Computer Sciences Raytheon
Two launch-platform items vacated, ramp item affirmed
Apply this to your situation
This order from 1995 bound only the parties to this case; it isn't precedent. Ezel answers your situation under the current OSHA standards and Commission precedent, with citations.
Plain-English summary
Computer Sciences Raytheon employees opened camera boxes on Kennedy Space Center's mobile launch platform after space shuttle launches. The judge found that workers approached unguarded blast holes and perimeter edges before tying off, but she vacated those two items under the multi-employer worksite defense. NASA controlled the launch sequence and platform configuration, while the company trained employees, enforced lanyard use at the camera boxes, and reasonably determined that retractable devices were ineffective in that setting. A separate three-foot guardrail gap on the access ramp was different because it was easy to correct and did not involve the same launch-platform constraints. The judge affirmed that ramp item as serious and assessed a $1,000 penalty because the company neither asked NASA to correct it nor sought permission to add a temporary railing.
Decision snapshot
- Cited standard(s): 29 C.F.R. §§ 1910.22(c), 1910.23(c)(1), and 1910.23(c)(2).
- Outcome: Mixed. The blast-hole and platform-perimeter items were vacated, while the serious ramp-guardrail item was affirmed with a $1,000 penalty.
- Key point: A multi-employer defense may protect a contractor where the controlling employer tightly manages a technically complex hazard and realistic alternatives were used, but it does not excuse an easily corrected guardrail gap the contractor never raised.
Full text (OSHRC public release)
UNITED STATES OF AMERICA
OCCUPATIONAL SAFETY AND HEALTH REVIEW COMMISSION
One Lafayette Centfe
1120 20th Street, N.W. - 9th Floor
Washington, DC 2003643419
PklQNE
COM (202) 6@4100
f=(202)-1=
SECRETARY OF LABOR
Complainant,
v. OSHRC DOCKET
NO. 93-0232
COMPUTER SCIENCE RAYTHEON
Respondent.
NOTICE OF DOCKETING
OF ADMINl[STRATM? UiW JUDGE’S DECISION
The Administrative Law Judge’s Report in the above referenced case was
docketed with the Commission on December 8, 1994. The decision of the Judge
will become a final order of the Commission on January 9, 1995 unless a
Commission member directs review of the decision on or before that date. ANY
PARTY DESIRING REVIEW OF THE JUDGE’S DECISION BY THE
COMMISSION MUST FILE A PETITION FOR DISCRETIONARY REVIEW.
Any such petition should be received by the Executive Secretary on or before
December 28, 1994 in order to permit sufficient time for its review. See
Commission Rule 91, 29 C.F.R. 2200.91.
All further pleadings or communications regarding this case shall be
addressed to:
Executive Secretary
Occupational Safety and Health
Review Commission
1120 20th St. N.W., Suite 980
Washington, DC. 2003603419
Petitioning parties shall also mail a copy to:
Daniel J. Mick, Esq.
Counsel for Regional Trial Liti ation
Office of the Solicitor, U.S. DOH.
Room S4004
200 Constitution Avenue, N.W.
Washington, D.C. 20210
*If a Direction for Review is issued by the Commission, then the Counsel for
Regional Trial Litigation will represent the Department of Labor. Any party
having questions about review nghts may contact the Commission’s Executive
Secretary or call (202) 606-5400.
Date: December 8, 1994 ~~~~~~
DOCKET NO. 93-0232
NOTICE IS GIVEN TO THE FOLLOWING:
Daniel J. Mick, Esq.
Counsel for Regional Trial Liti ation
Office of the Solicitor, U.S. DO8.
Room S4004
200 Constitution Ave., N.W.
Washington, D.C. 20210
Jaylynn Fortney
Re ‘onal Solicitor
O&e of the Solicitor, U.S. DOL
Suite 339
1371 Peachtree Street, N.E.
Atlanta, GA 30309
Mark S. Dreux, Esq.
