 and 2 during their erection and dismantling, he was, or
    should have been, aware of their existence as well as the fact that employee Kaneg was working from
    scaffold 2 and intended to perform work while standing on platform 1. Mr. Bourdeau’s knowledge, in
    his position as competent person, is imputed to his employer Ormet Corp 14 BNA OSHC 2134, 2138-
    39, 1991-93 CCH OSHD ¶29,254 (1991) Merritt Electric Co., Inc. 1981 CCH OSHD ¶25,556 Access
    Equipment Systems, Inc. 1991-1993 CCH OSHD ¶29,993. Therefor, Complainant has met her burden
    establishing that Respondent had actual or constructive knowledge of the violation.
    Notwithstanding the foregoing, Respondent urges that the violation be dismissed because of
    unpreventable employee misconduct. The burden to establish the affirmative defense of unpreventable
    employee misconduct falls upon Respondent. In order to establish the defense, the employer must

                                                  10
    

    show that (1) it had established work rules designed to prevent the violation; (2) had adequately
    communicated those work rules to its employees (including supervisors); (3) had taken steps to
    discover violations of those work rules, and (4) effectively enforced those work rules when they were
    violated.
    With respect to the first element, Respondent established that its safety manual includes an
    entire section devoted to the proper erection of scaffolding (Exh. R-4); that regular weekly safety
    meetings were conducted (Exh. R-5); and that its written safety program provided for progressive
    disciplinary procedures including a written warning for a first offense, suspension for the remainder of
    the work day on the second, and discharge for a third violation (Exh. R-2). Bast failed to establish,
    however, that the relevant rules on scaffolding were ever communicated during the weekly safety
    meetings. The only safety topic documented and offered into evidence concerned the health hazards
    associated with silica. The testimony, moreover, demonstrates that Respondent failed to implement its
    written disciplinary program, resulting in ineffective enforcement. The only disciplinary actions of
    which any of the Bast employees were aware, came about as a direct result of a prior OSHA inspection
    when two workers were discharged for riding in a manbasket without fall protection. Bast introduced
    no evidence that it had ever taken any disciplinary action where an OSHA inspection was not
    involved.. There was no evidence that any written warnings had ever been issued, or that any
    employees had ever been suspended prior to the OSHA inspection which is the subject of this action.
    Moreover, Foreman Salisbury testified that he had given only verbal warnings. The Commission has
    found that a program consisting only of pre-inspection verbal warnings is insufficient as effective
    enforcement. Precast Services, Inc., 17 BNA OSHC 1454, 1995 CCH OSHD ¶30,910.
    In addition, the Commission has found that misconduct by supervisory personnel constitutes
    strong evidence that safety program is lax. Consolidated Freightways Corp. 15 BNA OSHC 1317,
    1991-93 CCH OSHD ¶29,500 (No. 86-351, 1991), and that the involvement of a number of employees
    in the misconduct suggests ineffective enforcement. Gem Industrial, Inc., 17 BNA OSHC 1861, 1996
    CCH OSHD ¶31,197 (No. 93-1122, 1996). Because three separate employees, one of them the
    competent person for scaffold erection, were found violating, or observing violations of scaffolding
    violations, the employee misconduct defense has not been established.
    Finally, Respondent asserts that its employees were in the process of erecting or dismantling the
    scaffold at the time the compliance officer arrived at the scene. thus, dispensation from the
    requirements of the cited standards is applicable under the circumstances. Respondent points to (a) 29
    CFR 1926.451(b)(ii) which provides that full planking is not required when employees are erecting or

