Linde Enterprises, Inc.
Trenching cave-in items affirmed serious, seat-belt item vacated, $1,800
Apply this to your situation
This order from 1996 bound only the parties to this case; it isn't precedent. Ezel answers your situation under the current OSHA standards and Commission precedent, with citations.
Plain-English summary
Linde Enterprises is a Pennsylvania excavating contractor that was installing
utility lines in Dunmore, Pennsylvania. Acting on an anonymous complaint, an
OSHA compliance officer inspected the trench worksite and issued one serious
citation with four items. Linde first argued the inspection was invalid,
saying the officer had no basis to be there and videotaped the trench from
private property before a warrant was obtained. Judge John H. Frye, III
rejected those arguments: the complaint named Linde, and the videotaping was
done from a commercial parking lot open to the public, so the "open fields"
rule applied and the evidence stood.
On the merits, the judge affirmed the trenching violations. The soil was
properly classified as Type B (not the more stable Type A Linde claimed),
partly because of heavy truck traffic 20 to 30 feet away, so the trench was
improperly sloped (§ 1926.652(a)(1)); a trench box left only partly inserted
with a worker below its protection, and the failure to conduct a competent
daily inspection, also violated the standards (§ 1926.652(g)(2) and
§ 1926.651(k)(1)); and Linde's "impossibility" defense failed because it never
showed it tried feasible alternatives. A back-up alarm that was disconnected on
a front-end loader (§ 1926.602(a)(9)(ii)) was affirmed as serious but its
penalty was reduced to zero because Linde reconnected it immediately and had a
maintenance program. The seat-belt item (§ 1926.602(a)(2)(i)) was vacated
because the officer's observations did not show the equipment lacked compliant
seat belts. Total penalty: $1,800.
Decision snapshot
- Cited standard(s): 29 C.F.R. § 1926.652(a)(1), § 1926.652(g)(2), § 1926.651(k)(1), § 1926.602(a)(9)(ii), § 1926.602(a)(2)(i)
- Outcome: Items 1, 2a, 2b, and 3 affirmed serious (item 3 penalty reduced to $0); item 4 (seat belts) vacated; total $1,800
- Key point: Heavy adjacent traffic can push soil out of Type A classification, defeating a sloping defense; an "impossibility" defense requires proof the employer tried feasible alternative protection.
Full text (OSHRC public release)
```text
United States of America
OCCUPATIONAL SAF’ETY AND HEALTH REVIEW COMMISSION
1120 20th Street, N.W., Ninth Floor
Washington, DC 20036-34 19
Phone: (202) 606-5400
Fax:(202)606-5050
SECRETARY .OF LABOR
Complainant,
v. OSHRC DOCKET
NO. 95-1089
LINDE ENTERPRISES, INC.
Respondent.
NOTICE OF DOCKETING
OF ADMINISTRATIVE LAW JUDGE’S DECISION
The Administrative Law Judge’s Report in the above referenced case was
docketed with the Commission on April 11, 1996. The decision of the Judge
will become a final order of the Commission on May 13, 1996 unless a
Commission member directs review of the decision on or before that date. ANY
PARTY DESIRING REVIEW OF THE JUDGE’S DECISION BY THE
COMMISSION MUST FILE A PETITION FOR DISCRETIONARY REVIEW.
Any such etition should be received by the Executive Secretary on or before
May 1, 198 6 in order to permit sufficient time for its review. See
Commission Rule 91, 29 C.F.R. 2200.91.
All further pleadings or communications regarding this case shall be
addressed to:
Executive Secretary
Occupational Safety and Health
Review Commission
1120 20th St. N.W., Suite 980
Washington, D.C. 20036-3419
Petitioning parties shall also mail a copy to:
Daniel J. Mick, Esq.
,* .- Counsel for Regional Trial Litigation
Office of the Solicitor, U.S. DOL
Room S4004
200 Constitution Avenue, N.W.
Washington, D.C. 20210
If a Direction for Review is issued by the Commission, then the Counsel for
Regional Trial Litigation will represent the Department of Labor. Any party
having questions about review rights may contact the Commission’s Executive
Secretary or call (202) 606-5400.
