OSHRC ALJ decision Docket 92-2235 Decided July 12, 1993 Citations affirmed Judge John H. Frye III

Supermason Enterprises

Willful unprotected-trench violation affirmed

Apply this to your situation

This order from 1993 bound only the parties to this case; it isn't precedent. Ezel answers your situation under the current OSHA standards and Commission precedent, with citations.

Currency note: this decision dates from 1993
The OSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Final order, not Commission precedent
This decision by an OSHRC Administrative Law Judge became a final order of the Commission because no Commissioner directed review (29 U.S.C. § 661(j)). It binds the parties but is not binding precedent in other cases. The full text below is from the official OSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official OSHRC release. The full text is the Commission's own document.
Read the official release (oshrc.gov)

Plain-English summary

Supermason Enterprises installed a sanitary sewer in Pen Argyl, Pennsylvania, with two workers in an excavation eight to ten feet deep. The ALJ rejected the company's claim that the workers belonged to a subcontractor because the supposed agreement was unsigned, the alleged subcontractor had never seen it, and Supermason paid the workers hourly wages. The trench had no ladder, no competent-person inspection, no adequate employee training, and no cave-in protection. The judge affirmed those three serious items together with a $1,000 penalty. He classified the protective-system violation as willful because the contract and preconstruction meeting made Supermason responsible for federal safety compliance, yet its foreman disclaimed responsibility and no shoring equipment was present. That item carried a $7,000 penalty. Three other-than-serious hazard-communication items involving possible methane and hydrogen-sulfide exposure were affirmed without penalty, for a total penalty of $8,000.

Decision snapshot

  • Cited standard(s): 29 C.F.R. §§ 1926.59(e)(1), 1926.59(g)(1), 1926.59(h)(1), 1926.651(c)(2), 1926.651(k)(1), 1926.21(b)(2), and 1926.652(a)(1)
  • Outcome: All cited items were affirmed, including a willful cave-in-protection item; total penalties were $8,000.
  • Key point: A contractor cannot avoid OSHA responsibility through an unsupported subcontractor claim or by relying solely on workers' prior experience instead of providing competent supervision and site-specific training.

Full text (OSHRC public release)

OCCUPATIONAL SAF%%%Ei~~ii?kW Commission
One Lafayette Cents
1120 20th Street, N.W. - 9th Floor
I
--. Washington, DC 200364419
?.
f-4..

SECRETARY OF LABOR
Complainant,
v. OSHRC DOCKET
NO. 92-2235
SUPERMASON ENTERPRISES
Respondent.

                               NOTICE OF DOCKETING
                        OF ADMINISTRATIVE LAW JUDGE’S DECISION
The Administrative Law Judge’s Report in the above referenced case was

docketed with the Commission on June 11, 1993. The decision of the Judge
will become a final order of the Commissron on July 12, 1993 unless a
Commission member directs review of the decision on or before that date. ANY
PARTY DESIRING REVIEW OF THE JUDGES DECISION BY THE
COMMISSION MUST FILE A PETITION FOR DISCRETIONARY REVIEW.
Any such etition should be received by the Executive Secretary on or before
July 1 1983 m
’ order to permit sufficient time for its review. See
Com&sion Rule 91, 29 C.F.R. 2200.91.

All further pleadings or communications regarding this case shall be
addressed to:
Executive Secretary
Occupational Safety and Health
Review Commission
1120 20th St. N.W., Suite 980
Washington, D.C. 20036-3419
Petitioning parties shall also mail a copy to:

                    ,
                              Daniel J. Mick, Esq.
                              Counsel for Regional Trial Liti ation
                              Office of the Solicitor, U.S. DOgL
                              Room S4004
                              200 Constitution Avenue, N.W.
                              Washington, D.C. 20210

If a Direction for Review is issued by the Commission, then the Counsel for
Regional Trial Litigation will represent the Department of Labor. Any party
having questions about review rights may contact the Commission’s Executive
Secretary or call (202) 606-5400.
E COMMISSION

Date: June 11, 1993 Ray H. Darling, Jr.
Executive Secretary
DOCKET NO. 92-2235
NOTICE IS GIVEN TO THE FOLLOWING:

Daniel J. Mi4 ES&
Counsel for Re bud Trial Liti ation
Office of the SoT ‘&or, U.S. DOt&
Room S4004
200 Constitution Ave., N.W.
Washington, D.C. 20210

Marshall H. Harris, Esq.
Re ‘onal Solicitor
O&e of the Solicitor U.S. DOL
14480 Gatewa Building
3535 Market Htreet
Philadelphia, PA 19104

Toni E. Lynch, CEO
Su ermason Enterprises, Inc.
P.8. Box 533
Portland, PA 18351

John H. Frye, III
Administrative Law Jud e
Occupational Safety an (KHealth
Review Commission
One Lafayette Centre
1120 20th St. N.W., Suite 990
Washington, DC 20036 3419

00102934494:03
OCCUPATIONAL SAF~~?4iiEb~ii:%“IEW COhdMiSSION
One Lafayette Centfe
1120 20th Street, N.Wm- Qth Floor
Washington, DC 200363419

                                                      ..
                                                       ..