McDermott, Will & Emery
1850 K Street, N.W.
Washington, DC 20006 2296
Nancy J. Spies
Admmistrative Law Jud e
Occupational Safety an tf Health
Renew Commission
1365 Peachtree St., N. E.
Suite 240
Atlanta, GA 30309 3119
00106491574:04
UNITED STATES Of AMERlCA
OCCUPATIONAL SAFETY AND HEALTH REVIEW COMMISSION
1365 PEACHTREE STREET, NE, SUITE 240
ATlANTA, GEORGIA 30309-3119
PHONE: FAX.
COM (404) 3474197 COM (404) 347-0113
ns (404) 347-m 13
FTS (404) 3474197
SECRETARY OF LABOR,
Complainant,
v. OSHRC Docket No.: 93-232
COMPUTER SCIENCES RAYTHEON,
Respondent.
Appearances:
Stanley E Keen, Esquire Mark S. Dmx, Esquire
Office of the Sdicitor . McDermott, Will & Emery
U. S. Department of Labor Washington, DC
Atlanta, Georgia Fbr Respondent
For Complainant
Before: Administrative Law Judge Nancy J. Spies
DECISION AND ORDER
Computer Sciences Raytheon (CSR) contests a serious citation issued to it on
December 9, 1992, under the Occupational safety and Health Act of 1970 (Act).’ The
citation followed an inspection conducted by Occupational Safety and Health Administration
(OSHA) Compliance officer K&en Yarbrough from September 3 through October 29,1992
The citation alleges that three serious violations occurred while employ&s worked on the
Mobile Launch Platform (A&P) at the Ke~edy Space Center (Ksc), Florida, Ad
participated in the nation’s space shuttle program. CSR contracted with the United States
1 At the hearing, the Secretay withdrew the alleged nonserious vidati~n ksued as Citation No. 2
.
.
. .
*
Air Force to, among other things, assist in retrieving the film taken of each shuttle launch
(Tr. 412).
Specifically, OSHA charges that CSR violated 5 1910.22(c), for failure to guard
interior blast hoies; 8 1910.23(c)(l), for failure to guard the exterior perimeter of the top
level of the MLP; and 8 1910.23(c)(2), for failure to guard an access ramp to the MLP.
Identical violations were alleged for other contractors as well as for NASA’
CSR contends that the Secretary failed to prove that its employees were exposed to
a zone of danger or that the standards apply, Additionally, CSR maintains that it established
affirmative defenses.
Background--TheMobile Launch Platform
During an earlier stage of the launch process, one of the space shuttles was mounted
onto the MLP at the vehicle assembly building. When Wly prepared the MLP, with the
shuttle in place, was driven to the launch pad. The Fixed Service Structure, a work staging
area, sat beside the MLP on the launch pad (Exh. C-l). The Fixed Service Structure was
also mobile and was moved to or away from the MLP depending upon the stage of the
shuttle launch (Tr. 377, 378).
The Mobile Launch Platform itself is a large rectangular structure, approximately
165 feet by 140 feet, made of reinforced steel. It rises 45 feet above ground level? The
MLP has two interior levels; but the top of the MLP, the “zero level deck” was the work
location at issue. Fall protection on the zero level deck consisted of “removable guardrails.”
The guardrails were designed to be removable because they were not “survivable,” ie., they
could not sun&e the fire and force of 8 shuttle launch (Tr. 35,36,45,290).
Removable guardrails protected three large interior openings or blast holes on the
zero level deck of the MLP. As . part of preparation for the launch, these guardrailswere
- Decisions issued in the consolidated case, RockweUI’, copft USar. Co, M&id Mm Mbnncd
Spcc @stkms,and lkW Corp., Docket Nos. 93-54,~228,~233 and 93-234 ruspective~ and l%e B&wet&s
Cbp., Docket No. 9346, involved these wserted violations. Each decision was based on a separate record.
3 In the early l!J7& NASA built mobile launch platforms to launch spaoecraft including, more recently, the
spaceshuttle. NASA uses three mobile launch platforms. For purposesof this decision, the three are without
significant differen- (Tk. 42).