FOR THE COMMISSION
Date: April 11, 1996 Ray H. Darling, Jr.
Executive Secretary
DOCKET NO. 95-1089
NOTICE IS GIVEN TO THE FOLLOWING:
Deborah Pierce-Shields
Re ional Solicitor
Of&e of the Solicitor U.S. DOL
14480 Gatewa Building
3535 Market Htreet
Philadelphia, PA 19104
James C. Oschal, Esq.
Rosenn Jenkins & Greenwald, L.L.P.
15 South Franklin
Wilkes-Barre, PA 18711
John H. Frye, III
Administrative Law Jud e
Occupational Safety an B Health
Review Commission
One Lafayette Centre
1120 20th St. N.W., Suite 990
Washington, DC 20036 3419
00106466717:03
UNITED STATES OF AMERICA
OCCUPATIONAL SAFETY AND HEALTH REVIEW COMMISSION
SECRETARY OF LABOR .
Complainant
Docket Nr. 95-1089
v.
LINDE ENTERPRISES, INC./
Respondent
APPEARANCES
For Complainant For Respondent
J. Davitt McAteer, Esq. ROseM, Jenkins & Greenwald, LLP
Acting Solicitor James C. Oschal, Esq.
Wilkes-Barre, Pennsylvania
Deborah Pierce-Shields, Esq.
Regional Solicitor
Allison Anderson Acevedo, Esq.
Attorney
U.S. Department of Labor
Philadelphia, Pennsylvania
BEFORE
JOHN H FRYE, III
Judge, OSHRC
DECISION AND ORDER
I. INTRODUCTION
This case involves an action pursuant to Section 10 (c) of the
Occupational Safety and Health Act of 1970, 29 U.S.C. §§ 651 et seq,
(hereinafter the rrActll). Respondent, Linde Enterprises, Inc. is a
corporation with its principal place of business in Honesdale,
Pennsylvania. Respondent performed excavating work involving
installation of utility lines at a worksite in Dunham, Pennsylvania,
which was inspected by the Secretary.
As a result of an anonymous telephone call alleging that
workers were involved in a dangerous work situation, David Martin, a
compliance officer from the Wilkes-Barre area office of the
Occupational Safety and Health Administration (UOSHA1l), conducted
the inspection of Respondent's Dunham worksite from April 28, 1995
through May 18, 1995. As a result, the Secretary issued one serious
citation containing four items alleging violations of 29 C.F.R. §§
1926.652(a)(l), 1926.652(g)(2), 1926.65%(k)(l), 1926.602(a)(g)(ii)
and 1926.602(a)(2) (i). Respondent filed a notice of contest of the
citations on June 15, 1995, invoking the jurisdiction of the
Occupational Safety and Health Review Commission. Jurisdiction over
the subject matter and the parties has been established.
II. BACKGROUND
Acting following an anonymous complaint that Linde employees
were working in unprotected trenches on Tigue Street in Dunmore, Mr.
Martin's supervisor directed him to inspect the Respondent9 work
site on April 28. In fact, Respondent's worksite was on Dunham
Drive, about one-half mile from Tigue Street. Mr. Martin's
2
directions took him to Dunham Drive via Tigue Street, where he
noticed other contractors at work, but did not observe any
excavations. He did not stop, but continued on to Respondent's
worksite on Dunham Drive. (Tr. 32-38.)
When Mr. Martin arrived at Respondent's site at about 4:00 PM
on Friday, April 28, 1995, he observed the worksite while he was
parked on the south side of Dunham Street. Because Respondent was
closing the worksite for the day, he took no further action at that
time. He returned on Monday, May 1, 1995. (Tr. 17, 19).
On May 1, Mr. Martin first drove by the worksite making
observations. Next, he videotaped Respondent% jobsite from a hill
outside of the parking lot of a heavy equipment dealership located
on Dunham Street. He then videotaped Respondent% jobsite from the
entrance to GNB Batteries, a commercial establishment also located
on Dunham Street. At about 8:30 AM, he presented himself to Mr.