SECRETARY OF LABOR,
..

    Complainant,                                       ..
                                                      ..
                                                       ..
            v.                                                 Docket No. 92-2235
                                                      .
                                                      l

SUPERMASON ENTERPRISES, INC. ..
.
0

    Respondent.                       *

Appearances:

    Theresa Ce Timlin                             Toni E Lynch pm se
    Joseph Crawford                                    CEO
            Office of the Solicitor                    Supermason Enterprises
            U.S. Department of Labor                   Portland, Pennsylvania
            Philadelphia, Pennsylvania
            For Complainant                                 For Respondent

BEFORE: Administrative Law Judge John H Frye, III

    After receiving information           that workers were employed in an unprotected      trench,

OSHA inspected Sup&mason Enterprises’ work site in Pen Argyl, Pennsylvania, on May 6,
1992. As a result of this inspection, OSHA issued two serious and one willful citations to
Respondent Super-mason Enterprises which the latter contested. At the hearing, one of the
serious citations was reclassified as other than serious and the monetary penalty reduced to
$00 .
me hearing was held in Allentown, Pennsylvania, on January 19, 1993. In lieu of
closing argumentrs, th+ parties were directed to submit briefs. The Secretary of Labor
submitted a Pa Hearing Brief consisting of Proposed Findings of Fact, Conclusions of Law,
and Argument. The Respondent did not submit a brief. Consequently, this Decision and
Order is based largely on the Secretary’s brief.
Ia OPINION
A Complainant is an Employer Engaged in a Business Affecting Commerce and
is Therefore Subject to Jurisdiction Under the Act.

   Respondent’s      principal    defense      to the citations   is that it is not subject to the

requirements of the Occupational Safety and Health Act (Act) because it had subcontracted

out the job and had no employees working on the site at the time of the inspection. The

Act provides in pertinent part that the term “employer” means “one or more individuals,

partnerships, associations, corporations, business trusts, legal representatives, or any

organized group of persons engaged in a business affecting interstate commerce who has

employees.” 29 U.S.C. 5 652(4) and (5). An “employee” is “an employee of an employer

who is employed in a business of his employer which affects commerce.” 29 U.S.C. 0 652(6).

    In. this case, the weight of the evidence reflected in Findings Dl through D5 clearly

indicates that Respondent is an employer subject to the jurisdiction of the Act. The only

evidence which supports Respondent’s defense that it had subcontracted out the project is
l

an unsigned contract between Respondent and C & S Contracting, a company owned by

Kevin Corrigan. Mr. Corrigan testified not only that he had not signed this document, but

that he had never before even seen it. The evidence clearly establishes that at the time of

the inspection Respondent was paying Mr. Corrigan and Richard Schwind an hourly wage

as laborers.
There is also no real dispute that Respondent was engaged in a business affecting

commerce within Section 3(5) of the Act. Inspector Stelmack testified that he observed a

&se backhoe, manufactured in Racine, Wisconsin, which had been utilized to carry out the

excavation project. See Finding Fl. It is clear that Respondent is an employer engaged in

a business affecting commerce within Section 3(5) of the Act, and that I have jurisdiction

over the proceedings.

   Ba     Complainant Sustained Her Burden of Proving That Respondent         Violated 29
          C.F.R. 50 192659(e)(l), 192659(g)( 1) and 1926.59(h)

   To establish a violation of a standard, Complainant   must show that “(1) the standard

applies to the cited condition; (2) the employer violated the terms of the standard; (3). its

employees were exposed or had access to the violative conditions; and (4) the employer had

actual or constructive knowledge of the violation.” Secretary of Labor v. Sal Masonry

ContractorsInc., 15 BNA OSHC 1609, 1610 (Rev. Comm. 1992).

           1.29 C.F.R. SS 1926.59(e)f 1). 192659(g)(l)   and 1926.59(h) applv to the cited
              condition

   Section 1926.59(e)(l)   provides, in pertinent part, that

          employers shall develop, implement, and maintain at the workplace, a written
          hazard communication program for their workplaces which at least describes
          how the criteria specified in paragraphs (f), (g) and (h) of this section for
          labels and other forms of warning, material safety data sheets, and employee
          information and training will be met . . . .

   Section 1926.59(g)( 1) provides that

          employers shall have a material safety data sheet for each hazardous chemical
          which they use.

   Section 192659(h)( 1) states that




                                           3

employers shall provide employees with information and training on hazardous
chemicals in their work area at the time of their initial assignment, and
&never a new h-d is introduced into their work area.