2
removed to accommodate the shuttle’s main engine (positioned over the largest opening)
and two solid rocket boosters (SRBs) (sitting over the two smaller, parallel openings). The
three blast holes descended through the MLP into the trough of a “flame trench.” The
flame trench minimized damage from the rocket blasts. The distance from the zero level
deck to the base of the flame trench measured 90 to 95 feet (Tr. 40).
Removable guardrails also protected the four sides of the perimeter of the MU until
the shuttle was readied for launch. The perimeter distance from the zero level deck to the
ground level was 45 feet (Tr. 31).
Functioning much as a drawbridge, a ramp measuring 6 to 8 feet long and 5 feet wide
was lowered between the Fixed Service Structure and the MLP (Tr. 29). Prior to the
September 12 launch, there was a 3-foot gap in each side of the ramp guardrail! The
distance from the ramp to the ground was 45 feet (Tr. 31,33).
Cameras were mounted on the MLP to photograph each shuttle launch. These were
housed in permanent steel camera boxes, which were 33 inches high, 15 inches wide and
27 inches long (Tr. 295,296). As soon after the launch as the NASA safety representatives
gave the “all clear” signal, CSR employees, along with others in the scheduled sequence,
went onto the MLP. CSR employees opened the faceplate of each camera box. Employees
of another contractor, The Bionetics Corp. (Bionetics), followed CSR and actually retrieved
the film from the box (Tr. 289, 290, 297, 333). While opening the camera boxes, CSR
employees approached the perimeter and interior blast holes on the MLP. CSR employees
also returned to the camera boxes after Bionetics retrieved the film (Tr. 273). Guardrails
which protected the blast holes and the perimeter had been removed before the launch and
would not be fully replaced post-launch until after CSR had completed its work there
. (Tr. 35).
4 Although CSR employee Hedge estimated the gap in the ramp gunbils to be no morethan 1%to 2 feet
long, Hodge was amused about the conliguration of these guardrails (TL 325,338). Of grater probity was
the testimony of other witnesses and photographs of the ramp which support a 3-hot gap (Eh c2; Tr, 246).
3
ITEM 1: 8 1910.22(c)-Falling into Pits
The Secretary contends that the unguarded blast hole openings presented a fall
hazard to CSR employees in violation of 0 1910.22(c)? CSR denies that the standard
applies or was violated.
The Mobile Launch Ptiztjiorm is a Permanent Pk of Employment
CSR argues that the MLP is not covered by the general scope provisions of 0 1910.22,
which applies to “permanent place(s) of employment.” The MLP is permanent in the sense
that it affords employees a fixed workspace. It has been used in approximately the same
form for more than 20 years. Employees of many employers worked on the MLP for
extended periods of time. Although the MLP is also “mobile” and is one of three which
may be used at any &en time for a particular shuttle launch, it is no less a “permanent”
worksite. The argument is rejected.
CSR contends that 0 1910.22(c) was invalidly promulgated. It argues that “Material
Handling and Storage” was the title for the source standard which became subsections
0 1910.22(b) and (c). The title was not included when OSHA adopted the substantive
portion of the source standard pursuant to Q6(a) of the Act. The fact that source standards
were organized in a certain way or carried a title consistent with that organization is not .
considered a substantive limitation to the scope of the standard. Nonsubstantive omissions
need not invalidate a 5 6(a) promulgation of standards. See Mb&m Drop Forge
Co. v. Secretaryof Lubor, 683 F.2d 1105, llll(7th Cir. 1980) (although note accompanying
source standard’s provision was excluded, the standard at issue was adopted verbatim and
deletion was not a substantive difference). Further, the suggested “redundaq” between
0 1910.22(c) and 0 1910.23(a) does not exist since the latter standard specifically concerns
5 The standard requires:
0 191022(c). covets md guaniraik Covers and/or guardrails shall be provided to protea
personnel from the hazards of open pits, tanks, vats, ditches, etc,
4
“stairway floor openings” rather than the more general coverage of “open pits” in
8 1910.23(a).