                                               11
    

    dismantling a scaffold, (b) 29 CFR 1926.451(e)(9) which provides that a safe means of access is
    determined by the employer when employees are erecting or dismantling the scaffold and (c) 29 CFR
    1926.451(g)(2) which provides that its employer, through a competent person, shall determine the
    feasibility and safety of providing fall protection for employees erecting or dismantling scaffolds. It is
    clear that the regulations cited above do not contemplate employees performing work while the
    scaffold is being erected or dismantled. The record clearly establishes that employee Kaneg was
    performing construction work while standing on the partially erected scaffold number 1 and the
    partially dismantled scaffold number 2. These work activities were observed or should have been
    anticipated by the competent person on the site, Mr. Bourdeau. Moreover, there is no evidence that
    Mr. Bourdeau instructed Mr. Kaneg to remain off the scaffold until it was fully erected. Accordingly,
    Respondent has failed to present sufficient evidence to support the dismissal of the citations.
    Moreover, since all of the violations exposed employees to falls and/or tripping hazards on scaffolds as
    high as 13 feet from the ground, it is concluded that said falls could result in serious injury or death.
    Accordingly, the violations are affirmed as serious violations.
    With respect to the serious violations set forth above, the record supports a finding that the
    violations presented a moderate to low gravity factor. In view of the fact that Respondent has a
    complete written safety program and is of a moderate size in its industry, a penalty in the amount of
    $1,000.00 is assessed for each violation for a total penalty of four thousand dollars.
    With respect to Repeat Citation 2, item 2, Respondent stipulates to the facts underlying this
    violation (Tr. 54-56), and that a substantially similar violation, previously cited, has become a final
    order of the Commission (Tr. 256-58). A violation is repeated under section 17(a) of the Act if, at the
    time of the alleged repeated violation, there was a final order against the same employer for a
    substantially similar violation. Potlatch Corporation, 7 BNA OSHC 1061, 1979 CCH OSHD ¶23,294
    (16183, 1979). A repeat violation has been established. Based upon the probability of a serious injury
    and the repeated classification of this item, the proposed penalty in the amount of $5,600.00 is assessed
    for the violation.
    Citation 1, item 4, as amended (Tr. 7)
    29 CFR 1926.1053(b)(1): The side rails of through or sidestep fixed ladders did not extend 42 inches
    (1.1m) above the top of the access level or landing platform served by the ladder:
    (a) Rear wall of the existing building, a stepladder used to gain access to a scaffold platform
    did not extend 42" above the platform.

                                                 12
    

    The cited standard provides:
    When portable ladders are used for access to an upper landing surface, the ladder side rails shall
    extend at least 3 feet (.9 m) above the upper landing surface to which the ladder is used to gain
    access; or, when such an extension is not possible because of the ladder’s length, then the
    ladder shall be secured at its top to a rigid support that will not deflect, and a grasping device,
    such as a grabrail, shall be provided to assist employees in mounting and dismounting the
    ladder. In no case shall the extension be such that ladder deflection under a load would, by
    itself, cause the ladder to slip off its support.

    CO Wigger testified that during his inspection employee Caldwell told him that he used a six
    

    foot stepladder to access scaffold No. 3 (Tr. 232-33). At hearing, Caldwell admitted using the
    stepladder (Tr. 175, 187) The ladder did not extend the required three feet above the platform being
    accessed, but was 6 to 12 inches lower than the scaffold platform (Tr. 186, 233). Caldwell testified
    that the ladder was set up approximately a foot away from the wall in the back of the scaffold facing
    the side of the platform (Tr. 189) and he used the scaffold frame as a grabrail (Tr. 190). The
    compliance officer testified that an employee dismounting from the top of the ladder would have to
    reach 3-1/2 to 4 feet for an upright on the scaffolding to use as a grabrail (Tr. 235-244, 339). Wigger
    also stated that an employee could lose his balance and fall from the top of the ladder six and one half
    feet to a concrete floor (Tr. 239, 245). It is undisputed that the cited scaffold was not fully erected at
    the time of the cited violation (Tr. 186-187, 448). The evidence establishes that the ladder used for
    accessing the cited scaffold was neither three feet above the landing surface, nor was it secured to the
    scaffold. The record thus establishes a violation, regardless of the availability of the scaffold frame for
    a grab rail.
    Bast argues that where a scaffold is not fully erected, ladder access need not be provided, citing
    Baker Concrete Construction Co., 17 BNA OSHC 1236, 1995 CCH OSHC ¶30,768 (No. 93-606,
    1995). In Baker the Commission considered a single issue, i.e.,whether employers are on fair notice
    that ladders must be provided intermittently, whenever feasible, during the process of scaffold
    assembly or disassembly. Baker is inapposite where, as here, a ladder has actually been provided. In
    that instance, as stated at §1926.451(e)(2)4, ladder usage regulations found at subpart X are specifically
    applicable.
    For the foregoing reasons the violation is affirmed.