    According      to Inspector   Stelmack,    a written       hazard    communication      program   is

“basically an overview of all requirements of the standard and how the employer will

implement the standard on site.” (Tr. 39). An emnlover a 4
is required to have a written

hazard communication program whenever there is possible exposure to hazardous materials

at the work site. (Tr. 41). Likewise, whenever there is possible exposure to hazardous

materials at a work site, the employer must have material safety data sheets available and

must provide employees with information and training about the hazardous substances.

    Findings Fl through F3 indicate that Respondent’s employees were in the process of

installing a drop connection to an existing sanitary sewer manhole. Live lines which could

generate sewer gasses, in particular methane and hydrogen sulfide, ran out of the manhole.

Because the employees were potentially exposed to hazardous sewer gasses at the work site,

50 1926.59(e)(l), 1926.59(g)( 1) and 1926.59(h) apply.

            2. ResDondent violated the terms of the cited standards.

    Respondent       did not rebut Inspector     Stelmack’s testimony           that a written hazard

communication program and Material Safety Data Sheets were not available at the work

site. Respondent’s position, expressed to Inspector Stelmack, that it only hired people

experienced in trenching operations, does not comply with the terms of the standard, which

requires training upon initial employment and whenever a new hazard is introduced to the

work area.
30 esr>ondent’s emDlovees were exDosed to the violative conditions

    Respondent’s      employees working in a trench with live sewer lines could have been

exposed to sewer gasses such as methane and hydrogen sulfide, and consequently to the

danger of an explosion or oxygen displacement in the trench. Without a written hazard

communication program or material data sheets at the workplace, and without receiving

training regarding hazardous chemicals, the employees were uninformed about the dangers

of methane and hydrogen sulfide, and how to protect themselves from those dangers.

             4. ResDondent had actual or constructive knowledge of the violations

    Finding F3c reflects the fact that Respondent       was aware of the lack of a hazard

communication
I program, Material Safety ‘Data Sheets, and a training program, and that

Respondent previously had been cited for violation of the same standards. Respondent’s

position that the previous citations involved entirely different hazards does not alter the fact

that Respondent knew of the requirements of these standards and should have applied them

to the hazards presented by the work in which it was engaged. Complainant has established

violations of the cited standards that were properly characterized as other-than-serious

violations.
Ca Complainant Sustained Her Burden of Proving That
Respondent Violated 29 C.F.R. !$ 1926.65 l(c)(2)

             l&al
              f       ‘on 1926.651(c)(2) applies to the cited condition. Respondent violated
                jts terms, Respondent’s emplovees were exposed or had access to the
                violation, and Respondent had actual or constructive knowledge of the
                violation.

      Section 1926.651(c)(2), provides that

             a stairway, ladder, ramp or other safe means of egress shall be located in
             trench excavations that are 4 feet (1.22 m) or more in depth SO as to require
             no more than 25 feet (7.62 m) of lateral travel for employees.

The trench in which Respondent’s employees were working was 14 feet long, eight feet wide,

10 feet deep nearest the manhole, and eight feet deep at its shallowest point. Finding F4.

Thus, the standard applies to Respondent’s trench.

      When Inspector Stelmack arrived at the work site, two of Respondent’s employees

were working in the trench. There was no ladder or other safe means of egress fkom the

trench. Findings Fl and F9. Without a ladder or other safe means of egress from the

trench, the employees would not have been able to exit the trench rapidly in the event of

an emergency, such as a sidewall failure.

      It is clear that Respondent     had knowledge of the lack of safe egress from the trench

because one of the employees in the trench was Respondent’s foreman. Findings D4 and

Fl. Complainant has established a violation of 651(c)(2).

             2. Complainant       established that the violation of 651(c)(2) was properlv
                characterized     as a serious violation

      “Under Commission         precedent,   a serious violation is established    if an accident is

possible and there is a substantial probability that death or serious physical harm could result

from the accident.” Secretary of Labor v. ConsolidatedFreightwaysCop., 15 BNA OSHC

                                                 6

1317, 1324 (Rev. Chm. 1991) citing D~ZW cop., 7 BNA OSHC 2095, 2101, 1980 CCH

OSHD 124,154 p 29,370 (No. 16317, 1980),pet. for review denied, 639 F.2d 772 [9 OSHC

21441 (3d Cir. 1980). See aho 29 U.S.C. 0 666(k). In the event of an emergency, such as

a sidewall failure, employees would be unable to rapidly exit the trench. Inspector

Stelmack’s testimony that the most likely injury in the event of a trench collapse would be

death was unrebutted. Findings F9 and F12. This evidence establishes a serious violation.

          3. ResDondent has failed to Drove anv defense to the violation

  At trial, Respondent attempted to establish an infeasibility defense through his cross-

examination of Inspector Stelmack and through his own testimony that it was necessq to

remove the ladder from the trench as the trench dimensions were tight and the men would

have been unable to work with the ladder in place. (Tr. 107-111, 132). In order to prevail

on this defense, Respondent must prove that “(1) literal compliance with the terms of the

cited standard was infeasible under the existing circumstances and (2) an alternative

protective measure was used or there was no feasible alternative measure.” Secretary of

Labor v. Mosser Construction Company, 15 BNA OSHC 1408, 1416 (Rev. Comm. 1991),

citing Seibel M&em Mfg. & Welding Cop., 15 BNA OSHC 1218, 1226, 1228, 1981 CCH

OSHD ll 29,442, p. 39,678, 39,682,39,685 (Commission 1991). “Employers must alter their

customary work practices to the extent that alterations are reasonably necessary to

accommodate the abatement measures specified by OSHA standards.” Seibel, 15 BNA

OSHC at 1227.

