Berkman Brothers, Inc. (Commission decision, March 3, 1993)
Settlement requires fall protection and a $280 penalty
Apply this precedent to your situation
This is citable Commission precedent from 1993, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.
Plain-English summary
Berkman Brothers operated an electroplating facility where employees worked on walkways beside tanks containing heated and corrosive chemicals. OSHA cited the company for failing to guard employees against falls into the tanks or contact with their contents. In a settlement during Commission review, Berkman agreed to abate the violation within 45 days and withdrew its notice of contest. The company agreed to use personal fall-arrest systems designed to prevent contact with the plating chemicals, with overhead anchor points and components meeting the performance criteria in Appendix C to section 1910.66. Berkman also agreed to pay a $280 penalty, and each party agreed to bear its own fees and expenses. The Commission incorporated the settlement, set aside the ALJ's decision to the extent it was inconsistent, and entered the agreement as its final order.
Decision snapshot
- Cited standard(s): 29 C.F.R. § 1910.23(c)(3), with settlement abatement governed by Appendix C to 29 C.F.R. § 1910.66
- Outcome: Settlement approved, contest withdrawn, abatement required within 45 days, and a $280 penalty assessed.
- Key point: The approved fall-arrest system had to prevent workers from reaching the corrosive plating chemicals if they fell.
Full text (OSHRC public release)
UNITED STATES OF AMERICA
OCCUPATIONAL SAFETY AND HEALTH REVIEW COMMISSION
1825 K STREET NW
4TH FLOOR
WASHINGTON. DC 20006- 1246
.
SECRETARY OF LABOR, ..
.
Complainant,
..
.
Docket No. 91-2986
..
..
..
..
..
ORDER
This matter is before the Commission on a direction for rev ew entered by
Commissioner Velma Montoya on April 2, 1992. The parties have now fi ed a stipulation and settlement agreement.
Having reviewed the record, and based upon the representations appearing in the
stipulation and settlement agreement, we conclude that this case raises no matters
warranting further review by the Commission. The terms of the stipulation and settlement
agreement do not appear to be contrary to the Occupational Safety and Health Act and are in compliance with the Commission’s Rules of Procedure.
Accordingly, we incorporate the terms of the stipulation and settlement agreement
into this order, and we set aside the Administrative Law Judge’s decision and order to the extent that it is inconsistent with the stipulation and settlement agreement. This is the final order of the Commission in this case. See 29 U.S.C. $5 659(c), 660(a), and (b).
Edwin G. Foulke, Jr.
Chairman
Commissioner
Velma Montoya
Commissioner
Dated: March 3. 1993
NOTICE OF ORDER
The attached Order by the Occupational Safety and Health Review Commission was issued and served on the following on March 3, 1993.
Daniel J. Mick, Esq.
Counsel for Regional Trial Litigation
Office of the Solicitor, USDOL
200 Constitution Ave., N.W. Room S4004
Washington, D.C. 202 10
Patricia Rodenhausen, Esq.
Regional Solicitor
Office of the Solicitor, U.S. DOL
201 Varick St., Room 707
New York, NY 10014
Gerald R. Berkman
Berkman Bros., Inc.
55 Eckford Street
Brooklyn, NY 11222
FOR THE COMMISSION
.
Executive Secretary
UNITED STATES OF AMERICA
OCCUPATIONAL SAFETY AND HEALTH REVIEW COMMISSION
ROBERT REICH, SECRETARY OF LABOR, :
:
Complainant, : l a
v. : OSHRC Docket
: No. 91-2986
BERKMAN BROTHERS, INC.,
:
l l
l
0
Respondent. a l
l
0
STIPULATION AND SETTLEMENT AGREEMENT
I
The parties have reached agreement on a full and complete
settlement and disposition of the issues in this proceeding which
is currently pending before the Commission.