Joseph Jugan, Respondent% foreman on the site. (Tr. 46-48, 50; G-
6) l
The evidence with regard to the conversation between Mr. Martin
and Mr. Jugan conflicts. Mr. Martin testified that Mr. Jugan
consented to the inspection. Mr. Jugan testified that he asked Mr.
Martin to "remain there and do nothing until I get back/ In any
event, both agree that Mr. Jugan excused himself and retrieved
Respondent% written policy concerning OSHA inspections from his
3
truck. During this brief time, Mr. Martin measured and videotaped
the excavation. Mr. Martin stated that Mr. Jugan did not explain
the company policy to him until Mr. Jugan retrieved policy from the
truck. Respondent's written policy presented to Mr. Martin stated:
Companv Policv: OSHA Inspections
The following is the official Company policy of Linde
Enterprises, Inc. regarding OSHA field inspections:
Upon notification by an OSHA compliance officer of a job
site inspection, the person in change of the site shall advise
the compliance officer that he is to wait until one of the
owners of Linde Enterprises, Inc. or a representative designated
by the owners arrives on the job site.
Mr. Martin then stopped inspecting. Some time later, Mr. Scott
Linde arrived and advised him that Respondent would not consent to
the inspection without a warrant. Mr. Martin returned on May 9 with
.
a warrant and was permitted to inspect. (Tr. 21-23, 51-53, 85-86,
109; R-l.)
III VAIJDITY OF THE APRIL 28 - MAY 1 INSPECTION
Respondent submits that, based upon the foregoing, Mr. Martin
had no probable cause to be at the worksite based upon the anonymous .
complaint concerning a worksite about one-half mile away. Respondent
also argues that Mr. Martin videotaped the trench from private
property on May 1, 1995, without a warrant in circumstances where
Respondent had a reasonable expectation of privacy. Moreover,
Respondent argues that after he was asked by Mr. Jugan to wait until
4
one of Respondent's representatives arrived, Mr. Martin videotaped
and measured the trench. Respondent believes that Mr. Martin's
conduct violated its Fourth Amendment right to request a warrant, and
that its motion to exclude the all the evidence gathered prior to the
warrant being obtained should be granted. See Marshall v. Barlow%,
Inc., 1436 U.S. 307, 56 L. Ed. 2d 305, 314 (1978) (warrantless OSHA
inspections are unreasonable under the Fourth Amendment).
Respondent's motion is denied. First, RespondenPs argument
that the anonymous complaint was directed toward another contractor
is not supported. While the complaint did refer to work being done
on Tigue Street, where Respondent was not present, it also
specifically referred to Respondent by name and to the excavation
work which Respondent was engaged in. Moreover, the directions
given Mr. Martin clearly sent him to Respondent's worksite, and
while Mr. Martin observed some construction work on Tigue Street, he
did not observe any excavation work in progress there. I find that
the complaint contained sufficiently information to provide OSHA
with a reasonable basis on which to inspect Respondent at its Dunham
Street worksite.
Second, RespondenVs argument that Mr. Martin entered on
private property in order to videotape its activities on May 1,
thereby depriving it of a reasonable expectation of privacy, is not
persuasive. Respondent urges that the "open-fields" doctrine does
not apply here, because it was working on private property in a
trench below ground level that was not readily observable from
public property. However, there is no evidence that Mr. Martin
entered on any property to which the public's access was
restricted. As a result, the "open fields" doctrine clearly
applies.
Under that principle, there is no constitutional violation
where an inspector makes observations from areas on commercial
premises that are out of doors and not closed off to the
public, even if the inspector entered the premises without
permission.
Secretary v. Concrete Construction Co., 15 OSHC 1614, 1617 (Rev.
Corn. 1992). In this case, Mr. Linde testified that Mr. Martin would
have had to have taped from the GNB Batteries parking lot, and
produced photographs of that lot. (See R-2 - R-6.) Two signs at
the entrance to the parking lot advise that:
This entrance is reserved for the sole use of GNB employees,
customers, and suppliers. Contractors use Gate '3;
and
Warning. This property is protected by electronic
surveillance.
The photographs show that the lot is not protected by a gate or
fence. This fact, coupled with the fact that the first sign invites
customers and suppliers to use the lot, clearly indicates that the
GNB parking lot was not "closed off to the public" as contemplated
by Concrete Construction.
