OSHRC Commission decision Docket 97-1918 Decided September 28, 2000 Citations affirmed

McDevitt Street Bovis, Inc.

General contractor liable for a subcontractor's scaffold violations

Apply this precedent to your situation

This is citable Commission precedent from 2000, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.

Currency note: this decision dates from 2000
The OSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Decision of the Commission
This is a decision of the Occupational Safety and Health Review Commission, the highest level of agency review, citable as Commission precedent. It may have been appealed to a U.S. Court of Appeals after issuance; check subsequent history before relying on it. The full text below is from the official OSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official OSHRC release. The full text is the Commission's own document.
Read the official release (oshrc.gov)

Plain-English summary

McDevitt Street Bovis was the general contractor building a two-story medical center in Douglas, Georgia. During a 1997 inspection, OSHA found that a scaffold used by employees of subcontractor CPD Plastering was not fully planked, lacked cross-bracing, guardrails, and safe access, and had not been erected under a competent person's supervision. OSHA cited McDevitt, the general contractor, for five serious scaffolding violations even though McDevitt did not create the conditions and none of its own employees were exposed. The only issue on review was whether McDevitt could be held responsible under the multi-employer worksite doctrine. The Commission majority held that McDevitt, given its supervisory authority and control over the site and the fact that the violations were in plain view, could reasonably have obtained abatement from CPD, so it affirmed all five violations and the $1,750 penalty for each ($8,750 total). Commissioner Visscher dissented, arguing the doctrine should not attach liability to a general contractor for a subcontractor's violations where the general contractor neither created nor controlled the specific hazard. The appended decision of Administrative Law Judge Ken S. Welsch, which the Commission affirmed, is included in full.

Decision snapshot

  • Cited standard(s): 29 C.F.R. § 1926.451(b)(1); § 1926.452(c)(2); § 1926.451(e)(1); § 1926.451(f)(7); § 1926.451(g)(1)
  • Outcome: All five serious scaffolding violations affirmed, $1,750 penalty each ($8,750 total). Majority decision (Rogers, Weisberg); Visscher dissenting.
  • Key point: A general contractor with supervisory authority and control over a construction site can be held liable under the multi-employer worksite doctrine for a subcontractor's violations it could reasonably have detected and abated, even if its own employees were not exposed.

Full text (OSHRC public release)

```text
SECRETARY OF LABOR,

 Complainant,


   v.                                        OSHRC Docket No. 97-1918

MCDEVITT STREET BOVIS, INC.
Respondent.

                                   DECISION

Before: ROGERS, Chairman; VISSCHER and WEISBERG, Commissioners.
BY THE COMMISSION:
On October 6, 1997, McDevitt Street Bovis, Inc. (“McDevitt”) was issued a
serious citation stemming from the inspection of a construction site located in Douglas,
Georgia. McDevitt was the general contractor for the project, which involved the
construction of a two-story medical center. At the time of the inspection, seven
employees of CPD Plastering Inc. (“CPD”), a subcontractor for McDevitt, were installing
insulation from a two-stage scaffold erected on the penthouse level of the medical
center’s roof. According to compliance officer Ron Byrd, the scaffold which was
owned, erected, and maintained by CPD was not erected under the supervision and
direction of a competent person, was not properly decked, and lacked cross-bracing,
guardrails, and an access ladder. It is undisputed that McDevitt did not create these
conditions and none of its own employees were exposed to them.
Under the citation, the Secretary alleged five serious violations of various
scaffolding standards and proposed a penalty of $1,750 for each violation.1 Judge Ken S.
Welsch affirmed all five violations and assessed the proposed penalty for each. The only
issue before the Commission is whether under relevant circuit court case law, the judge
erred in holding McDevitt responsible under the multi-employer worksite doctrine for the
alleged violations.2 For the following reasons, we affirm the judge’s decision.3

1
The scaffolding conditions observed by compliance officer Byrd were cited, in this order,
under the following standards: 29 C.F.R. § 1926.451(b)(1) (scaffold platform not fully
planked); § 1926.452(c)(2) (missing sections of scaffold’s cross-bracing); § 1926.451(e)(1)
(unsafe scaffold access); § 1926.451(f)(7) (scaffold erection not supervised or directed by
competent person); and § 1926.451(g)(1) (scaffold’s lack of guardrails).
2
Although the existence of the violations and McDevitt’s knowledge of them was questioned
by McDevitt in its petition for discretionary review, these issues were not included in the
Commission’s briefing notice. However, for the purposes of any appeal of our decision, we
note that these matters were adequately addressed and resolved by the judge.
3
Chairman Rogers would respectfully disagree with the dissent of her colleague,
Commissioner Visscher. In particular, she would make four points.

First, the dissent creates the mistaken impression that the Commission has developed the
multi-employer worksite doctrine out of thin air, “to simply accommodate the Secretary’s
citation policy.” In fact, there is extensive precedent by both the Commission (see the
discussion in the text below) and the Circuit Courts (see, for example, some of the cases
cited in footnote 11) supporting the doctrine’s application to general contractors in the
construction industry by virtue of their supervisory capacity or control over the construction
site. While Chairman Rogers believes the Commission must carefully analyze the extent of
a particular general contractor’s supervisory authority on a case by case basis, she has no
doubt that in this case, McDevitt possessed sufficient supervisory authority to obtain
abatement of the violations. In this case, then, the Commission has merely applied its
longstanding precedent.

Second, as noted, the Commission and the Courts have previously held general contractors
liable under the multi-employer worksite doctrine, notwithstanding the fact that none of their
own employees were exposed and notwithstanding the fact that the standards under which
the general contractors were cited did not, by their terms, impose a specific duty on the
general contractor. See, e.g., Universal Constr. Co. v. OSHRC, 182 F.3d 726 (10th Cir.
1999) (“Universal”); R.P. Carbone Constr. Co. v. OSHRC, 166 F.3d 815, 819-20 (6th Cir.
(continued...)
3
(...continued)
1998) (“R.P. Carbone”); Centex-Rooney Constr. Co., 16 BNA OSHC 2127, 1993-95 CCH
OSHD ¶30,62 (No. 92-0851, 1994) (“Centex-Rooney”); Gil Haugan d/b/a Haugan Constr.
Co., 7 BNA OSHC 2004, 1979 CCH OSHD ¶ 24,105 (No. 76-1512, 1979) (“Gil Haugan”);
Knutson Constr. Co., 4 BNA OSHC 1759, 1976-77 CCH OSHD ¶21,185 (No. 765, 1976),
aff’d, 566 F.2d 596 (8th Cir. 1977) (“Knutson”). Indeed, Chairman Rogers notes that her
dissenting colleague has downplayed the significance of these decisions by arguing that in
several of these cases, the general contractor was nevertheless the “employer responsible for
creating or controlling the particular hazard, and would thus be responsible for the violation
on that basis.” In so doing, he has cited Gil Haugan for the proposition that “citations issued
to employer for exposing its own employees were affirmed on the basis that it was the
general contractor on the site.” In fact, while the compliance officer conducting the
inspection may have believed that the exposed employees were employed by Gil Haugan,
the general contractor, the judge found they were employed by the subcontractor and
affirmed the violations on the basis of the multi-employer worksite doctrine. Gil Haugan,
7 BNA OSHC at 2005-06, 1979 CCH OSHD at p. 29,290. The Commission affirmed the
judge, finding “no error in the judge’s decision.” Id. at 2006, 1979 CCH OSHC at p. 29,290.