II
It is hereby stipulated and agreed by between the l
Complainant, Secretary of Labor, and the Respondent, Be&man
Brothers, Inc. that:
1 l Respondent represents that the alleged violation of
29 C.F.R. 1910.23(c)(3) (Serious Citation 1, item 1) for which it
has been cited shall be abated within 45 days of the execution of
this agreement and shall remain abated.
2 l Respondent hereby withdraws its notice of contest
previously filed in this case.
3 l The parties agree that respondent shall protect its
employees working adjacent to electroplating tanks in the copper
and nickel plating areas of its workplace from falls into the
tanks, and/or accidental contact with the chemicals therein, by
means of a personal fall arrest system as defined in Appendix C
to 29 C.F.R. 5 1910.66. Respondent represents that the fall
arrest system utilized will be designed in a manner which
prevents employee contact with corrosive plating chemicals in the
event of a fall. This shall include locating the anchor point of
the fall arrest system at a point directly above the employee's
work area in order to minimize employee free falling, including
swing falling. Respondent further agrees to provide employees
with a personal fall arrest system that meets or exceeds the
design for system components and system performance criteria of
paragraphs (c) and (d), respectively, of Mandatory Section I of
Appendix C to 1910.66.
40 Respondent hereby agrees to pay a penalty in the amount
of $280 by submitting its check, made payable to W.S. Department
of Labor - OSHA" to the OSHA Area Office within 45 days from the
date of this agreement.
5 l Each party agrees to bear its own fees and other
expenses incurred by such party in connection with any stage of
this proceeding.
60 No authorized employee representative elected party
status in this case.
70 The parties agree that this Stipulation and Settlement
Agreement is effective upon execution.
8 l Respondent hereby certifies that on February J;15,
1993, a copy of this Stipulation and Settelement Agreement was
served on the authorized employee representative by pre-paid
first class mail or by personal delivery in accordance with
Commission Rule 7(c). Respondent further certifies that a copy of this Stipulation and Settlement Agreement was posted on the s!2 s day of February, 1993, pursuant to Commission Rules 7 and 100, and will remain posted for a period of ten days.
Dated this d"a*day of February, 1993,
JUDITH Eo MRAMER
Deputy Solicitor
JOSEPH M. WOODWARD
Associate Solicitor for
Occupational Safety and Health
DONALD Go SHALHOUB
Deputy Associate Solicitor for
Occupational Safety and Health
DANIEL J. MICK
Counsel for Regional
Trial Litigation
GERALD R. BERKMAN
President
Attorney for the
Berkman Brothers, Inc.
Secretary of Labor
UNITED STATES OF AMERICA
OCCUPATIONAL SAFETY AND HEALTH REVIEW COMMISSION 1825 K STREET N.W.
4TH FLOOR
WASHINGTON D.C. 20006-l 246
FAX:
~~-~
c~~~MO8
SECRETARY OF LABOR
Complainant,
v. OSHRC DOCKET
NO. 91.2986
BERKMAN BROS, INC.
Respondent.
NOTICE OF DOCKETING
OF ADMINISTRATIVE LAW JUDGE’S DECISION
The Administrative Law Judge’s Re ort in the above referenced case was docketed with the Commission on Marciii 25, 1992. The decision of the Judge will become a final order of the Commission on April 24, 1992 unless a Commission member directs review of the decision on or before that date. ANY PARTY DESIRING REVIEW OF THE JUDGE’S DECISION BY THE COMMISSION MUST FILE A PETITION FOR DISCRETIONARY REVIEW. Any such etition should be received by the Executive Secretary on or before April 14, P992 in order to ermit sufEicienttime for its review. See Commission Rule 91, 29 CT .F.R. 2200.91. All further pleadings or communications regarding this case shall be addressed to:
Executive Secretary
Occupational Safety and Health
Review Commission
1825 K St. N.W., Room 401
Washington, D.C. 20006-1246
Petitioning parties shall also mail a copy to:
Daniel J. Mick, Esq.