Third, because Mr. Linde, not Mr. Jugan, informed Mr. Martin
that Respondent would not consent to a warrantless inspection, .
Respondent can make no claim that Mr. Martin ignored that demand
when he measured and videotaped the trench during the period that
Mr. Jugan was retrieving the company's policy from his truck. Once
presented with that policy, which simply asked that he await a
company representative, Mr. Martin complied. Assuming, as
Respondent maintains, that Mr. Jugan initially had asked Mr. Martin
to await that representative, Mr. Martin's failure to do so does not
violate Respondent's Fourth Amendment rights. At most, it offends §
8(e) of the Act, which provides that the Secretary shall afford a
representative of the employer the opportunity to accompany the
inspector. Here, there is no showing that Mr. Martin acted in such
a way as to deny Mr. Jugan that opportunity. Nor does it appear
that Mr. Jugan's brief absence prejudiced Respondent in the
preparation of its defense. Secretary v. Concrete Construction Co.,
supra, 15 OSHC at 1617-19.
IV. THE MERITS OF THE CITATIONS
Citation 1. Item 1
The Secretary cited Respondent for a violation of 29 C.F.R. §
1926.652(a)(l). This regulation provides:
Each employee in an excavation shall be protected from cave-ins
by an adequate protective system designed in accordance with
paragraph (b) or (c) of this section.
Mr. Martin observed Respondent's employees working in the
excavation on May 1, 1995. (Tr. 20-21, 147, 157, G-2 [Video Counter
Nos. 0:51, 3:02]). He measured the excavation, and found the north
side to have a depth of 10 feet and the south side a depth of six
feet. He found a small bench, 20 to 22 inches wide, located on the
north side six feet from the bottom of the excavation. There was no
slope. (Tr. 27-28, 64). He observed trash compactor trucks, trucks
delivering heavy machinery, and tractor trailers traveling along
Dunham Street within 20 to 30 feet of the excavation. (Tr. 132).
Based on this, Mr. Martin concluded that the adjacent road was
subject to extremely heavy traffic. (Tr. 143; G-2 [Video Counter
Nos. 0:56-1:35]).
Mr. Martin conducted a manual test on the soil in the
excavation on May 1, 1995, and determined that the soil was not
cohesive. Based on this and the heavy traffic, he concluded that
the soil in the excavation should be classified as Type B. (Tr.
175). Accordingly, he testified that, to comply with the OSHA
8
regulations, the excavation should have been sloped on a one-to-one
basis. (Tr. 28). He determined that fractures, or asphyxiation
resulting in serious physical harm or death could result from the
conditions present in the excavation. (Tr. 200).
Mr. Martin recommended a penalty of $900. In determining this
amount, Mr. Martin considered the severity and probability of injury
associated with the violation. The proposed penalty also included a
forty percent reduction for Respondent's size. A fifteen percent
reduction was made for good faith, based on the fact that the
employer had a written safety policy. Respondent did not receive a
reduction for history, as it had one serious violation within the
last three years. (Tr. 201, 202)
Respondent notes that it is charged with violating 29 C.F.R. §
1926.652(a), which requires an adequate protective system designed in
accord with § 1926.652(b) or (c). It notes that § 1926.652(b)(2)
permits sloping and benching systems to exist consistent with
Appendices A and B to that subpart. Citing Appendix B, Figure B-l.1
for excavations made in Type A soil, it maintains that the slope of
the trench was l/2:1, permissible for excavations which are open 24
hours or less and are 12 feet or less in depth. Mr. Yelland,
Respondent 9 superintendent, testified that the trench was sloped at a
ratio of l/2:1. (Tr. 369-70.) Mr. Yelland also indicated that he
conducted both visual and Uthumbfl tests on the soil, and he concluded
that the soil was UhardpanU (Tr. at 3600362), which is specifically
defined as Type A soil in Appendix A to 29 C.F.R. 5 1926.652.
Similarly, Mr. Linde testified that he performed visual inspections
and concluded that the soil was hardpan. (Tr. at 349-350).