Similarly, in Blount Intl. Ltd., 15 BNA OSHC 1897, 1900-01, 1991-93 CCH OSHD
¶ 29,854, pp. 40,750 & 40,752 (No. 89-1394, 1992) (“Blount”), two of the violations were
affirmed on the basis of the multi-employer worksite doctrine even though Blount, the
general contractor, was not the employer who created the hazard.

Third, Chairman Rogers notes that her dissenting colleague appears to concede that it is
appropriate to hold the general contractor responsible where it is the controlling employer.
Indeed, that is part of the rationale of the multi-employer worksite doctrine - the general
contractor is “responsible for violations it could reasonably have been expected to prevent
or abate by reason of its supervisory capacity.” Grossman Steel & Aluminum Corp., 4 BNA
OSHC 1185, 1188, 1975-76 CCH OSHD ¶20,691, p. 24,791 (No. 12775, 1976) (“Grossman
Steel”). This doctrine is premised on the general contractor’s control of the construction
worksite and concomitant authority to obtain abatement. See Universal, 182 F.3d at 730-31.

Finally, Chairman Rogers takes issue with her dissenting colleague’s claim that the majority
“has therefore attached what appears to be strict liability for a subcontractor’s violation.”
Indeed, a general contractor’s liability is based on what violations the contractor, by virtue
of its supervisory capacity, could reasonably have been expected to detect or abate. The use
of a reasonableness standard is far from strict liability. Indeed, in David Weekley Homes,
Docket No. 96-2898 (September 28, 2000), also decided today, the Commission
unanimously vacated all citation items issued to a general contractor. Several of the items
were vacated on the basis that the general contractor did not know or could not have known,
with the exercise of reasonable diligence, of the existence of the cited conditions.
DISCUSSION
The Commission’s position on multi-employer construction worksites is well-
established. Under Commission precedent, an employer who either creates or controls
the cited hazard has a duty under § 5(a)(2) of the Act, 29 U.S.C. § 666(a)(2), to protect
not only its own employees, but those of other employers “engaged in the common
undertaking.” Anning-Johnson, 4 BNA OSHC 1193, 1199, 1975-76 CCH OSHD
¶20,690, p. 24,784 (No. 3694, 1976); Grossman Steel, 4 BNA OSHC at 1188, 1975-76
CCH OSHD at p. 24,791. Specifically, the Commission has concluded that an employer
may be held responsible for the violations of other employers “where it could reasonably
be expected to prevent or detect and abate the violations due to its supervisory authority
and control over the worksite.” Centex-Rooney, 16 BNA OSHC at 2130, 1993-95 CCH
OSHD at p. 42,410. See also Blount, 15 BNA OSHC at 1899, 1991-93 CCH OSHD at p.
40,749-50; Gil Haugan, 7 BNA OSHC at 2006, 1979 CCH OSHD at p. 29,290.
The record here contains strong evidence of McDevitt’s control over the worksite.
McDevitt had 22 employees onsite, including two assistant superintendents and a project
manager.4 At the hearing, assistant superintendent Scott Kopplin admitted that McDevitt had
overall authority at the worksite. Both he and the second assistant superintendent assigned to
the project walked the worksite twice a day to check on the work, including safety

4
In addition to serving as general contractor for the project, McDevitt performed some of the
concrete work associated with the medical center’s construction.
practices, of McDevitt’s subcontractors, and also performed weekly safety inspections.
According to Kopplin, as assistant superintendent, he had specific authority to demand a
subcontractor’s compliance with safety requirements, to stop a subcontractor’s work if safety
violations were observed, and to remove a subcontractor from the worksite.
The judge found that McDevitt’s representatives could have detected the cited
conditions because the violative scaffold was in plain view and erected for a significant period
of time. Taken together with the evidence of control, we find the judge reasonably concluded
under Commission precedent that McDevitt could have, by virtue of its supervisory authority,
obtained abatement from CPD. See R.P. Carbone, 166 F.3d at 819-20 (general contractor
liable for subcontractor’s lack of fall protection where condition was in plain view and lasted
for two weeks); Centex-Rooney, 16 BNA OSHC at 2130, 1993-95 CCH OSHD at p. 42,410
(where conditions were in plain view and existed for a significant period of time, general
contractor could have ascertained their existence through the exercise of reasonable diligence).
As the Commission has observed:
[T]he general contractor normally has responsibility to assure that
the other contractors fulfill their obligations with respect to
employee safety which affect the entire site. The general
contractor is well situated to obtain abatement of hazards, either
through its own resources or through its supervisory role with
respect to other contractors. It is therefore reasonable to expect the
general contractor to assure compliance with the standards insofar
as all employees on the site are affected. Thus, we will hold the
general contractor responsible for violations it could reasonably
have been expected to prevent or abate by reason of its supervisory
capacity.
Grossman Steel, 4 BNA OSHC at 1188, 1975-76 CCH OSHD at p. 24,791 (footnote omitted).
Accordingly, under applicable Commission precedent, the judge properly held McDevitt liable
for the violations of CPD.
“Where it is highly probable that a case will be appealed to a particular circuit, the
Commission generally has applied the law of that circuit in deciding the case, even though it
may clearly differ from the Commission’s law.” Tidewater Pacific, Inc., 17 BNA OSHC
1920, 1926, 1997 CCH OSHD ¶ 31,267, p. 43,909 (No. 93-2529, 1997) (citation omitted),
rev’d in part on other grounds, 160 F.3d 1239 (9th Cir. 1998). McDevitt argues that the
Eleventh Circuit and the D.C. Circuit have rejected the multi-employer worksite doctrine and,
therefore, the doctrine should not be applied in this case.5 We disagree. The Eleventh Circuit
has neither decided nor directly addressed the issue of multi-employer liability,6 and the Fifth
Circuit has not had an opportunity to consider the issue in the context of a Commission case
since the Commission adopted the doctrine in 1976. The Fifth Circuit has, however, rejected
the concept of multi-employer liability in a series of mostly tort cases.7
McDevitt cites specifically to the following Fifth Circuit decisions: Southeast
Contractors, Inc. v. Dunlop, 512 F.2d 675 [3 BNA OSHC 1023] (1975) (per curiam)
(“Southeast Contractors”); Horn v. C.L. Osborn Contracting Co., 591 F.2d 318, 321 (5th Cir.

5
McDevitt can appeal to the Eleventh Circuit because the construction site was located in
Georgia. In addition, the pleadings establish that McDevitt’s principal office is located in
Georgia.
6
In his decision, the judge referenced an Eleventh Circuit case in which the court affirmed
per curiam an administrative law judge’s decision to hold a general contractor responsible
for the violations of its subcontractor even though it was not clear whether any of its own
employees were exposed. Pace Constr. Co., 840 F.2d 24 (11th Cir. 1988), aff’g 13 BNA
OSHC 1282, 1986-87 CCH OSHD ¶ 27,889 (No. 86-517, 1987). However, both the judge
and the Secretary acknowledge that Pace, an unpublished decision, cannot be considered
binding precedent in the Eleventh Circuit. But see Anastasoff v. U.S., 2000 U.S. App. LEXIS
21179 (8th Cir. 2000) (court finds portion of Eighth Circuit’s rule which states that
unpublished opinions are not precedent unconstitutional).
7
The Eleventh Circuit has held that Fifth Circuit decisions issued prior to October 1, 1981
are considered binding precedent in the Eleventh Circuit. Bonner v. City of Prichard,
Alabama, 661 F.2d 1206, 1209 (11th Cir. 1981). Of the decisions issued by the Fifth Circuit
after that date, only those issued by Unit B are binding. See Stein v. Reynolds Securities,
Inc., 667 F.2d 33, 34 (11th Cir. 1982) (“Unit A...decisions [issued] after October 1, 1981,
are...not binding precedent in the Eleventh Circuit,” while Unit B decisions are).