   Respondent did not prove that literal compliance with the terms of 651(c)(2) was

infeasible at the time of the inspection, either through cross-examination of Inspector

                                         7

Stehack, or through Mr. Lynch’s own direct testimony. (Tr. 107~111, 132). Respondent

seemed to be arguing that it could not comply with 651(c)(2) by keeping the ladder in the

trench and still accomplish its job. This argument is not persuasive. The standard requires

that a safe means of egress be provided from a trench excavation that is more than four feet

deep. Respondent did not show that literal compliance with 651(c)(2) was infeasl’ble. The

mere suggestion that compliance would have made the laborer’s job harder does not

establish infeas~bility.

    The second element of the infeasibility defense requires Respondent to prove that

it either used an alternative means of protecting the laborer, or that no alternative means

existed. On cross-examination, Inspector Stelmack stated that the ladder should have been

moved to a location in the trench where it would have been out of the way of the work area,

but still located so that employees would not have to travel more than 25 feet to reach it.

(Tr. 109). Respondent did not present any evidence showing that this means of complying

with the standard was infeasible.

    For the foregoing reasons, Respondent     did not establish the infeasibility defense.

    D.      Complainant Sustained Her Burden of Proving That Respondent          Violated 29
            C.F.R. 5 1926.65 l(k)( 1)

            1. Section 1926.651(k)(l)   applies to the cited condition

    Section 192665l(k)( 1) p rovides in pertinent part, that

            [d]aily inspections  of excavations, the adjacent areas, and
            protective systems shall be made by a competent person for
            evidence of a situation that could result in possible cave-ins,
            indications  of failure of protective     systems, hazardous
            atmospheres, or other hazardous conditions.     An inspection
            shall be conducted by the competent person prior to the start
            of work and as needed throughout the shift. . .l

2g C.F.R 5 1926.651(k)(1). The standard apphes as employees. were working in a trench.
.

29 C.F.R 8 1=6%I(a).

          2. Respondent violated the terms of 65 l(k)(l). Respondent’s emplovees were
             emsed or had access to the violation. and Respondent had actual or
             constructive knowledge of the violation of 65l(k)(l\

   On obsenring Respondent’s employees working in an unprotected trench, Inspector

Stelmack interviewed Respondent’s foreman, Mr. Cotigan, at the work site. Despite his

substantial experience as an excavation contractor and his position as foreman, Mr. Corrigan

stated that not only was he unfamiliar with the OSHA trenching regulations, he was not

responsible for employee safety and health and that he was not sure that anyone was.

Finding FlO. Mr. Corrigan has denied that he was the person responsible for employee

safety, and . Respondent has not suggested that any other individual was responsr%le.

Complainant has established a serious violation of 9 1926.651(k)(1).

   E.     Complainant Sustained Her Burden of Proving That Respondent Violated 29
          C.F.R. 0 1926.21(b)(2)

          1. Section 1926.21(b)(2) applies to the cited condition.

   Section 1926,21(b)(2) provides that

          [t]he employer shall instruct each employee in the recognition and avoidance
          of unsafe conditions and the regulations applicable to his work environment
          to control or eliminate any hazards or other exposure to illness or injury.

This general training standard applies to all construction sites covered under the Act.

Because Respondent is a covered employee under the OSHA Act, 21(b)(2) applies.
QEDosed or had access to the violation, and Resnondent had actual or
mm&e knowledge of the violation.

   Iqectcx      Stelmack determined that Respondent violated the terms of 21(b)(2) when

Mr. Corrigan stated that he was not familiar with the OSHA trenching regulations. Finding

FlO. At the hearing, Respondent seemed to believe that by hiring employees who had

trenching experience, he fulfilled his responsibilities with respect to training. However, the

law is clear that training by former employers does not fulfill the requirements of 21(b)(2).

Ford Development Co., 15 BNA OSHC 2003,2009 (Rev. Comm. 1992) (Serious citation for

violation of 29 C.F.R. 3 1926.21(b)(2) upheld where company failed to provide its foreman

with adequate training in excavation hazards, relying on the foreman’s on-the-job training

with a previous employer). “Each worksite presents a different work environment posing

its own specific set of safety considerations.” Siegel Interior SpecialistsCo., 15 BNA OSHC

1665, 1666 (ALJ 1992) (serious violation of 29 C.F.R. 5 1926.21(b)(2) affirmed).

Complainant has established a serious violation of 21(b)(2).