The first question to be decided is whether the soil was
properly classifiable as Type A. Respondent is correct that hardpan
' is, by definition, Type A soil. However, Mr. Martin's concluded that
the soil was not cohesive, a condition inconsistent with hardpan. It
is unlikely that a Compliance Officer with Mr. Martin's experience
would make an error in this regard. If the soil were hardpan, that
condition should be evident from the soil deposited in the spoil pile,
where Mr. Martin obtained his sample. It is not likely that clumps of
hardpan would be completely broken up in the digging process.
Moreover, the presence of heavy truck traffic on the adjacent
roadway dictates against the Type A'classification. Appendix A
provides that no soil is Class A if it is subject to vibration from
traffic. While Mr. Martin conceded that the standard does not specify
a safe distance from the traffic (Tr. 172-173), Dr. Peck indicated
that heavy traffic on a road located some 20 to 30 feet from the
excavation Y.. would cause vibrations that would be transmitted to
the soil and cause it to become additionally unstable." (Tr. 297.)
It is clear that the soil in question was properly classified as Type
10
B. The slopes which Respondent maintains were employed in the trench
are not acceptable for Type B soil.
Additionally, there is some question whether the trench was
sloped or benched. If the trench walls were sloped in Type A soil,
the l/2:1 ratio to which Mr. Yelland testified would be acceptable.
While the Respondent's witnesses often spoke in terms of slopes, it is
not clear whether they intended to imply that the walls were sloped to
the exclusion of utilizing benches. Mr. Yelland seems to say that
both were used. (Tr. 364-70.) Mr. Martin clearly indicated that the
trench walls were not sloped, and that the north wall was benched. If
the Respondent employed benches, a ratio of 3/4:1 would be required
(see Appendix B, 5 Bl.l(2)), and Mr. Yelland's ratio of l/2:1 would be
unacceptable.' In sum, the preponderance of the evidence supports the
issuance of this citation.
Citation I~ Items 2a and 2b
Item 2(a) alleges a violation of 29 C.F.R. § 1926.652(g)(2),
which states:
Excavations of earth material to a level not greater than 2
feet (.6lm) below the bottom of a shield shall be permitted,
but only if the shield is designed to resist the forces
calculated for the full depth of the trench, and there are no
indications while the trench is open of a possible loss of soil
from behind or below the bottom of the shield.
Item 2(b) alleges a violation of 29 C.F.R. § 1926.651(k)(l),
which states in part that:
Daily inspections of excavations, the adjacent areas, and
protective systems shall be made by a competent person for
evidence of a situation that could result in possible cave-ins,
indications of failures of protective systems, hazardous
atmospheres, or other hazardous conditions.
When Mr. Martin arrived at the worksite on May 9, 1995, he
observed a trench box protruded half way out of the excavation. A
worker was in the trench. Mr. Yelland was present? After Mr.
Martin's arrival, the worker exited the trench and the box was more
fully inserted, an operation that entailed some difficulty because
the trench was not wide enough to accommodate the trench box. (Tr .
22-23, 204, 236). Mr. Martin measured the trench and the trench box .
and found the depth of the trench to be eight feet and the height of
the trench box to be five feet. (Tr. 204, G-2, Video Counter Nos.
5~28-5~44). Mr. Yelland testified that the trench box reached to
about 2 l/2 to 3 feet of the bottom of the trench. (Tr. 376, 382).
Mr. Martin observed earth falling into the excavation while a
worker was present in the excavation after the box had been more
fully inserted into the trench. Mr. Martin observed that the worker
was working below the level of protection provided by the trench
l While Mr. Yelland testified that he had not recollection of a worker in
the trench at this time (Tr. 377, 380), Mr. Martin's testimony that a
worker was present was unequivocal. (Tr. 236-38, 240-43.) In this
circumstance, I credit Mr. Martin's testimony as accurate.
12
box. (Tr. 23, 211, G-2./ Video Counter No. 9:18). He also observed
heavy traffic passing near the excavation which could reduce the
stability of the soil, and that the soil had been previously
excavated. (Tr. 211-12, G-2, Video Counter Nos. 4:40-5:27). Mr.
Martin testified that the failure to properly install a protective
system into this excavation could result in broken bones or
asphyxiation of a worker. (Tr. 212).