1979) (“Horn”); and Barrera v. E.I. duPont de Nemours & Co., 653 F.2d 915, 920 (5th Cir.
1981) (“Barrera”).8 We agree with the judge that McDevitt’s reliance on these cases is
“misplaced.”
In Southeast Contractors, the Fifth Circuit’s initial decision on the issue of multi-
employer liability, the court reversed the Commission in a one-paragraph opinion, expressing
agreement with the “well-reasoned dissent of [then] Chairman Moran...and especially with the
portion pertaining to the general rule that a contractor is not responsible for the acts of his
subcontractors or their employees....” Southeast Contractors, 512 F.2d at 675. The
Commission had applied § 1926.601(b)(4) which prohibits an employer from using a motor
vehicle with an obstructed rear view unless it has an audible reverse signal or an observer
signals that it is safe to back up to a paving company who received an asphalt shipment from
a dump trailer it hired. Southeast Contractors, Inc., 1 BNA OSHA 1713, 1714-15, 1973-74
CCH OSHD ¶ 17,787 p. 22,148 (No. 1445, 1974). The Commission concluded that the
standard was intended to protect the “accepting” employer’s employees, one of whom had
directed the trailer driver and another who was fatally injured by the trailer. Id. Former
Chairman Moran dissented, stating that an employer cannot be found in violation of § 5(a)(2)
of the Act, 29 U.S.C. § 654(a)(2), if its own employees are not “affected by noncompliance
with a standard” and “some other employer [is charged] with the duty of implementing the
standard.”9 Id. at 1716, 1973-74 CCH OSHD at p. 22,149 (citations omitted).
In Horn, a tort case, the court relied upon its decision in Southeast Contractors in

8
Although also relied upon by McDevitt, the most recent Fifth Circuit decision on multi-
employer liability, Melerine v. Avondale Shipyards, Inc., 659 F.2d 706 (5th Cir. Unit A
1981), cannot be considered binding upon the Eleventh Circuit because it is a Unit A case,
decided after October 1, 1981.
9
At the time that former Chairman Moran wrote his dissent, the Commission’s position on
multi-employer liability was that an employer could not be held responsible for failing to
comply with OSHA standards when the only employees exposed were those of another
employer. See, e.g., Gilles & Cotting, Inc., 1 BNA OSHC 1388, 1389, 1973-74 CCH OSHD
¶ 16,763, p. 21,512-13 (No. 504, 1973), aff’d in pertinent part, 504 F.2d 1255 (4th Cir.
1974). The Commission subsequently adopted the multi-employer worksite doctrine in
Anning-Johnson and Grossman Steel.
finding that § 5(a) of the Act does not impose a duty on a general contractor to provide a
subcontractor’s employee with a safe working environment. Horn, 591 F.2d at 321. Similarly,
in Barrera, also a tort case, the court concluded that the trial court erred when it told the jury
that the Act required the defendant to furnish the plaintiff, an “invitee,” a place of employment
which was free from recognized hazards. Barrera, 653 F.2d at 920. Although the court found
the error to be harmless, it noted that the Act “does not create duties between employers and
invitees, only between employers and their employees....” Id.
In Access Equipment Systems, 18 BNA OSHC 1718, 1999 CCH OSHD ¶ 31,821 (No.
95-1449, 1999) (“Access”), a recent multi-employer case which also arose in the Eleventh
Circuit, the Commission reaffirmed the multi-employer doctrine and did not find that circuit
precedent precluded the doctrine’s application. In that case, a scaffold which Access had
erected and leased to a subcontractor collapsed, killing three employees of another
subcontractor. The Commission determined that Access could be held responsible for failing
to determine the weight the scaffold could safely bear.10 Id. at 1723-1726, 1999 CCH OSHD
at p. 46,779-81.

10
In Access, the Commission relied upon U.S. v. Pitt-Des Moines, Inc., 168 F.3d 976, 982-83
(7th Cir. 1999) (“Pitt-Des Moines”), a recent Seventh Circuit decision which upheld the
validity of the multi-employer worksite doctrine based upon the language and broad remedial
purpose of the Act. Access, 18 BNA OSHC at 1723-1726, 1999 CCH OSHD at p. 46,779-

  1. See also Universal (court concluded that the language of the Act is ambiguous on the
    issue of multi-employer liability, but deferred to the Secretary’s reasonable interpretation of
    the statute and held a general contractor responsible under the doctrine for violations of its
    subcontractor). We note, however, that both Access and Pitt-Des Moines involved
    determining the liability of one subcontractor for the violations of another subcontractor,
    rather than, as here, the liability of a general contractor for the violations of its subcontractor.
    As the Commission observed in Access, the Fifth Circuit cases represent a minority
    position among the circuits, most of whom have adopted the principles associated with multi-
    employer liability.11 Access, 18 BNA OSHC at 1725, n.12, 1999 CCH OSHD at p. 46,780,
    n.12. Furthermore, as the judge observed here, Horn and Barrera are tort cases whose
    precedential value in the context of a case before the Commission is questionable. Id., quoting
    Frohlick Crane Service, Inc. v. OSHRC, 521 F.2d 628, 631 (10th Cir. 1975) (“This is not a tort
    case. Rather, it is an administrative proceeding brought under remedial legislation designed to
    provide a safe place to work for every working man and woman in the Nation. The Act should
    not be given a narrow or technical construction...”).
    Although Southeast Contractors was originally a Commission proceeding, it was
    summarily decided and issued before the Commission even adopted the multi-employer
    doctrine.12 See Access, 18 BNA OSHC at 1725, n.12, 1999 CCH OSHD at p. 46,780, n.12.

11
See, e.g., Pitt-Des Moines (subcontractor responsible under doctrine for violation based
upon death of another subcontractor’s employee); Universal (general contractor responsible
under doctrine for violations of subcontractor); R.P. Carbone (general contractor responsible
under doctrine for violations of subcontractor); Teal v. E.I. duPont de Nemours & Co., 728
F.2d 799 (6th Cir. 1984) (tort case) (employer’s duty to comply with the Act extends to
employee of independent contractor); New England Telephone & Telegraph Co. v. Secretary
of Labor, 589 F.2d 81 (1st Cir. 1978) (subcontractor established multi-employer affirmative
defense and found not responsible for exposing its employees to violations created by general
contractor); Beatty Equip. Leasing, Inc. v. Secretary of Labor, 577 F.2d 534 (9th Cir. 1978)
(subcontractor responsible under doctrine for violation it created but to which another
subcontractor’s employees were exposed); Marshall v. Knutson Constr. Co., 566 F.2d 596
(8th Cir. 1977) (general contractor not responsible under doctrine for subcontractor’s
violation because it could not have reasonably detected the condition); Brennan v. OSHRC
(Underhill Constr. Corp.), 513 F.2d 1032 (2d Cir. 1975) (subcontractor responsible under
doctrine for violations it created but to which another employer’s employees were exposed).
12
In addressing the Fifth Circuit’s decision in Southeast Contractors, the judge relied upon
Central of Georgia R.R. Co. v. OSHRC, 576 F.2d 620, 622 (5th Cir. 1978), a subsequent
decision in which the court “agreed...that issues of creation and control...are important in
determining liability” for an OSHA violation. In Central of Georgia, the court held the cited
railroad company responsible for a housekeeping violation related to conditions along a set
of railroad tracks owned and maintained by Continental Can Corporation, but to which the
railroad’s employees had access pursuant to an agreement between the two companies. Id.