       4
          (2) Portable, hook-on, and attachable ladders (Additional requirements for the proper construction and
    

    use of portable ladders are contained in subpart X of this part -- Stairways and Ladders):

                                                       13
    

    Penalty
    A penalty of $1,600.00 was proposed for this item. Compliance Officer Wigger stated that the
    probability of an accident occurring was small (Tr. 246). However, a fall would likely result in broken
    bones. He assessed the probable severity of an accident as medium (Tr. 245) and a 20% reduction for
    size (Tr. 246). Taking into account the relevant factors, the proposed penalty is appropriate and is
    assessed for the violation.
    Citation 3, item 1 alleges:
    29 CFR 1926.350(j) Section 3.2.4.3 American National Standards Institute Z49.11967 as adopted by
    29 CFR 1926.350(j): Oxygen cylinder(s) in storage were not separated from fuel gas cylinders, reserve
    stocks of carbides, or highly combustible materials (especially oil or grease) by a minimum distance of
    20 feet or by a noncombustible barrier at least five feet high having a fire resistance rating of at least ½
    hour:
    (a) North end of the Vestibule area, 1 oxygen and 1 acetylene cylinder were stored together.

Facts
CO Wigger testified that he observed an oxygen and acetylene tank stored side by side in the
north side of the vestibule (Tr. 259; Exh. C-15) and the tanks were not in use. The tanks were secured
to the metal studs with rope, caps in place, and no torches or hoses were located nearby (Tr. 261, 350).
Respondent argues that the gas cylinders were not “in storage” because the tanks had been used to cut a
one foot steel beam at approximately 8:00 to 8:30 that morning (Tr. 426-27), and were to be used later
to cut a second beam approximately 12 feet away (Tr. 452-53). Mark Salisbury testified that the tanks
are regularly separated when in storage; one was stored near scaffold No. 3, the other at the temporary
entrance wall (Tr. 426).
The Commission most recently discussed the definition of the term “in storage” in Andrew
Catapano Enterprises Inc., 17 BNA OSHC 1776 (Nos. 90-0050, 90-0189, 90-0190, 90-0191, 90-0192,
90-0193, 90-0771, 90-0772, 91-0026, 1996). In Catapano, the Commission noted that whether a
cylinder was in storage must be determined from looking at the evidence as a whole, taking into
consideration the length of time the cylinders were not in use, as well as whether the cylinders were to
be used intermittently or were available for immediate use. Salisbury testified, without contradiction,
that the cylinders had been in use approximately an hour before the OSHA inspection, and were needed
to cut a second beam. Based upon the evidence as a whole, it is concluded that the tanks were not in
storage within the meaning of the standard. Accordingly, this item is vacated.

                                                 14

Findings of Fact
Findings of fact relevant and necessary to a determination of all issues have been made above.
Fed. R. Civ. P. 52(a). All proposed findings of fact inconsistent with this decision are hereby denied.
Conclusions of Law

  1. Respondent is engaged in a business affecting commerce and has employees within the
    meaning of Section 3(5) of the Act.
  2. Respondent, at all times material to this proceeding was subject to the requirements of the Act
    and the standards promulgated thereunder. The Commission has jurisdiction of Respondent and the
    subject matter of this proceeding.

                                            ORDER
    
  3. Serious citation 1, item 1, alleging violation of §1910.1200(h)(2)(ii) is VACATED.

  4. Serious citation 1, item 2, alleging violation of §1926.451(b)(1) is AFFIRMED, and a penalty
    of $1,000.00 is ASSESSED.

  5. Serious citation 1, item 3, alleging violation of §1926.452(c)(2) is AFFIRMED, and a penalty
    of $1,000.00 is ASSESSED.

  6. Serious citation 1, item 4, as amended, alleging violation of §1926.1053(b)(1) is AFFIRMED,
    and a penalty of $1,600.00 is ASSESSED.

  7. Serious citation 1, items 5a and 5b, alleging violations of §1926.451(b)(4) and (b)(5)(i) are
    AFFIRMED, and a combined penalty of $1,000.00 is ASSESSED.

  8. Serious citation 2 item 1, as amended, alleging violation of §1926.451(e)(1) is AFFIRMED,
    and a penalty of $1,000.00 is ASSESSED.

  9. Repeat citation 2, item 2, alleging violation of §1926.451(g)(1) is AFFIRMED, and a penalty of
    $5,600.00 is ASSESSED.

                                               15
    

    8. Other citation 3, item 1 alleging a violation of 29 CFR 1926.350(i) is VACATED.

                                                     Robert A. Yetman
                                                     Judge, OSHRC
    

Dated:

                                            16

Get today's answer for your situation

You just read what one judge decided for one employer in 1999, and it binds only those parties. Ezel checks the current OSHA standards and Commission precedent and answers your specific situation, with citations.

Opens in Ezel Pro. Every answer cites the authority it relies on.