Respondent asserts that it was not possible to insert the
trench box far enough into the trench to comply with 5
1926.652(g)(2) because the box was obstructed by solid rock and some
utility lines. (Tr. 255-58, 267, 370, 378.) When an employer makes
an affirmative defense that compliance with the regulations is
impossible or infeasible, the employer bears the burden of
demonstrating that compliance with the standard is impossible and
that the employer used alternative means to protect its employees or
that alternative means were unavailable. See, Bancker Construction
Corp. v. Reich, 31 F.3d 32, 34 (2d Cir. 1994); Brock v. Dun-Par
Engineered Form Co./ 843 F.2d 1135, 1136 (8th Cir. 1988); Long Beach
Container Terminal, Inc. v. OSHRC, 811 F.2d 471, 479 (9th Cir. 1987);
Noblecraft Industries, Inc. v. Sec. of Labor, 614 F.2d 199, 205 (9th
Cir. 1980).
13
In Dun-Par, an employer was cited for failing to provide
guardrails at a construction site. As its defense, Dun-Par claimed
that it was impossible to install the guardrails. The court held
that since it is the employer's responsibility for its employee's
safety under the Act, the employer must "affirmatively investigate
alternative measures of preventing the hazard, and actually
implement such alternative measures, to the extent feasible." Id.
at 1139.
In the present case, Respondent failed to adequately protect
its employees from cave-ins, but did not explore alternative means
of protecting its employees in the trench. Mr. Yelland indicated
that existing utilities and a rock preventing the box from being
inserted further into the excavation. (Tr. 379). However, the
defense of impossibility of performance will not lie Y.. if an
employer shows merely that compliance would be difficult,
inconvenient, or expensive-u Long Beach, supra. He also insisted
that a trench plate, which had been inserted, would protect the
workers. (Tr. 380). However, the video shows soil sporadically
flowing into the trench from the vicinity of the trench plate even
as an employee was working, as well as the presence of heavy truck
traffic immediately above the employee. (G-2, Video Counter No.
9:18). Respondent provided no evidence that it investigated and
attempted to implement any alternative measures to protect employees
14
from a cave-in. Consequently, its arguments regarding the
impossibility or infeasibility of compliance are rejected.
Moreover, when Mr. Martin arrived on the site, the trench box
was only inserted to the extent of one-half of its height and a
worker was in the trench. Clearly, that worker received little if
any protection from the trench box. This hazard was blatant and
occurred in the presence of Respondent's competent person, Mr.
Yelland. Therefore, I must conclude that Mr. Martin is correct that
Mr. Yelland failed to recognize a blatant hazard. The Secretary has
demonstrated that Respondent violated 5s 1926.651(k)(l) and
1926.652(g) (2).
Respondent urges that these items, and item 1, involving the
sloping of the trench, should be classified as "Other Than Serious/
Respondent urges that
it is hard to imagine any scenario under which any employee
in-the trenches which are the subject of [these items] could be
subject to a "substantial probability" of asphyxiation and
fracture hazards as alleged.... The trenches were sloped, and a
trench shield was installed in each case, respectively. In the
case of the trench shield, it was resting on one side on solid
rock which could not have collapsed below the shield. Thus,
under any scenario, Citation I, Items .1and 2a should be reduced
in classification from WeriouP to "Other Than SeriousH, even
assuming arguendo that LINDE violated the regulations. The
monetary penalties should be eliminated or reduced
correspondingly as well. (Respondent's brief, p. 13.)
Trenching is a hazardous activity. Despite Respondent's
protestations to the contrary, it violated OSHA standards applicable
15
to these trenches. The close proximity of heavy truck traffic and the
sporadic spilling of soil into the trench partially protected by the
trench box and shield dramatize the potential for serious injuries
even after the trench box had been more fully inserted into the
trench. Similarly, the failure to properly slope or bench the trench
inspected on May 1 carried with it the potential for serious injuries.
These violations were appropriately classified as "serious/ and the
penalties properly calculated by Mr. Martin.