(continued...)
Indeed, as noted, the Fifth Circuit has not reviewed any Commission decisions on multi-
employer liability since the Commission adopted the doctrine. Id. Accordingly, we find that
the Fifth Circuit cases relied upon by McDevitt do not preclude us from following Commission
precedent here.
The D.C. Circuit has also not expressly accepted or rejected the multi-employer
worksite doctrine, but has raised doubts about its validity. In IBP Inc., 144 F.3d 861, 865-66
(D.C. Cir. 1998), the court found it unnecessary to decide the doctrine’s validity, but observed
that it has a “checkered history”: “We see tension between the Secretary’s multi-employer
theory and the language of the statute and regulations and we have expressed doubt about its
validity before.” Id. at 865. This previous “doubt” was expressed in Anthony Crane Rental v.
Reich, 70 F.3d 1298, 1306 (D.C. Cir. 1995), where, without deciding the issue, the court
questioned whether “the multi-employer doctrine is consistent with the Secretary’s own
construction regulation, 29 C.F.R. § 1910.12(a).” Since the D.C. Circuit has yet to decide the
issue of multi-employer liability, we will apply our precedent in this case.13

12
(...continued)
at 621-25.

 According to the Secretary, the Central of Georgia decision “eroded” any precedential value
 accorded to the Fifth Circuit’s decision in Southeast Contractors. However, the court never
 actually applied the multi-employer doctrine in Central of Georgia because the arrangement
 between the companies in question did not “fit easily into the mold of a relationship between
 a general contractor and a subcontractor.” Central of Georgia, 576 F.2d at 622. See also
 Access, 18 BNA OSHC at 1725, n.12, 1999 CCH OSHD at p. 46,780, n.12. Therefore, we
 do not consider the Fifth Circuit’s decision in Central of Georgia to be a modification of its
 position on multi-employer liability.
 13
   Chairman Rogers notes that the multi-employer doctrine can be applied in different factual
 contexts. For example, under the doctrine, liability can be based on either a contractor’s
 creation or a contractor’s control of a hazard at a multi-employer construction site. In one
 typical context, a subcontractor on a construction site has created a hazard to which
 employees of another subcontractor on the site are exposed. Under the multi-employer
 doctrine, the first subcontractor can be liable for the hazard it has created even though none
 of its own employees may be exposed. This was the factual situation in Access.

                                                                                   (continued...)

In response to our dissenting colleague’s challenge to the legal basis for the
Commission’s multi-employer worksite doctrine, a policy which has existed and been
precedent for almost 25 years, we reiterate that this case was directed for review on the very
narrow question of whether adverse circuit law precludes application of Commission
precedent. As we conclude that it does not, a point that Commissioner Visscher apparently
does not dispute, we affirm the judge’s decision.
As a final matter, we note that in its brief, McDevitt has cited to the discussion in
Anthony Crane regarding the relationship between § 1910.12(a) and the multi-employer
worksite doctrine. Anthony Crane, 70 F.3d at 1306-07. Relying on this portion of the court’s
decision, as well as the fact that the scaffolding standards cited here are construction standards,
McDevitt argues that the cited standards “apply only to the employer [CPD], not to the general
contractor for a subcontractor’s employees.”
The D.C. Circuit did not resolve this question in Anthony Crane because “the parties
have not briefed this issue, nor has any court that has adopted the multi-employer doctrine
explicitly considered it.” Id. at 1307. For the same reasons, we decline to resolve this
argument here. Neither party has concretely addressed the relationship between § 1910.12(a)
and the doctrine in their briefs before the Commission. McDevitt merely quotes to the relevant
language from Anthony Crane without any supporting analysis, while the Secretary does not
address the argument at all. Under these circumstances, we do not decide this issue here.

13
(...continued)
In another typical context, a subcontractor on a construction site has created a hazard which
the general contractor could reasonably have been expected to prevent or abate by reason of
its supervisory capacity or control over the construction site. Under the multi-employer
doctrine, the general contractor can be liable for the hazard created by the subcontractor even
though none of its own employees may be exposed. This is the situation here and in cases
such as Universal and R.P. Carbone.

 While the Commission has applied the doctrine in both contexts and various Circuit Courts
 have upheld the doctrine in both contexts, Chairman Rogers believes it is important to keep
 in mind the different factual scenarios in which the doctrine is applied. In her view, the
 rationale for applying the doctrine, as well as the factual and legal analysis, would differ
 depending upon the factual context of the case.

PENALTIES
The Secretary proposed a penalty of $1,750 for each violation. The judge assessed the
proposed penalty amount for each violation, taking into account McDevitt’s size, lack of prior
history, and good faith. He also considered the gravity of the violations to be high since there
were seven employees working on the unsafe scaffolding and they were exposed to a fall of
twelve feet. On review, neither party has addressed the issue of penalties and we see no reason
to disturb the judge’s findings on this matter. Therefore, we affirm the penalties as assessed by
the judge.
ORDER
Accordingly, we affirm the violations alleged under Items 1 through 5 of Serious
Citation 1, and assess a penalty of $1,750 for each violation.

                                                    /s/
                                                    Thomasina V. Rogers
                                                    Chairman


                                                    /s/
                                                    Stuart E. Weisberg
                                                    Commissioner

Dated: September 28, 2000
VISSCHER, Commissioner, dissenting:
The issue in this case is whether McDevitt Street Bovis, Inc. (“MSB”), as the general
contractor for the construction of a two-story medical center, is liable for violations involving
the condition of scaffolding that was owned, erected, and maintained by subcontractor CPD
Plastering (“CPD”), and was accessed solely by CPD’s employees. As discussed below, I can
find no legal duty in the cited scaffolding standards requiring MSB to supervise CPD’s
employees to ensure compliance with the standards. I further disagree with the majority that
the “multi-employer worksite doctrine” can be invoked to provide any such duty. I would
therefore vacate the citations.
The validity of citations issued under the multi-employer worksite doctrine has often
been based on whether or not section 5(a)(2) of the OSH Act allows the duty to comply with
standards to be imposed on an employer beyond the immediate employer-employee
relationship. See, e.g. Universal Construction Co., Inc. v. OSHRC, 182 F.3d 726 (10th Cir.
1999). On that question the Commission’s long-standing answer has been that section 5(a)(2)
does not limit an employer’s duty to comply with standards only to exposures to the
employer’s own employees. Access Equipment Systems, 18 BNA OSHC 1718, 1723, 1999
CCH OSHD ¶ 31,821, p. 46,778 (No. 95-1449, 1999).
In Anthony Crane Rental v. Reich, 70 F.3d 1298 (D.C. Cir. 1995), however, the D.C.
Circuit distinguished the question of how section 5(a)(2) should be interpreted from the further
question of whether the alleged multi-employer duty was consistent with the cited standards
and regulations. The court noted that it had twice upheld OSH Act violations against chemical
manufacturers charged with violating standards that imposed a duty to warn downstream
employees of hazards. But the court was unwilling to assume multi-employer liability where
the standards and regulations had not given notice to the employer of the obligations and duties
the Secretary sought to enforce. Id. See also IBP, Inc. v. Secretary of Labor, 144 F.3d 861,
865 (D.C. Cir. 1998)(further noting the court’s misgivings based on “tension between the
Secretary’s multi-employer theory and the language of the statute and regulations”).