CSR argues that the blast hole openings were not “open pits” within the meaning of
6 1910.22(c) as to cameras B-4 and B-8. Neither camera box was in issue. Further, the
main engine and booster rocket blast holes presented unguarded or open “pits” (defined in
RandomHowe Unabridged Dictiomwy,2d Ed., 1983, as a“hole or cavity”) since they were
not guarded on all sides.
The standard is valid and applies to the conditions cited.
Although thirty-two camera boxes were located on the zero level deck of the MLP,
by stipulation, only camera boxes designated as B-13, B-16, O-1 and O-4 constituted fti
hazards into the blast holes (Ehs. C-4, R-l; Tr. 50, 5647,289).
Exposure to a zone of danger exists when employees are in the immediate area of
a hazard. As the parties agree, there is no established distance which automatically equates
to being in an immediate area of hazard. That determination is speci& to the facts.
The weather became stormy on June 25,1992, one of the two launch dates at issue.
Bionetics employee Steven Hills described the weather conditions during film retrieval that
day as follows: .
When we got on top of the Fixed Service Structure at the 90-fmt level, which
is the MLP deck level, the wind was high and the deck was wet and water
was--the deluge system was leaking like it ahvays does.
And, because there’s solid residue left over from the solid& the deck is real
slippery, and water was flowing vertically up through the solid rocket booster
blast holes and from the main engine blast holes. And it Wasblowing from all
different directions (Tr. 255).
On that day the- wind was high and gusting (Tr. 271). The zero level deck, which was
constructed of welded steel, had slightly varying elevations along the deck. Some areas of
the zero level deck, particularly between the solid rocket and the main engine blast holes,
_ v---w
had pipes protruding along the surface. CSR employees shared the deck with as many as
twenty other persons performing a variety of tasks. Often there was “high pressure or gas
noises [from] different areas of the pad and on the deck or on top of the Fixed Service
Structure” (EA. C-2, C-3; Tr. 36, 255). The conditions on that day heightened the
potential for a fall into blast holes on the MLP.
Camera boxes B-13 and B-16 angled beside the northernmost comers of the main
engine blast hole, one on the east side and one on the west. Each was within 6 feet of the
90-to 950footdrop. Camera boxes O-1 and O-4 were located near the inside comers of each
solid rocket blast hole on a ledge formed between them and the main engine blast hole.
Employees were no more than 6 feet from the blast hole edges when they reached these
cameras (Exhs. C-3, C-4; Tr. SO).”
On June 25 and July 31,1992, one of two CSR employees opened the camera boxes
by unscrewing eight bolts and laying open the box door (Tr. 290, 296). CSR employees
routinely used safety belts or harnesses with double lanyards to provide fall protection after
they reached the camera boxes on the MLP (Tr. 299). Thus, the Secretary’s charge covers
the time during which employees approached the camera boxes before they tied o&
Although CSR employees testified that by June 25, 1992, B-13 and B-16 had been
removed from service, these camera boxes remain at issue because of the way employees
approached boxes O-1 and O-4 (Tr. 317, 367). On June 25, CSR employees walked
alongside a large pipe which “cuts off’ behind B-13 and B-16 (Tr. 322). They then crossed
under the pipe so that they could tie off to B-13 or B-16. Having connected to that camera
box, employees were protected while approaching O-1 or O-4, where they tied their second
lanyard. The employees then released the B-13 or B-16 lanyard, completed their work at
O-1 or O-4, and reversed the process in leaving the area (Tr. 322,323).
Since employees were tied off while approaching the more precarious positions at O-1
or O-4, they were not exposed as they serviced those cameras. In approaching B-13 or B-16,
however, CSR employees came within 6 feet of the blast hole edge and were in the zone of
6 Yarbrough measured the distance from the nearest edge of the blast hole to the eye of the camera box,
which was the tiedown point. He included in his measurement the length that his arm could extend while
he reached for the eye of the camera box (‘I?. 44).
6
danger on that date. The fact that there was a pipe along a portion of the approach route
may have lessened the extent of the exposure, but it did not negate it. See Hamilton Fixture,
16 BNA OSHC 1073, 1094, 1993 CCH OSHD Ii 30,034 at p. 41,189 (No. 884720,
1993)(short duration of exposure is no defense against evidence of a violation).