             3. Comnlainant established that the DroPer nenaltv was assessed for items 2a,
                2b, and 2c of serious citation no. 1

   The Secretary grouped the penalty for these items because of the similarity in the

nature of the violations. (Tr. 67). Inspector Stelmack testified that the first step in assessing

a penalty is assigning a value for the severity of the injury to be expected and a value for the

probability of injury. (Tr. 68). These violations were classified as high severity because the

resulting injury could be death. Findings F9 and F12. Inspector Stelmack, however, assessed

the probability of injury as lesser, because when he observed the trench and trench sidewalls

he did not notice any materials spalling from the sidewalls, any visible tension cracks or

                                                 10

fissures &ng the excavation face, or any water either in the trench or seeping from the

sidewalls. Fiiii F8 The gravity-based penalty for a high severity/lesser probability injury

is $2,500. (Tr. 69).

   The $2,500 penalty was then reduced by 60% because of the small size of

Respondent’s company. (Tr. 69-70). No other adjustments were made. The final

recommended penalty was $l,OOO.OO. Inspector Stelmack’s testimony regarding the

assessment of the penalty for these items was not rebutted by Respondent. Accordingly, the

appropriateness of the penalty was established.

   F0      Complainant Sustained Her Burden of Proving That Respondent Violated 29.
           C.F.R. 5 1926.652(a)(1)

           1. Section 1926.652(a)(l) applies to the cited condition. Respondent m
              its terms. Respondent’s emplovees had access to the hazard. and
                 Respondent had actual or constructive notice of the hazard,

   Section 1926.652(a)( 1) provides that

   each employee in an excavation shall be protected from cave-ins by an
   adequate protective system designed in accordance with paragraph (b) or (c)
   of this section except when: (i) excavations are made entirely in stable rock;
   or (ii) excavations are less than 5 feet (1.52 m) in depth and examination 01
   the ground by a competent person provides no indication of a potential cave-
   in.

This standard clearly applies. Inspector Stelmack observed two of Respondent’s employees

working in an excavation that was made in Type B soil rather than stable rock, that was

greater than 5 feet deep, and that was not protected against cave-ins. One of the employees

was Respondent’s foreman. Findings D4, Fl, F4 through F6.

   At the hearing, Respondent suggested that given the confined space in the trench, no

protective system was available that would allow the employees to still do the work necessary

                                            11

to insa the drop connedon. Iqxxtor Stelmack testified that he believed manufactured

systems are availaMe that could have been used to shore the trench. (Tr. 114). Moreover,

Respondent’s OWIIforeman testified that speed shoring or widening the trench might have

worked as protective systems that did not interfere with the employees ability to install the

drop connection. (Tr. 157). Respondent’s suggestion appears to raise the infeasibility

defense. That defense fails here for the same reasons that it failed in connection with the

violation of 9 1926.652(c)(2). Complainant has proved a violation of 0 1926.651(a)(1).

            2. ComDlainant established that the violation of 652(a)(l) was Droperlv
               characterized as a willful violation and that the arxxoDriate Denaltv was
               assessed

      Although the term “willful“ is not defined in the statute, one accepted definition

states that a willful violation is one “involving voluntary action, done either with an

intentional disregard of, or plain indifference to, the requirements of the statute.“ I%#@-

Bicqord Co. v. OSHRC, 717 F.2d 1419, 1423 (D.C. 1983), cert. denied, 466 U.S. 937, 104

S.Ct. 1909 (1984); Georgia Elec. Co. v. Marshall, 595 F.2d 309, 319 (5th Cir. 1979); AC

Delovade, Inc., 1987 OSHD (CCH) ll 27,786 at p. 36,341 (Commission 1987); OSHA

Instruction CPL 2.45B, ch. IV, B(3)(b) (J une 15, 1989), reprinted in O.S.H. Rep. (BNA)

“Reference File“ volume 3, at 772510 and 3 Empl. Safety and Health Guide (CCH) 1

7966.290. This standard describes misconduct that is more than negligent but less than

malicious or committed with specific intent to violate the Act or a standard. E.g., Enrign-

Bicybrd Co., 717 F.2d at 1422-23, Georgia Elec. Co., 595 F.2d at 318-19.

      The Court of Appeals for the Third Circuit has held that

      willfulness connotes defiance or such a reckless disregard of consequences as to be
      equivalent to a knowing, conscious, and deliberate flaunting of the Act. Willful

                                          12

meafw L~#)TCthan merely voluntary action or omission-it involves an element of
obstimte refbsal to comply.

Frank Irey, Jr., k v. OSHRC, 519 F.2d 1200, 1207 (3d Cir. 1974), affd, 519 F.2d 1215

(1975) (en bane), affd on othergrounds sub nom. Atlas Roofing Co. v. OSHRC, 430 U.S. 442,

97 S.Ct. 1261 (1977).

   While some courts have suggested that this is a narrower             definition   of willful,

requiring a showing of “bad purpose“, the Court of Appeals for the Third Circuit has taken

the position that there is little, if any, difference between their approach in Fmnk I&y, Jr.,

Inc. and the approach of other circuits.