Citation 1 Item 3
This item alleges a violation of 29 C.F.R. § 1926.602(a)(g)(ii)
which provides:
All bidirectional machines, such as rollers, compactors, front-
end loaders, bulldozers and similar equipment, shall be
equipped with a horn, distinguishable from the surrounding
noise level, which shall be operated as needed when the machine
is moving in either direction. The horn shall be maintained an
operative condition.
Mr. Martin testified that he observed a worker operating
Respondent's front-end loader on May 9, 1995, on the Respondent's
worksite. (Tr. 195-96, 219-220; G-2, Video Counter Nos. 6:46-7:15).
Mr. Martin saw the front-end loader back up several times in a ten-
minute period but did not hear the reverse signal alarm operating.
(Tr. 215, 220, 271; G-2,. Video Counter Nos. 6:46-7:15). Mr. Yelland
was present. (Tr. 360). Mr. Martin testified that when this
16
situation was brought to the foreman's attention, the latter
indicated that the alarm had been disconnected for some reason and
immediately reconnected it. Thereafter, Mr. Martin heard the alarm
operating. (Tr. 214-15.) An accident which occurs as a result of
an inoperable back-up alarm could cause an employee to suffer death
from internal injuries, fractures, blood loss or asphyxiation. (Tr .
220).
Respondent urges that it has an active, ongoing vehicle
maintenance program (R-9) I and quickly corrected the violation. It
also urges that there is no evidence that it knew of and permitted
the condition to exist. However, Mr. Yelland's presence on the site
is sufficient to impute knowledge to Respondent. Respondent urges
that the violation should be classified as other-than-serious.
While the violation is clearly serious, Respondent's quick action to
correct it and its ongoing vehicle maintenance program dictate that
the penalty should be reduced to $00.
Citation 1 Item 4
This item 4 alleges a violation of 29 C.F.R. §
1926602(a)(2) (i), which provides, in part:
Seat belts shall be provided on all equipment covered by this
section and shall meet the requirements of the Society of
Automotive Engineers, J386-1969, Seat Belts for Construction
Equipment.
17
Mr. Martin testified that on April 28, 1995, he observed an
employee riding on the access ladder of a front-end loader, without
being secured in the vehicle by a seat belt. (Tr. 129, 221, 222; G-
2, Video Counter Nos. 0:05-0:21, 0:39-0:44). Mr. Martin's
observations are not relevant to the issue of whether the front-end
loader was equipped with seat belts meeting the requirements of the
cited standard. This citation is vacated.
v. CONCLUSIONS OF LAW
A. Respondent Linde Enterprises, Inc., is an employer
engaged in a business affecting commerce within the meaning of
section 3(5) of the Occupational Safety and Health Act of 1970, as
amended, 29 U.S.C. § 652(S) ("the Act").
B. Jurisdiction of this proceeding is conferred upon the
Occupational Safety and Health Review Commission by section 10(c) of
the Act, 29 U.S.C. § 659(c).
Citation 1, Item 1.
c. Respondent Linde Enterprises, Inc., was in serious
violation of the standard set out at 29 CFR §§ 1926.652(a)(l). A
penalty of $900 is appropriate.
Citation 1, Items 2a and 2b
18
/--
D. Respondent Linde Enterprises, Inc., was in serious
violation of the standards set out at 29 C.F.R. 5s 1926.652(g)(2)
and 1926.651(k)(l). A penalty of $900 is appropriate.
E. Respondent Linde Enterprises,, Inc., was in serious
violation of the standard set out at 29 C.F.R. 5 1926.602(a)(g)(ii).
A penalty of $00 is appropriate.
F. Respondent Linde Enterprises,, Inc., was in not serious
violation of the standard set out at 29 C.F.R. 5 1926.602(a)(2)(i).
VI. ORDER
A. Citation 1, items 1, 2a, 2b, and 3 are affirmed as
serious violations of the Act.
B. Citation 1, Item 4, is vacated.
C. A total civil penalty of $1,800 is assessed.
Dated: -Am I 1 1996
Washington, D.C.
19
```
Get today's answer for your situation
You just read what one judge decided for one employer in 1996, and it binds only those parties. Ezel checks the current OSHA standards and Commission precedent and answers your specific situation, with citations.
Opens in Ezel Pro. Every answer cites the authority it relies on.