Knowledge
CSR’s supervisor was on the MLP and had obsemed substantially identical work for
four years (Tr. 360). He had knowledge of the work practices which resulted in exposure.
His knowledge is imputed to CSR. See e.g., Gary Concrete, 15 BNA OSHC 1054,
1991-93 CCH OSHD 1 29,344 (No. 861087, 1991).
CS.‘s MidKEmplbyet Defense
CSR asserts that under the precedent of the An&g-JO~~~O~/GIXISVM82 rule,’ it
established the multi-employer worksite defense. 8 That defense requires an employer, who
did not create or control the violative condition, to establish that alternative protective
measures were used or were unavailable. The burden of establishing each element of the
defense rests with the employer. See Seibel Mb&LMfg.& Welding Cop, 15 BNA
OSHC 1214 1991 CCH OSHD 1 29,442 (No. 88-821, 1991).
The Secretary suggests that the relationship of NASA to CSR is best analogized to
that of a general contractor to its subcontractor on any multi-employer worksite. To the
extent the analogy applies, it is with a significant caveat. The “general contractor” was
NASA NASA is responsible for launches of the nation’s space shuttle, an achievement of
monumental technical complexity. NASA asserts control over the precise timing and
detailed sequencing of the myriad activities needed to launch and land the shuttle. This is
especially true for the work on the MU? immediately before and after the launch. NASA
strictly enfofces what items can be taken onto the MU? and what activities can be performed
’ Arming-JohnsonCo., 4 BNA OSHC 1193,1975-76 CCH OSHD ll20,69Q (No. 3694,1976);-Grossman Steel
& AIuntinwn Cop., 4 BNA OSHC 1185,1975-76 CCH OSHD ll20,691 (No. 12775, 1976).
’ Although the Arming Johnso~~lcrossmm rule pertains to construction, it can be applicable in this general
industry case because the fact situation presepts such unusual similarities to construction worksites.
7
there. NASA monitors all post-launch operations on the MLP via consoles. Further, NASA
has evidenced its overall concern for safety. It employs safety professionals throughout KSC
and has implemented specific safety rules.
NASA’stechnical or safety expertise may logically impart a degree of confidence that
when NASA kquired its contractors to perform activities on the MLP immediately after the
launch, it was necessary that the task be performed at that time. It might also be inferred
that NASA had considered safety when the task was assigned.
That assumption may have been bolstered by the fact that NASA previously delayed
film retrieval to coincide with the guardrail installation (Tr. 388). However, the timing of
the film retrieval was changed so that NASA could get a “quick look” at the launch film
(Tr. 368-369). Likewise, although Lockheed had earlier suggested that permanent,
survivable guardrails be installed around the perimeter of the MLP, NASA rejected the
proposal (Tr. 151). NASA’s motives in failing to develop launch-survivable guardrails or in
changing the sequence of the f3lm retrieval may not have been known to CSR, but it
reasonably may have assumed that the decisions reflected necessity. Nevertheless, even
recognizingNASA’sunique .status, NASA’s contractors were not completely relieved of their
obligation to protect their own employees on the MLP.
CSR did not create or control the hazani. NASA built the MLP. It established the
time sequence under which guardrails were to be removed or reinstalled and when the film
was to be retrieved (Tr. 376378). CSR lacked authority or expertise to abate the violation
by covering or guarding the flame holes. Such activity would be contrary to NASA’s master
sequencing plan. Further, extraneous materials could damage the shuttle and were not
allowed on the MU?.
CSR’S Altemative Me-B. Did CSR undertake realistic alternative measures to
protect its employees from the hazard? Realistic measures m be less than fUl compliance
because “[wlhat is realistic depends upon a balance of the hazard involved with
considerations of efficiency, ecunomy, and equity.” Hayden Ekcbik Sam, 4 BNA
OSHC 1494, 1495, 1976-77 CCH OSHD B 20,939, p. 25,149 (No. 4034, 1976). Although
perhaps an employer could have done more, the conduct must be viewed in its totality and
in terms of “whether a reasonable employer would have done more” under the
8
circumstances. Capfonn, Inc., 16 BNA OSHC 2040 (No. 91-1613, 1994), citing Hectic
Smith, Inc. v. Secretaryof Labor, 666 F.2d 1267, 1273-74 (9th Cir. 1982).