   To our way of thinking, an “intentional disregard of OSHA requirements” differs
   little from an “obstinate refusal to comply;” nor is there in context much to
   distinguish “defiance” from “intentional disregard.”

Babcock & WUcoxv. OSHRC, 622 F.2d 1160, 1167 (3d Cir. 1980). See aho UniversalAuto

RadiatorMfg. Co. v. Marshall, 63 1 F.2d 20, 23 (3d Cir. 1980).

    Respondent       knew of the necessity to shore or otherwise protect the employees in the

trench and refused to do so. From the time that Respondent first became invoked in

bidding for the sanitary sewerage system construction project, it was on notice that it had

sole responsibility for ensuring employee safety and that it was required to comply with all

federal safety regulations. (Tr. 20-21, 82, GX 1). Specifically, the contract directed that

“[t]he Contractor is required to do such trench bracing, sheathing, or shoring necessary to

perform and protect the excavation and as required for safety and to conform to governing

laws.” (GX 1, p. 74).

    Additionally,    during the pre-construction   conference on March 17, 1992, during the

discussion of the general project responsibilities, it was again made clear that the Contractor

                                              13

wm “r,poa~l’b~i&for compliance with all applicable federal, -state, and local laws and

Or~~CeS SlEit dldl l l . OSHA, and other safety codes.” (GX 4, p. 3). Not only were

Respc&ent’s foreman and another representative present at the pre-construction

conference, but Mr. Lynch was sent a copy of the minutes of the meeting. (Tr. 24).’

    Nonetheless,          Inspector Stelmack did not see anything on the work site which could

have been used as shoring in the trench. (Tr. 84). And when Inspector Stelmack questioned

him, Respondent’s foreman disavowed any responsibility for employee safety and indicated

that he was not aware that anyone was responsible. Finding FlO. This certainly illustrates

an “intentional disregard of OSHA requirements” which may also be characterized as an

“obstinate refusal to comply.” A contractor who permits excavation to go forward without

having both. a competent person in charge of the work and the equipment necessary to

ensure safety present repudiates its obligation for employee safety imposed by the Act?

Complainant has established a willful violation of 0 1926.652(a)(l).

    Having established the violation as willful, Inspector Stelmack also testified in detail

as to how he determined the penalty. (Tr. 91-92). The violation was classified as high

severity because the possible injury that could be expected would be death. The inspector

rated the violation as lesser probability as the trench sidewalls showed no visible signs of

imminent failure such as material spalling from the sides, tension cracks that could be

AInspector Stelmack also testified that when he spoke with the observer from G. Edwin Pidcock Co., he
learned that Respondent had been apprised of the need for shoring in the trenches. Tr. 84.

LThere is some indication in the record that Respondent may have fallen victim to a reluctance on the part
of Mr. Corrigan, an individual with substantial excavation experience, to become involved with OSHA. Tr.
159-60. However, if Mr. Corrigan was unwilling to assume that responsibility, Respondent had an obligation
to provide a competent person who would.

                                                          14

obseryed, cr&~ or fissures in the sidewalls, or water either seeping fkom the sidewalls or

smding m the trench. The gravity based penalty for a high severity/lesser probability

violation is S2JoO. (Tr. 91).

     That amount was multiplied by 7 for a total of $17,500.00 to reflect the element of

willfulness. Inspector Stelmack then gave a 60% reduction for the company’s small size,

giving a final recommended penalty of $7,000.00. (Tr. 91). No adjustments for good faith

or history are given when a violation is classified as willful. (Tr. 92). The Inspector’s

testimony regarding the factors used to determine an appropriate penalty was not rebutted

by Respondent. Accordingly, the appropriateness of the penalty was also established.

II l FINDINGS OF FACT

     A       Respondent, Supermason Enterprises, is a corporation with a principal place

of business at Box 533, Portland, Pennsylvania. (Complaint, ll 1).

     B.      In May of 1992 Respondent was engaged in excavation work at Bayberry and

Crestmont Streets, Pen Argyl, Pennsylvania. (Tr. 33-34). The construction project involved

the installation of a sanitary sewer. (Tr. 33).

     C. G. Edwin Pidcock & Company was engaged by Plainfield Township to oversee

the design and construction of the Bayberry Area Sanitary Sewerage Construction Project.

(Tr. 10).

     D   l   Respondent had approximately 6 employees at the work site who identified

themselves as employees of Supermason Enterprises. (Tr. 34, 70).

                                          15

L The contract for the sewerage system project required that at least 60

percent of the major portions of the project be accomplished by the bidders own personnel,

a requirement of which Respondent was aware. (Tr. 13, GX 1).

                2. Respondent engaged in correspondence with the attorney for the Township

and G. Edwin Pidcock regarding the amount of subcontracting Respondent intended to use.