I share the D.C. Circuit’s concern as to the legal basis for multi-employer liability.1
While § 5(a)(2) may not necessarily limit the employer’s duty to comply with standards to the
employer-employee relationship, the cited standards must actually impose the duty which the
employer allegedly violated. Following this inspection, the Secretary cited CPD with five
violations of the scaffolding standards at 29 C.F.R. §§ 1926.451 et. seq., as CPD was directly
responsible for the scaffolding and for the employees exposed to the hazards. MSB was cited
because, in the Secretary’s view, it failed to adequately supervise CPD.2 However, my review
of the scaffolding standards under which MSB was cited reveals nothing about a general
contractor’s duty to supervise other employers on the worksite.
This case thus presents a very different issue from the one resolved in the Grossman
Steel & Aluminum Corp., 4 BNA OSHC 1185, 1188, 1975-76 CCH OSHD ¶ 20,691, p. 24,790
(No. 12775, 1976) and Anning-Johnson Co., 4 BNA OSHC 1193, 1975-76 CCH OSHD ¶
20,690 (Nos. 3694 & 4409, 1976). In those jointly-issued cases, the Commission’s concern
was to assess liability against the employer best positioned to abate the hazard.3 In Grossman

1
MSB may appeal this case to either the D.C. Circuit or to the Eleventh Circuit. The D.C.
Circuit, as indicated above, has expressed doubt about the validity of the multi-employer
liability doctrine. The Eleventh Circuit has not decided or directly addressed the multi-
employer liability doctrine.
2
The Secretary’s counsel made this clear during her opening statement at the trial: “Although
there were no McDevitt Street Bovis employees working on the scaffolding at the time of the
inspection, McDevitt Street Bovis was cited for the violations because as a general
contractor, it had the overall site supervision and authority to direct and ensure that the
conditions were corrected.”
3
Prior to those decisions, the Commission had held that “a respondent cannot be held liable
for violations of [section 5(a)(2)] when none of its own employees were exposed to the
noncompliant conditions.” Martin Iron Works, Inc, 2 BNA OSHC 1063, 1063,1973-74 CCH
OSHD ¶ 18,164, p. 22,341 (No. 606, 1974) (company that failed to guard an open stairway
platform not responsible for violation where none of its own employees exposed). But see
Robert E. Lee Plumbers, 3 BNA OSHC 1150, 1974-75 CCH OSHD ¶ 19,594 (No. 2431,
1975)(affirming violations of a guardrail standard against subcontractor whose employees
were exposed, even though the employer had no responsibility for installing or maintaining
the guardrails).
Steel and Anning Johnson, the Commission announced that, as an exception to the general rule
that an employer is liable only when its own employees have access to the violative condition,
an employer who either creates or controls a citable hazard on a multi-employer construction
worksite could be liable for the violation regardless of whether its own employees were
exposed to it.
It is true that dicta in Grossman Steel, supra, made broad reference to “hold[ing] the
general contractor responsible for violations it could reasonably have been expected to prevent
or abate by reason of its supervisory capacity.” Grossman Steel, 4 BNA OSHC 1185, 1188,
1975-76 CCH OSHD at p. 24,791; accord Anning-Johnson, 4 BNA OSHC at 1199, 1975-76
CCH OSHD at p. 24,783-84. But in both cases, the general contractor created or controlled the
particular violative conditions. Furthermore the Commission seems to have been concerned
that, in recognizing an exception to the previous rule that liability always followed employee
exposure, situations might arise in which it was unclear which employer was most responsible
for a particular violative condition. In such a case, the Commission could find liability based
on the general contractor’s overall responsibility for the worksite. In neither case did the
Commission indicate that it was stating a new and separate duty of supervision for general
contractors that would parallel the responsibility of the employer that created or controlled the
particular violative condition. The Commission expressed no interest in a rule that would allow
for multiple layers of liability for a single violative condition. Indeed, both decisions were in
response to the remand of Anning-Johnson to the Commission, in which the Seventh Circuit
Court of Appeals observed:
We fail to see how requiring several different employers to [correct
the same conditions] fulfills the purposes of the Act any more
effectively than requiring only one employer to do so. The
Secretary's position is premised on the theory that the more people
responsible for correcting any violation, the more likely it will get
done. This is, of course, not necessarily true. Placing responsibility
in more than one place is at least as likely to cause confusion and
disruption in normal working relationships on a construction site.
Such a policy might in effect prove to be counterproductive.
Anning-Johnson Company v. OSAHRC, 516 F.2d 1081, 1089 (7th Cir. 1975).
That being said, I recognize that previous Commission decisions have found the sort of
“supervisory employer” liability the Secretary argues for here. But in several of these cases,
notwithstanding the Commission’s reference to liability on the basis of its supervisory role, the
general contractor was the employer responsible for creating or controlling the particular
hazard, and would thus be responsible for the violation on that basis. See Centex-Rooney
Constr. Co., 16 BNA OSHC 2127, 1994 CCH OSHD ¶ 30,621(No. 92-851, 1994)(general
contractor on the project was also the employer in charge of the guardrails, and therefore
created and controlled the violative conditions); Blount International Ltd., 15 BNA OSHC
1897, 1991-93 CCH OSHD ¶ 29,854 (No. 89-1394, 1992)(the general contractor was the
creating or controlling employer as to three of four violations affirmed against it); Gil Haugan,
d/b/a Haugan Constr. Co., 7 BNA OSHC 2004, 1979 CCH OSHD ¶ 24,105 (No.
76-1512,1979) (consolidated cases)(citations issued to employer for exposing its own
employees were affirmed on the basis that it was the general contractor on the site); Knutson
Constr. Co., 4 BNA OSHC 1759, 1976-77 CCH OSHD ¶ 21,185 (No. 765, 1976), aff'd, 566
F.2d 596 (8th Cir. 1977)(affirming a scaffolding violation against a general contractor both on
the grounds of the general contractor’s supervisory role and on the fact that its own employees
were exposed to the hazard). Where the Commission has previously found liability for general
contractors based upon their failure to supervise the subcontractors that were directly
responsible for violations, the Commission has yet to examine or explain the source of this
purported duty to supervise. Unfortunately the majority fails to do so in this case as well.
Instead the Commission has avoided any meaningful critical analysis of this issue, choosing
instead to simply accommodate the Secretary’s citation policy. See also Knutson Constr. Co., 4
BNA OSHC at 1762-63, 1976-77 CCH OSHD at pp. 25,482-83 (Moran, Commissioner,
dissenting in part).
The employer’s duty under § 5(a)(2) of the Act is to “comply with occupational safety
and health standards promulgated under this Act.” A general contractor’s duty to supervise,
however, cannot be found in any of the standards thus far promulgated by the Secretary. On
the contrary, the Secretary has chosen not to impose this duty on general contractors. In
establishing her initial body of construction safety standards as permitted under OSH Act
section 6(a), 29 U.S.C. § 655(a), the Secretary adopted the standards that had been previously
promulgated under the Contract Work Hours and Safety Standards Act (Construction Safety
Act), 40 U.S.C. § 333. The regulations under the Construction Safety Act include a provision
that does establish a broad duty for the “prime contractor” to assure safety compliance
throughout the job. See 29 C.F.R. § 1518.16. But when the Secretary adopted Construction
Safety Act standards as OSH Act standards, she chose not to include that provision, nor has she
since proposed any such standard of her own.
In the absence of a standard setting forth MSB’s duty to supervise, the majority opinion
cites two possible “sources” for MSB’s duty to supervise. First, the majority says that MSB is
“responsible for the violations under the multi-employer liability doctrine.” But that simply
begs the question, for the doctrine cannot impose a duty that is not imposed by a standard.