CSR employees received training in the use of safety belts and lanyards (Tr. 300-301).
CSR had a safety program which enforced the use of safety belts and lanyards on the MLP,
although they were used after employees reached the camera boxes (Tr. 415). New
employees toured the h&P with their supervisors and were instructed on potential hazards
before they were allowed to work on the structure @xhs. R-4, Rd; Tr. 300, 361-364).
I&W& Reel. CSR used a self-retracting, inertia reel on September 12, 1992. Thus,
OSHA did not allege that a violation occurred on that date (Tr. 98). However, CSR did not
again use inertia reels, claiming their use was unacceptable on the MLP. Lowell Jones,
CSR’s expert witness, contended that since there was no way for inertia reels to be attached
overhead (without hardware--which CSR could not construct on the ALP), they were not
effective or safe. The Secretary did not seriously assert that inertia reels should be used on
the MLP. Although CSR did not consider use of an inertia reel before the September
launch, it was not required to utilize ineffective measures.
As noted, NASA’s overriding technical superiority and its reputation for safety
affected what CSR reasonably must do to challenge a procedure. Balancing the degree of
the hazard with the measures used to lessen the danger, CSR exercised reasonable care and
diligence and undertook appropriate realistic alternative measures to protect its employees.
CSR has established its defense. The alleged violation of 5 1910.22(c) is vacated.
ITEM 2: 8 1910.23(c)(l)-Perimeter Falls
The Secretary charges that the unguarded perimeter exposed CSR employees to a
fall hazard in violation of 8 1910.23(c)(l)?
g The standard pravides:
0 191023(c). Protection of opendedj7oom~ pl~tjiorms, andnmwap. (1) Everyopen-sided
floor or platform 4 feet or more above adjacent floor or ground level shall be guarded by a
standard railing (or the equivalent as specified in paragraph (e)(3) of this section) on all open
sides except where there is entrance to a ramp, stainway, or fixed ladder. . . .
9
Applicability of 8 1910.23(c)(l) .
CSR argues that 8 1910.23(c)(l) does not apply. Since the MLP has two interior
levels and its zero level deck is open to the sky, CSR contends the zero level deck is a roof.
The Secretary maintains that the zero level deck is a work platform. Whether the cited
surface is a platform within the meaning of the standard is a question of fact. Unatr=o
Commetcr’al Abducts, 16 BNA OSHC 1499, 1502, 1993 CCH OSHD B 30,294, p. 41,731
(No. 89-1555, 1993).
A “platform” is defined in 0 1910.21(a)(4) as:
(4) A working space for persons, elevated above the surrounding floor
or ground; such as a balcony or platform for the operation of
machinery and equipment.
CSR relies on Arkan.susRke Growers Coop., 10 BNA OSHC 1616, 1982 CCH
OSHD ll 26,049 (No. 77-3974, 1982), for the proposition that a “roof’ is not transformed
into a “floor” or “platform” merely because machinery is used or work is performed on ito
However, unlike Arkansas Growers,where the uppermost surface was both a roof and a
walkin@orking surface, the zero level deck of the MLP is only a working surface. A “roof’
is defined hAtirz.sus Growersas “a covering to protect against the weather and to complete
the building.” Id, 10 BNA OSHC at 1620, 1982 CCH OSHD li 26,049 at p. 32,724. The
W, on the other hand, is a unique structure built to launch spacecraft. Even though the
h&P has interior levels, its uppermost surface serves as the working and staging area. Its
purpose is not to cover or protect the interior levels. The interior levels only incidentally
facilitate the primary work activity taking place at the surface. The zero level deck is an
elevated workspace and meets the definition of “platform” in the standard.
Camera boxes Gl, L-4, L5 and IX are angled diagonaIly at the four cornen of the
zero level deck Boxes C2 and L3 are located midway along its east perimeter side.