On December 9,1991, by letter to Attorney Layman, Township Solicitor, Supermason stated

that they would supply all equipment, labor and material. (Tr. 1446, GX 2.)

                3.   Supermason Enterprises filed weekly Payroll Certification records with

Plainfield Township, which identified Kevin Corrigan and Richard Schwind as laborers

employed by Supermason Enterprises during the workweek which includes May 6, 1992 on

the Payroll Certification records. (Tr. 18, 36, GX 3).

                4. Kevin Corrigan, the owner of C&S Contracting, was hired by Respondent

as a site foreman, with the responsibility for getting the other men working in the morning,

ordering pipe and ensuring that the job was completed. He was paid by Supermason by

employee check, rather than as a subcontractor for this particular project. (Tr. l’45,146,

149, 152, GX 11).

                5.   Mr. Lynch testified that Richard Schwind was employed by Supermason

Enterprises on May 6, 1992. (Tr. 165).

      E   l     On   May 6,1992 Mark Stelmack, a Compliance Safety and Health Officer with

the Occupational Safety and Health Administration inspected Respondent’s work site. (Tr.

33) l F. Upon first arriving at the work site on May 6, 1992,Mr. Stelmack observed the

                                              16

Mea where the crcavation was taking place, introduced himselE, and asked to speak to the

foreman. I&V&BCorrigan was introduced as the foreman on the site. (Tr. 33, 61).

            1. Inspector Stelmack observed two employees, Kevin Corrigan and Richard

Schwind, working in a trench adjacent to an existing sanitary sewer manhole, which had live

lines running out of the manhole. Mr. Stelmack also observed that a Case backhoe,

manufactured in Racine, Wisconsin, was in use. (Tr. 34, 36, 39, 43, 60, GX 6, 7, 49).

            20        The employees   in the trench were installing            a drop connection,   a

connection placed outside the manhole to direct sewage so that it enters the manhole closer

to the bottom, adjacent to the existing manhole. (Tr. 39, 43, 60, 76, 14).

            3. The existence of the live lines into the manhole created the possibility that

employees would be exposed to methane and hydrogen sulfide gasses when working on the

drop connection to the existing manhole. (Tr. 42).

                 a.      Methane   and    hydrogen      sulfide   are     commonly    found   in the

decomposition of organic materials such as raw sewage. Their infiltration into the trench

would create a hazard of oxygen displacement or explosion. (Tr. 46).

                 b. This potential hazard was limited by the fact that a mechanical plug

had been placed in the sewer lines, which, if working properly, would prevent the escape of

gasses from the live lines. Nevertheless, employees working in trenches where sewer gasses

may be present need-to be aware of how to identify the gasses and the precautions to be

taken in the event of their presence. (Tr. 45).

                 c. Supermason Enterprises did not have a written hazard communication

program covering these gasses. (Tr. 41-42). Material safety data sheets for these gasses were

                                               17

not available to employees at the work site. (Tr. 45, 47). Superniason Enterprises did not

prhde informatimr and trainingon hazardous materials at the work site to employees. (Tr.

53). S~permas~n Enterprises was aware of these deficiencies and had been previously cited

for violations of 00 1926.59(e)(l), 192659(g)(l) and 1926.59(h). (Tr. 41, 45, 53; GX 5).

Inspector Stelmack did not observe any monitoring equipment, such as an oxygen meter or

combustl’ble gas meter, on the work site. (Tr. 53, 55).

            4e        Using a steel tape, Inspector Stelmack measured the trench dimensions.

(Tr. 59, 73). The trench was 14 feet long, 8 feet wide at both the bottom and the top, and

approximately 8 to 10 feet deep. (Tre 59,73,85, 111). The trench walls were vertical. (Tr.

59, 72, GX 7, 8, 9).

             5   l      No   protective    system was utilized in the trench.           (Tr. 71, 73, 76).

Protective systems which might have been used include sloping or benching of the sidewalls

of the trench, a shoring system such as timber, balloon, or hydraulic shoring, or a trench box

or trench shield. (Tr. 77).

             6   l      Using the OSHA trenching standards             definitions,   Inspector   Stelmack

classified the soil in the trench as type “B“ soil, The material surrounding the manhole was

angular gravel backfilled around the manhole. The soil in the trench had also previously

been disturbed when a water line was installed. The remainder of the material in the trench

was compacted clay interspersed with various sized gravel. (Tr. 74, 101).

             7e Inspector Stelmack determined that the manhole he observed in the trench

was not a new manhole, but an existing manhole because the road surface above the

manhole was intact. (Tr. 98, GX 6, 7, 8, 9). Kevin Corrigan confirmed this. (Tr. 147).

                                                     18

8 There was no evidence of materials spalling fk~linthe sides of the trench

wa no ten&m cracks vi&Ie along the excavation face, no fissures in the face and no water

&Rmed either in the trench or seeping from the sidewalls of the trench. (Tr. 69).