Second, the majority appears to base MSB’s duty to supervise on the presence of MSB
employees on the workplace, as well as contract provisions that allowed MSB to demand that
CPD comply with safety requirements. But the majority can point to no standard as a source
for the proposition that a general contractor who is present on the worksite has a legal duty
under the OSH Act to supervise and enforce standards against the subcontractors. Indeed the
notion that a general contractor’s duty under the Act depends on what role the general
contractor assumes on the worksite and in contract provisions runs directly contrary to the
principle that an employer’s duties are set by the Act, not by contract, and therefore an
employer may not contract away its duties and responsibilities under the OSH Act. See, e.g.,
Baker Tank Company/Altech, 17 BNA OSHC 1177, 1180, 1995 CCH OSHD 30,734, p. 42,684
(No. 90-1786-S 1995). Furthermore, if we are to apply the rule stated by the majority, a general
contractor that is present on the worksite and assumes a role in health and safety of its
subcontractor’s employees becomes equally liable with that subcontractor for the
subcontractor’s violations, while the general contractor which avoids any role also avoids OSH
Act liability. As a leading commentary on occupational safety and health law has pointed out,
it is unlikely that such a rule promotes the purposes of the Act. See M. Rothstein, Occupational
Safety and Health Law 169 at 233 (4th ed. 1998).
The “duty to supervise” for which MSB is held liable here not only lacks any
discernible legal basis, it also lacks any definition as to its scope. The majority never indicates
what MSB was required to do under its duty to supervise CPD. Were they to walk the worksite
more frequently? Hire separate safety inspectors? Train CPD employees on how to erect
scaffolding? Assume permanent responsibility for CPD’s OSHA compliance? Nor do they
state what other general contractors must do in order to avoid liability. In the absence of a any
standard or regulation defining the extent of the general contractor’s obligations, the majority
has therefore attached what appears to be strict liability for a subcontractor’s violations: MSB
is liable for CPD’s scaffolding violations simply because it failed to prevent them.
In short, MSB was cited under standards which do not apply because they do not
impose the duty for which MSB was cited. I would therefore vacate these citations.

                                                             /s/
                                                             Gary L. Visscher
                                                             Commissioner

Dated: September 28, 2000
Secretary of Labor,
Complainant,
v
McDevitt Street Bovis, Inc., OSHRC Docket No. 97-1918
Respondent.

APPEARANCES

           Karen E. Mock, Esq.                           Richard D. Wayne, Esq.
           Office of the Solicitor                       Hinckley, Allen & Snyder
           U. S. Department of Labor                     Boston, Massachusetts
           Atlanta, Georgia                                      For Respondent
                    For Complainant

Before: Administrative Law Judge Ken S. Welsch

                                       DECISION AND ORDER
   McDevitt Street Bovis, Inc. (MSB), is a general construction contractor. On September 12,

1997, the Occupational Safety and Health Administration (OSHA) inspected a hospital construction
project in Douglas, Georgia. As a result of the inspection, MSB received a citation for scaffolding
erected by a subcontractor. MSB timely contested the citation.
The citation alleges serious violations of § 1926.451(b)(1) (item 1) for failing to fully plank or
deck the working platform of the scaffolding; § 1926.452(c)(2) (item 2) for failing to properly brace
the scaffolding; § 1926.451(e)(1) (item 3) for failing to provide proper access for the scaffolding; §
1926.451(f)(7) (item 4) for failing to ensure the scaffolding was erected by a competent person; and §
1926.451(g)(1) (item 5) for failing to provide standard guardrails throughout the scaffolding. The
citation proposes a penalty of $1,750 for each alleged violation.
The hearing was held on May 5, 1998, in Atlanta, Georgia. The parties were represented by
counsel and post-hearing briefs were filed. MSB acknowledges that it is an employer engaged in a
business affecting commerce within the meaning of the Occupational Safety and Health Act (Act) (Tr.
4-5).
Although not admitting the violative conditions, MSB principally argues that as general
contractor it was not responsible for the scaffolding erected and maintained by a subcontractor. It is
undisputed that MSB did not erect the scaffolding and MSB’s employees were not exposed to the
hazards created by the scaffolding (Tr. 7-8). For the reasons stated, the violations are affirmed against
MSB.

                                         The Inspection
    In September, 1997, MSB, as general contractor, was constructing a new hospital, Coffee

Regional Medical Center, in Douglas, Georgia. The hospital, 125,000 (250,000) square feet, was
designed as two stories with a penthouse area on the roof to house the mechanical equipment. The
penthouse was approximately 200 feet by 110 feet (Tr. 13, 100, 113).
In addition to its general contractor responsibilities, MSB’s employees performed some of the
concrete work. MSB had approximately 22 employees on the project, including two assistant
superintendents and a project manager. The assistant superintendents’ office was a job trailer within
75 yards of the hospital construction (Tr. 100-101).
As part of his duties, assistant superintendent Scott Kopplin walked the construction site twice
a day to check on subcontractors’ work and progress, including safety. Assistant superintendent
Mitchell Surrency performed similar walk-around inspections. MSB also conducted weekly safety
inspections of the project each Monday and prepared a report (Tr. 113-115). As described by Kopplin,
the purpose of the Monday inspections was “[T]o make sure they were tied off, make sure we didn’t
have any bad contractors on the job. Basically, just safety walk-through” (Tr. 115).
On September 12, 1997, Safety and Health Compliance Officer Ronald Byrd initiated a
planned, programed OSHA inspection of the hospital project. Byrd arrived at 11:00 a.m. and started
his closing conference at 2:15 p.m. (Tr. 12, 16-17, 100). There were three subcontractors working at
the project, including CPD Plastering, Inc. (CPD), the insulation contractor (Tr. 106). CPD was on the
roof area penthouse installing Styrofoam insulation around the penthouse. To install the insulation,
seven of CPD’s employees were working from two-stage tubular welded scaffolding approximately 12
feet above the roof (Exh. C-3; Tr. 22, 102-103, 109).
The scaffolding was owned, erected and maintained by CPD (Tr. 94, 117). In inspecting the
scaffolding, compliance officer Byrd noted that the scaffolding had no cross-bracing on the side next
to the penthouse. Also, cross-bracing members were missing in various other locations in front of the
bracing (Exhs. C-4, C-6; Tr. 26-27, 39-40). The working platform on the scaffolding was not fully
decked, leaving gaps between the guardrails and the uprights (Exh. C-3; Tr. 20). Also, there were
guardrails missing and the scaffolding was not equipped with access ladders. Employees were
observed climbing down the cross-bracing (Exhs. C-5, R-1; Tr. 40-41, 47-48).
According to compliance officer Byrd, assistant superintendent Kopplin stated that the
scaffolding was erected a week prior to the inspection (Tr. 52, 79). However, at the hearing, Kopplin
testified that the scaffolding was erected the day preceding the inspection (Tr. 116). He stated that
CPD was just beginning work on the penthouse the prior day (September 11, 1997) by pulling
scaffolding to the roof. Kopplin testified that he was not on the roof on September 11 and had not left
MSB’s trailer on the day of OSHA’s inspection (Tr. 103, 106).
As a result of the inspection, MSB received a serious citation on October 6, 1997, for the
scaffolding violations created by CPD. CPD also received a citation for the same scaffolding
violations as MSB (Exh. R-2; Tr. 92). There were no OSHA citations issued relative to the safety of
MSB’s employees (Tr. 85).

                                           Discussion

Alleged Violations
The Secretary has the burden of proving a violation.