Additionally, the Secretary alleges that when CSR employees crossed over the ramp between
10
the zero level deck and the Fixed Surface Stnrcture, they were necessarily within the zone
of danger of a perimeter fall.
Yarbrough measured the distances for the perimeter camera boxes and concluded
that employees would have been within 6 feet of a perimeter fall by the time they tied off
at the camera boxes (Tr. 44, 47). The distances were also measured by Hodge and
Liford0lo The distances Hodge measured from the tie-off point at the eyebolt of the
camera box to the perimeter edge were (Tr. 315-316):
L-l 64 inches (5 feet, 4 inches)
L2 83 inches (6 feet, 11 inches)
L-3 70 inches (5 feet, 10 inches)
L4 54 inches (4 feet, 6 inches)
L5 62 inches (5 feet, 2 inches)
L6 64 inches (5 feet, 4 inches)
Some additional distance can also be implied from the fact that employees reached
forward to tie the lanyard to the eyebolt. This distance would vary and would not be
significant for all camera boxes.l1 Given the conditions existing on the zero level deck
during film retrieval on June 25, 1992, CSR employees were exposed to a zone of danger
while they approached the perimeter camera boxes. They were also exposed to an
unprotected perimeter fall as they stepped off the ramp.
CSR’SM&i~Employer Defense
For generally the same reasons discussed above, however, CSR meets its multi-
employer defense for both the perimeter cameras and for the perimeter exposure which
existed near the ramp. Although employees were exposed, the reasonableness of alternative
I* Liford was a confused witness, both vague and uncertain in his testimony. His testimony is accorded little
CredibilitjC
I1 CSR argues that an additional 2 fet (arm’s length from the eyebolt) must be added to each mwurement
to account for the employee’s reach as he tied off to the eyebolt. Where camera boxes and qtebbolts are
positionedat different angles (some facing forward and some away), however, it is not reasonable to assume
that employees would extend their arms in some rigid posture as they approached the camera box
11
protection is weighed against the lessened degree of exposure. Thus, the distances from the
edges which employees maintained as they approached the cameras, the employees’ training,
and their use of safety belts and lanyards have been considered. Employees could use safety
belts as they began work on the cameras, but such alternative protection was impossl%le
when they walked off the ramp. At the perimeter near the ramp, only guardrails could
abate the hazard. CSR could not install them. In light of the previous discussion of NASA’s
status, CSR utilized reasonable alternative measures in both alleged instances. CSR
established its defense.
The violation is vacated.
ITEM 3: Alleged Violation of 9 1910.23(c)(2)
After each launch, the Fixed Surface Structure was moved back beside the MLP.
A ramp was lowered connecting the two structures. The ramp was only partially protected
by guardrails. In preparation for the OSHA inspection on September 11, 1992, the
compliance officer went to KSC and advised that the unguarded gap in the accessway
guardrails presented a hazard. By the September 12 launch, an additional railing had been
clamped over the guardrail opening, abating the hazard (I%. C-l; Tr. 34). Alleging that
the ramp guardrail gap existed during the June 25, 1992, and July 31, 1992 launches, the
Secretary charged a violation of 0 1910.23(c)(2).‘2
CSR employees were exposed to a fall of 45 feet from the unguarded portion of the
ramp as they walked to the MLJ? during the two launches.*3 A fall would almost surely
result in death. The existence of the gap was easily observable. CSR supervisor Elrod
himself crossed the ramp on both launch dates.
I2 The standard requires:
1
51910.23(c) RO~&OIZof open-skkdjZcw, pkiz$bm, und nutways. (2) Every runway shall
be guarded by a standard railing (or the equivalent as specified in paragraph (e)(3) of this
section) on all open sides 4 feet or more above floor or ground kveL
l3 The opinion of CSR’s expert witness, Jones, that employees were not in a zone of danger as they crossed
this rampis contradicted by common sense.
12
CSR’S iUulti~EmployerDefense
It is unclear whether CSR asserts the multi-employer worksite defense for this item.