Counsel for Regional Trial Liti ation
Office of the Solicitor, U.S. DO%
Room S4004
200 Constitution Avenue, N.W.
Washington., D.C. 20210
If a Direction for Review is issued by the Commission., then the Counsel for Regional Trial Litigation will represent the Department of Labor. Any party having questions about review nghts may contact the Commission’s Executive Secretary or call (202) 634-7950.
Date: March 25, 1992
DOCKET NO. 91-2986
NOTICE IS GIVEN TO THE FOLLOWING:
Daniel J. Mick, Esq.
Counsel for Re l onal Trial Liti ation
Office of the SoQkitor, U.S. DOc
Room S4004
200 Constitution Ave., N.W.
Washington, D.C. 20210
Patricia Rodenhausen, Esq.
Re ‘onal Solicitor
O&e of the Solicitor U.S. DOL
201 Varick, Room 707
New York, NY 10014
Howard G. Estock, Esquire
Clifton, Budd & DeMaria,
420 Lexington Avenue
New York, NY 10170 0089
Gerald R. Be&man, President
Be&man Bros., Inc.
55 E&ford Street
Brooklyn, NY 11222
bin Sommer
Chie f Administrative Law Jud e
Occupational Safety and Heal fil
Review Commission
Room 417/A
1825 K Street, N.W.
Washington, DC 20006 1246
00100600311:02
UNITED STATES OF AMERICA
OCCUPATIONAL SAFETY AND HEALTH REVIEW COMMISSION 1825 K STREET N.W.
4TH FLOOR
WASHINaON D.C. 20006- 1246
..
SECRETARY OF LABOR, ..
.
.
Complainant,
v. .. Docket No. 91-2986
..
BERKMAN BROS.,
..
INC. ..
.
.
Respondent.
..
..
APPEARANCES:
WILLIAM G. STATON, ESQ.
HOWARD G. ESTOCK, ESQ.
U.S. Department of Labor
Clifton, Budd & DeMaria, Esqs.
201 Varick Street
420 Lexington Avenue
New York, New York
New York, New York
For Complainant
For Respondent
Before: Administrative Law Judge Irving Sommer
DECISION AND ORDER
This proceeding arises under the Occupational Safety and Health Act of 1970 (29 U.S.C. 651 et seq., hereafter called the “Act”).
Following an inspection by the Occupational Safety and Health Administration
(OSHA) between August 1990-January 1991 Respondent Berkman Bros. Inc. (“Berkman”) was issued a serious citation containing 23 alleged violations, and an other than serious citation alleging 2 violations. All of the items in both citations were settled except for item 1 of serious citation no. 1, which alleged a violation of 29 CFR 1910.23 (c)(3), which is at
-29
issue herein. The trial of this case was held on December 20, 1991, in New York, New York. All parties were represented and filed post-hearing briefs. No jurisdictional issues are in dispute.
BACKGROUND
Be&man is a New York corporation with its principal place of business at 55 E&ford Street, Brooklyn, New York. It is engaged in electroplating and related activities. Specifically, it puts a metal coating on various items for “decorative and corrosion purposes” with its primary source of business being the “ lamp and lighting industry, wire display goods, catering products, hardware.“(T-80).
The alleged violation of 29 CFR 1910.23 (C)(3) took place in the nickel plating area
of the plant. The plating process was generally described by Gerald Be&man, the company president as follows: The items to be plated are hung on a plating rack or with copper wire to induce conductivity; they are put through a cleaning process( an alkaline caustic cleaner), then rinsed in a mild muriatic acid solution, rinsed again and put into nickel plating tanks; the nickel plater lifts the work out of the bath and hangs it above the tank so that the chemicals dripping therefrom can be recovered; the item is then given further rinses and then goes out of the plating room by an overhead conveyor. (T89) The nickel plating tank is maintained at a PH level of 4 which is mildly corrosive. (T91) The temperature of the chemicals in the nickel plating tank is maintained at approximately 140 degrees. The tank contains nickel sulfite, nickel chloride, boric acid, ammonia and other chemical compounds. Atop the nickel tank is a cathode bar which separates the tank at midpoint (T97), being necessary in the electroplating process to attract the positively charged metal. There is a wooden walkway approximately 1-2 feet above the floor surrounding the tanks which the employees use to walk on when working around the tanks. The height of the tanks extended approximately 30-32 feet above the walkway.