In order to establish a violation of an occupational safety or health
standard, the Secretary has the burden of proving: (a) the applicability of
the cited standard, (b) the employer’s noncompliance with the standard’s
terms, (c) employee access to the violative conditions, and (d) the
employer’s actual or constructive knowledge of the violation (i.e., the
employer either knew or, with the exercise of reasonable diligence could
have known, of the violative conditions).

Atlantic Battery Co., 16 BNA OSHC 2131, 2138 (No. 90-1747, 1994).
Violations of the Scaffolding Standards
MSB was cited because the scaffolding used by CPD failed to have full planking, in violation of
§ 1926.451(b)(1); failed to have proper cross-bracing, in violation of § 1926.452(c)(2); failed to have
proper access, in violation of § 1926.451(e)(1); failed to be erected under the supervision of a
competent person, in violation of § 1926.451(f)(7); and failed to have guardrails at all locations, in
violation of § 1926.451(g)(1).
There is no dispute that the scaffolding used by CPD lacked the required guardrails, cross-
bracing, planking and means of access (Tr. 20, 23, 26-27, 34-35, 39-41, 47-49). The photographic
evidence and observations by compliance officer Bryd show the violations. The nature and extent of the
violations observed establishes that the scaffolding was not erected by a competent person. Also, it is
undisputed that CPD’s employees working on the scaffolding were exposed to the hazards caused by
the missing guardrails, bracing, access ladders, and planking. The scaffolding did not comply with the
requirments of the standards (Exh. C-3 - C-5).
Although it does not admit the scaffolding violations, MSB does not offer any contrary evidence
or dispute the observations of compliance officer Byrd. Assistant superintendent Kopplin agreed that
the “scaffolding was not up to par” (Tr. 103). He acknowledges that the scaffolding was missing
guardrails, cross bracing, decking and lacked a means of access (Tr. 109-110).
Thus, the record supports the application of the scaffolding standards, CPD employees’
exposure to the conditions and noncompliance with the terms of §§ 1926.451(b)(1), 1926.452(c)(2),
1926.451(e)(1), 1926.451(f)(7) and 1926.451(g)(1).

                                General Contractor Responsibility
   MSB argues that as general contractor, it was not responsible for a subcontractor’s (CPD)

failure to comply with the scaffolding standards. MSB asserts the multi-employer worksite defense.
MSB argues that CPD was responsible for the health and safety of its employees (Tr. 118). CPD
indemnified MSB for any violations and was responsible for promptly correcting any violations
(Tr. 116-119). The Secretary concedes that MSB did not create the scaffolding violations nor were
MSB’s employees exposed to the violative conditions (Tr. Tr. 7-8).
Under Review Commission precedent, a general contractor, however, who, as in this case, does
not have employees exposed and did not create the violative condition is still considered responsible for
violations of a subcontractor where the general contractor could reasonably be expected to prevent or
detect and abate the violation. Centex-Rooney Construction Co., 16 BNA OSHC 2127 (No. 92-0851,
1994). A general contractor’s responsibility does not depend on whether the general contractor acutally
created the hazard or has the manpower and expertise to abate the hazard itself. Red Lobster Inns of
America Inc., 8 BNA OSHC 1762 (No. 76-4754, 1980). A general contractor at a construction project
is presumed to have sufficient control over its subcontractors to require them to comply with the safety
standards and to abate violations. Its “supervision over the entire worksite [provided] sufficient control
over its subcontractors to require them to comply with occupational safety and health standards and to
abate violations.” Gil Haugan d/b/a Haugan Construction Company, 7 BNA OSHC 2004, 2006 (Nos.
76-1512 & 1513, 1979). Also see Lewis & Lambert Metal Contract, Inc., 12 BNA OSHC 1026, 1030
(No. 80-5295, 1984).
For example, in Knutson Construction Co., 4 BNA OSHC 1759, 1761 (No. 765, 1976), aff’d
566 F.2d 596 (8th Cir. 1977), the Review Commission relieved a general contractor of liability for
failing to detect a one-inch crack on the underside of a scaffolding platform before it collapsed. It
concluded that it was unreasonable to expect a general contractor to detect such a crack. However, in
Blount International Ltd., 15 BNA OSHC 1897, 1899 (No. 89-1394, 1992), the Commission found it
reasonable to expect a general contractor to detect a GFCI problem even though the condition was by
nature latent and hidden from view. In exercising reasonable diligence, a general contractor may rely in
part upon the assurances of a subcontractor, so long as it has no reason to believe that the work is being
performed unsafely. See Sasser Electric and Manufacturing Co., 11 BNA OSHC 2133 (No. 82-178,
1994).
In this case, MSB failed to exercise reasonable diligence in preventing and detecting the unsafe
scaffolding. MSB exercised and maintained overall authority over the hospital project (Tr. 111). Its
responsibility extended to the work performed by its subcontractors, including CPD. MSB selected
CPD to do the insulation work. It oversaw the subcontractor’s work and safety (Tr. 110-111, 119).
Based on the subcontract, MSB had the authority to demand CPD’s compliance or ultimately to
terminate the subcontractor for noncompliance (Tr. 119; MSB post-hearing brief, p. 4).
CPD’s scaffolding was in plain view. The lack of planking, cross bracing, access and guardrails
was clearly visible throughout the project. Compliance officer Byrd testified that he observed the
problems with the scaffolding from the ground (Exh. C-7; Tr. 41, 52, 67). On the morning of the
inspection, some of MSB’s employees were also working on the roof area (Tr. 84). It is clear that MSB
was not as diligent as it could have been in preventing and detecting the scaffolding violations. MSB’s
personnel should have noticed the lack of guardrails, planking, bracing and an access ladder. MSB’s
supervisors were knowledgeable of the scaffolding requirements and made regular inspections of
subcontractors’ work. Although Kopplin denied inspecting the scaffolding prior to the OSHA
inspection, there is no evidence that the other assistant superintendent had not inspected the area.
According to Kopplin, the entire worksite was inspected twice a day by the assistant superintendents.
Kopplin’s testimony that the scaffold was erected the day prior to the OSHA inspection is not
supported by the record. During the inspection, Kopplin told Byrd that the scaffolding had been erected
for a week. The court accepts Kopplin’s statement to the compliance officer. Admission statements by
a supervisor are permitted. Fed. Rules of Evid. 801(d)(2). Weight is given to the statement because the
it was made contemporaneous with the inspection, and Kopplin did not deny making the statement or
offer an explanation. His testimony at the hearing six months later lacked confirmation by a record or
other witness testimony. MSB referred to daily progress reports showing that scaffolding equipment
was delivered on Monday, September 8, 1997 (Tr. 116). However, the reports were not offered into
evidence and the delivery of some equipment does not necessarily show when the scaffolding in
question was erected. Also, the amount of erected scaffolding at the time of the inspection appears
extensive and required more than a few hours to erect (Exhs. C-3, C-4, C-6). The scaffolding was
erected around the penthouse, 200 feet by 110 feet (Tr. 81). It is reasonable to conclude that the unsafe
scaffolding existed for several days prior to the inspection.
MSB had the ability to prevent the violations (Tr. 110-111). Under the subcontract, CPD was
required by MSB to comply with safety and health regulations and promptly correct any violations (Tr.