To the extent that it does, the defense is not met. These circumstances are unlike those
which existed for the blast holes and for the perimeter hazards. Both of those latter
conditions existed on the tightly controlled zero level deck of the MLP, and abatement
involved obvious logistical and technological problems. The fall hazard on the ramp, on the
other hand, could easily be evaluated and remedied, as it was, by clamping on an additional
railing. It was also a more immediate hazard. Even if CSR would be required to secure
NASA’s agreement, abatement could have been technically accomplished by CSR itself.
Also, unlike suggested abatement on the zero level deck, NASA predictably would not
object. Only the post-launch access from the Fixed Surface Structure was at issue, not
concerns for eliminating potential harm to the shuttle launch. NASA’s “quick look” at the
film taken of the launches would not be delayed. CSR dib not seek or utilize alternative
protection for its employees. CSR failed to seek permission to abate the violation or even
to request abatement Tom NASA. This failure was not reasonable. The multi-employer
defense is not met for this violation.
The violation is affirmed as serious.
Penalty
The Commission and its judges have final authority to assess penalties in all contested
cases. Hem Iron Woks, Inc., 16 BNA OSHC 1619, 1621-23, 1994 CCH OSHD ll 30,363,
p. 41,881-83 (No. 88-1962, 1994). It must give “due consideration” to the size of the
employer’s business, the gravity of the violation, the good faith of the employer, and the
history of previous violations in determining the appropriate penalty. JA. Jones Constr. Co,
15 BNA OSHC 2201, 2213-14, 1993 CCH OSHD II 29,964, p. 41,032 (No. 87-2059, 1993).
These factors are not necessarily accorded equal weight. The gravity of the violation is the
primary element in the penalty assessment. Ttitity Ikch.s., 15 BNA OSHC 1481, 1483,
1992 CCH OSHD ll29,582, p. 40,033 (No. 88-691, 1992).
CSR is a joint venture partnership between two major corporations, Computer
Sciences Corp., and Raytheon Service Corp. (Respnt.‘s Motion For Additional Time to
13
Answer Complt.). The undersigned takes official notice that each of these corporations has
tens of thousands of employees. The number of persons employed by CSR itself is
unknown. Yarbrough knew only that it had more than 251 employees (Tr. 64). As to its
history of previous violations, Yarbrough reviewed a computer scan of the company’s OSHA
history and allowed no credit for past history. However, he did not know if the data
established that CSR had previous serious violations (Tr. 64,65,84). CSR’s safety manager
testified that CSR had never before received an OSHA citation (Tr. 428). CSR’s testimony
is credited.
Two technicians and a supervisor crossed the ramp and were briefly exposed to a
45foot fall. Employees were within 2 feet of two unguarded edges as they carried light tools
and safety equipment across the ramp. Considerations of the gravity of the violation also
include the fact that no real precautions were taken against injury. Also, while the likelihood
of a fall was moderate, the likelihood that a fall would result in death was high.
Weighing toward a finding of good faith is CSR’s written safety and health program.
Further, the asserted violation was abated even before the physical inspection was conducted
(Tr. 405410).
Having considered the above, a penalty of $1,000 is assessed.
FINDINGS OF FACT AND CONCLUSIONS OF LAW
The foregoing decision constitutes the findings of fact and conclusions of law in
accordance with Federal Rule of Civil Procedure 52(a).
ORDER
Based on the foregoing decision, it is ORDERED:
(1) Item 1, alleging a violation of 3 1910.22(c), is vacated.
(2) Item 2, alleging a violation of 5 1910.23(c)(l), is vacated.
(3) Item 3, alleging a violation of 5 1910.23(c)(2), is affirmed as serious and a
penalty of $1,000 is assessed.
Is/ Nancy J. Spies
NANCY J, SPIES
Date: November 28, 1994 Judge
14
Get today's answer for your situation
You just read what one judge decided for one employer in 1995, and it binds only those parties. Ezel checks the current OSHA standards and Commission precedent and answers your specific situation, with citations.
Opens in Ezel Pro. Every answer cites the authority it relies on.