          9. Inspector Stelmack observed that there was no ladder or other means of

egress from the trench. However, a ladder was lying on the ground, outside of the trench.

(Tr. 58, 107, GX 6). In the event of a sidewall failure or trench collapse, employees would

not be able to exit the trench rapidly and would probably die. (Tr. 60, 62).

          10. Daily inspections of the excavations and surroundings areas for situations

that could result in cave-ins or failure of the protective systems were not being made by a

competent person. The site foreman, Kevin Corrigan, told Inspector Stelmack that he was

not familiar . with the OSHA trenching regulations, although apparently he had substantial

experience as an excavation contractor. Mr. Corrigan also told Inspector Stelmack that he ,

was not responsible on site for employee safety and that he was not sure who was

responsible. (Tr. 62-63, 65, 152-53).

          11. The employees had not been trained in the recognition and avoidance
                                                                 Y

of unsafe conditions. (Tr. 66).

          12. The employees working in the unsloped, unshored trench 840 feet deep

were exposed to a hazard of trench wall collapse. (Tr. 64). The most likely injury to result

from failure of a trench sidewall would be death. (Tr. 65, 68).

   G. The project manual supplied to Super-mason Enterprises advised that under the

terms of the contract, the contractor was responsible for complying with applicable safety

and health laws governing construction and trenching. (Tr. 20, 21, 81, 82, GX 1). The last

                                        19

paragraph on page 74 of the project manual addresses the responsibility to protect trenches

during the mtion. (Tr. 21, GX 1).

             1. SupermasonEnterprises was aware of the provisions in the project manual,

as the specifications in the project manual are used by the contractor in order to draw up

the bid. (Tr. 21, 83).

             2.   Supermason Enterprises was also aware of the responsibility to comply

with applicable federal, state and local laws and ordinances by virtue of the pre-construction

conference. (Tr. 22, 83, GX 4).

             3. Mk Steven Goffredo and Mr. Kevin Corrigan were in attendance at the

pre-construction conference as representatives from Supermason. (Tr. 23, GX 4)

             4l   Mr.   Lynch was informed about the topics that were discussed at the

pre-construction conference as the minutes of the meeting were transmitted to Supermason’s

office. (Tr. 24, GX 4).

III 0 CONCLUSIONS OF LAW

    A.       Respondent utilizes tools, equipment, machinery, materials, goods and supplies

which have originated in whole or in part from locations outside the Commonwealth of

Pennsylvania and is therefore engaged in business affecting commerce and is subject to the

requirements of the Act. 29 U.S.C. 0 652(5).

    B   l    Respondent is an employer within the meaning of the Act and is therefore

subject to its requirements.

    C.      Respondent failed to comply with the terms of 29 C.F.R. 3 1926.59(e)(l) as

charged in Citation 1, Item l(a). A civil penalty of $00 is appropriate.

                                           20

D0 Respondent failed to comply with the tern of 29 C.F.R. 0 192659(g)(l) as

charged in Citatbn 1, Item l(b). A civil penalty of $00 is appropriate.

    E.       Respondent failed to comply with the terms of 29 C.F.R. 0 192659(h)(l)              as

charged in Citation 1, Item l(c). A civil penalty of $00 is appropriate.

    F0        Respondent    failed to comply with the terms of 29 C.F.R. 0 1926.651(c)(2) as

charged in Citation 1, Item 2(a).

    G.        Respondent    failed to comply with the terms of 29 C.F.R. 8 1926.651(k)(l) as

charged in Citation 1, Item 2(b).

    H    l    Respondent
                  *         failed to comply with the terms of 29 C.F.R. 8 1926.21(b)(2) as

charged in Citation 1, Item 2(c).

    I0        Citation 1, Items 2(a), 2(b), and 2(c) were properly characterized        as serious

violations of the Act. The proposed penalty for these violations of $1000 was calculated in
.
conformity with the requirements ol section 17(j) of the Act and is appropriate.

    J.        Respondent    failed to comply with the terms of 29 C.F.R. 0 1926.652(a)(l) as

charged in Citation 2, Item 1. This failure was properly characterized as a willful \;iolation

of the Act. The proposed penalty of $7,000 was calculated in conformity with the

requirements of section 17(j) of the Act and is appropriate.

Iv 0 ORDER

    Aa        Citation   1, Items l(a), l(b), and l(c) are affirmed      as other than serious

violations of the Act.

    B.        Citation 1, Items 2(a), 2(b), and 2(c) are affirmed as serious violations of the

Act .

                                             21

C l Citation 2 is afEm& as a willfidviolation of the Act.

     D   l   Tot& civil-penalties of $8,000 are assessed.

Dated: JUNI 1 1993
Wihiqgton,D.C.

                                          22

Get today's answer for your situation

You just read what one judge decided for one employer in 1993, and it binds only those parties. Ezel checks the current OSHA standards and Commission precedent and answers your specific situation, with citations.

Opens in Ezel Pro. Every answer cites the authority it relies on.