117-118). However, merely requiring CPD’s compliance with safety standards does not relieve the
MSB of its responsibility to prevent or detect unsafe conditions. MSB could stop CPD’s work if it
observed safety violations (Tr. 119). MSB’s supervisors had the authority to have safety problems by
subcontractors corrected immediately (Tr. 110). MSB made sure that CPD corrected the scaffolding
violations (Tr. 49, 110-111). MSB’s two assistant superintendents walked the worksite twice a day
specifically checking on subcontractors’ work (Tr. 114-115). MSB’s job trailer was within 75 yards
and within view of the hospital construction (Tr. 100-101). Each Monday, the assistant superintendents
made a safety inspection of the hospital construction with subcontractors (Tr. 113-114). On a daily
basis, MSB exercised its authority to inspect CPD’s compliance with safety regulations and accept or
reject its work performance.
MSB was familiar with the scaffolding requirements. Assistant superintendent Kopplin
acknowledges that he knew OSHA’s scaffolding requirements and the proper procedures for erecting
scaffolding (Tr. 107). Also, MSB maintained a written site safety plan and safety manual, including
rules for its own scaffolding program which the compliance officer reviewed and considered acceptable
(Tr. 92-93). MSB was responsible to ensure that CPD complied with the scaffolding standards and
MSB should have known with reasonable diligence of CPD’s noncompliance.

                                           Fifth Circuit Precedent
    MSB argues that as a matter of law a general contractor “should not be subject to vicarious

liability for alleged violations of standards committed by other employers on a multi-employer worksite”
(MSB post-hearing brief, p. 6-7). Based on former Fifth Circuit decisions which are binding on the
Eleventh Circuit,4 MSB argues that the cases hold that as a matter of law a general contractor can not
be held responsible for the safety violations of a subcontractor. MSB cites Melerine v. Avondale
Shipyards, Inc., 659 F.2d 706 (5th Cir. 1981); Southeast Contractors, Inc., v. Dunlop, 512 F.2d 675
(5th Cir. 1975); Barrera v. E.I. DuPont De Nemours & Co., 653 F.2d 915 (5th Cir. 1981); and Horn v.
C.L. Osborn Contracting Co., 591 F.2d 318 (5th Cir. 1979) (MSB post-hearing brief, p. 2).
“Where it is highly probable that a case will be appealed to a particular circuit, the Commission
generally has applied the law of that circuit in deciding the case, even though it may clearly differ from
the Commission’s law.” D.M. Sabia Co., 17 BNA OSHC 1413, 1414 (No. 93-3274, 1995), vacated
and remanded on other grounds, 17 BNA OSHC 1680 (3rd Cir. 1996). Here, the violations occurred
and MSB has offices in the Atlanta, Georgia, area. Accordingly, this case could be appealed to the
Eleventh Circuit.

4
Decisions of the former Fifth Circuit entered before October 1, 1981, are binding precedent on the Eleventh Circuit.
Bonner v. City of Prichard, Alabama, 661 F.2d 1206, 1209 (11th Cir. 1981) (en banc).
MSB’s reliance on Fifth Circuit case law is misplaced. Southeast Contractors enunciates a
“general rule that a contractor is not responsible for the acts of his subcontractors or their employees.”
512 F.2d at 675. However, in a subsequent case, the Fifth Circuit in Central of Georgia Railroad
Company v. OSHRC, 576 F.2d 620, 622 (5th Cir. 1978), “agreed with the Anning-Johnson5 decision
that issues of creation and control of a violation are important in determining liability.” The court
further stated that “the degree to which the party charged does control the alleged hazard and the
degree of his ability actually to abate that hazard” is important in determining liability. 576 F.2d at 623.
In Central of Georgia, the court considered several factors in assessing a general contractor’s liability,
including the general contractor’s technical expertise to abate the hazard, its contractual bargaining
power, and its ability to enforce the contract. 576 F.2d at 623-624.
Similarly, the decisions in the Horn, E.I. Dupont and Melerine cases do not support MSB’s
position. Horn and E.I. Dupont involve private causes of action, not an OSHA enforcement action.
Melerine was decided after the split of the Fifth Circuit into the Fifth and Eleventh Circuits and is not
binding on the Eleventh Circuit.
Therefore, there is no showing that the Eleventh Circuit, as a matter of law, rejects the general
contractor responsibility principle. Although not a precedent, the Eleventh Circuit affirmed per curiam
the decision of the Review Commission finding a general contractor in violation even if it did not have
employees exposed to the hazard. Pace Constr. Corp. v. Secretary, 840 F.2d 24 (11th Cir. 1988).
Accordingly, MSB’s violations of the scaffolding standards are affirmed.

Classification of Violations
In determining whether the scaffolding violations are serious within § 17(k) of the Act, the
Secretary must show that MSB knew or should have known, with the exercise of reasonable diligence,
of the presence of the violations and that there was a substantial probability that death or serious
physical harm could result from the condition.
As discussed, the record establishes that MSB should have known of the unsafe scaffolding with
the exercise of reasonable diligence. MSB has “an obligation to inspect the work area to anticipate
hazards to which employees may be exposed and to take measures to prevent the occurrence.” Frank

5
Anning-Johnson Co. v. OSHRC, 516 F.2d 1081 (7th Cir. 1975) recognizes that a general contractor is responsible for
violations where a subcontractor’s employees are exposed if it creates or controls the conditions.
Swidzinski Co., 9 BNA OSHC 1230, 1233 (No. 76-4627, 1981). The scaffolding used by CPD was
open and clearly observable. As for the expected injury, the issue is whether the resulting injury would
likely be death or serious harm if an accident should occur. Whiting-Turner Contracting Co., 13 BNA
OSHC 2155, 2157 (No. 91-862, 1993). The failure to utilize adequate scaffolding at heights of 12 feet
can reasonably be expected to cause serious injury or death to employees. Therefore, a serious
violation is established.

Penalty Consideration

    The Commission is the final arbiter of penalties in all contested cases. Under § 17(j) of the Act,

in determining an appropriate penalty, the Commission is required to consider the size of the employer’s
business, history of previous violations, the employer’s good faith, and the gravity of the violation.
Gravity is the principal factor to be considered.
MSB is a large employer with over 250 employees. There were 22 employees at the hospital
site. Credit is given to MSB for history and good faith because it had received no citations within the
last three years and it maintained good safety programs (Tr. 54-55). With regard to gravity, probability
and severity is considered high in that employees were exposed to a fall of 12 feet to a concrete surface.
There were seven employees exposed to the hazards posed by the unsafe scaffolding.
Accordingly, for the serious scaffolding violations a penalty of $1,750 for each violation is
appropriate.

                                  FINDINGS OF FACT AND
                                  CONCLUSIONS OF LAW

    The foregoing decision constitutes the findings of fact and conclusions of law in accordance with

Rule 52(a) of the Federal Rules of Civil Procedure.

                                                ORDER

    Based upon the foregoing decision, it is ORDERED that serious Citation:
    1.      Item 1, violation of § 1926.451(b)(1), is affirmed and a penalty of $1,750 is assessed.

2. Item 2, violation of § 1926.452(c)(2), is affirmed and a penalty of $1,750 is assessed.
3. Item 3, violation of § 1926.451(e)(1), is affirmed and a penalty of $1,750 is assessed.
4. Item 4, violation of § 1926.451(f)(7), is affirmed and a penalty of $1,750 is assessed.
5. Item 5, violation of § 1926.451(g)(1), is affirmed and a penalty of $1,750 is assessed.

                                        KEN S. WELSCH
                                        Judge

Date: December 2, 1998
```

Get today's answer for your situation

You just read Commission precedent from 2000. Ezel checks whether it still stands, including any court review since, and answers your specific situation, with citations.

Opens in Ezel Pro. Every answer cites the authority it relies on.