Alleged Violation of 29 CFR 1910.23 (c)(3)
The Secretary alleges that the Respondent violated the section by failing to provide employees working around the tanks in the nickel plating area protection from falls into the tanks and contact with the hazardous chemical materials therein. The standard provides:
1910.23 (c)(3) Protection of open-sided floors, platforms, and runways.
(3) Regardless of height, open-sided floors, walkways, platforms, or runways above or adjacent to dangerous equipment, pickling or galvanizing tanks, degreasing units, and similar hazards shall be guarded with a standard railing and toe board.
The compliance officer( CO) testified she observed two employees working and
walking on a raised wooden walkway adjacent to the tanks of chemicals used in the electroplating process. The walkway was noted to be wet and slippery. These tanks contained hazardous chemicals (T149, 150). The employees were subject to the hazard of falling into the tanks and coming into contact with their hazardous chemical contents while either working lifting objects in and out of the tanks, or while walking in the vicinity. To protect the employees from the hazard therein the CO suggested feasible methods of abatement including removable railings, tieing up of employees to a stationary object, automation of the work so that objects could be placed in the tanks and lifted and lowered automatically as was being carried out in the brass operation at the plant. Mr. Peter Martinez, the head plater at Berkman testified that management had installed railings all around the tanks and asked him to do his regular job; with the railings installed he worked 5-10 minutes on three or four days, and found lifting the materials above the railings so that it could be plated and rinsed caused pain in his back and arms.
Mr. Gerald Be&man, the company president testified he felt the guard railings could not be used because it created a greater hazard for his employees
causing them back problems, etc. He stated they could not tie off while doing the work since they were always moving around between tanks; Finally, he was of the opinion that the nickel process could not be automated as was done in the brass plating area since there was not adequate space and mainly because it was too expensive to install. His best estimate was that it would cost half a million dollars to install. He stated that the company had applied for a variance the week prior to the hearing.
By its plain language this standard applies to the unguarded tank operation herein.
The evidence is clear that the chemicals in the nickel plating tank which were heated, and the other tanks containing deleterious substances were hazardous to the employees working at the plant. Be&man had knowledge of such hazard, having been supplied this information by their outside consultant engineer. (T112, Exh. C-2). * In short, there is no dispute of the applicability of the standard, that the tanks contained hazardous materials, that the employees had access to the hazard, and that Be&man knew of the violation. Actually, Gerald Berkman testified, “we work under the assumption that all of the tanks contain hazardous materials and they need to be treated with respect and appropriately.“(T119).
Berkman asserts two affirmative defenses. It contends: (1) Compliance with the
standard is a greater hazard than noncompliance; and (2) Infeasibility of compliance with the standard.
An employer is excused from strict compliance with the standard if compliance would
result in a greater hazard than noncompliance. To establish such defense, the employer must prove: (1) The hazards created by complying with the standard are greater than those of non-compliance; (2) Other methods of protecting its employees from the hazards are not available, and (3) a variance is not available or that application for a variance is inappropriate. Spancrete Northeast, Ix. 15 BNA OSCH 1020, 1022 (No. 86-521, 1991).
The allegation that the railings which had been installed around the tanks presented A
a greater hazard to emDlovees than working without them is based on the statement u A 4 u
of
Martinez that on three occasions while working with them in place for 5-10 minutes he experienced arm and back pain. Berkman made no further investigation, called in no consultants in the field of ergonomics or other experts in the dynamics of work activity, so that a more positive appraisal be given to the problems, if any, were associated with the work activity if a railing was used. The verbalized fears of the employee engendered after a very short trial period carried out at the request of his employer and under the employers observation and at his request is not the type of fully credible evidence demonstrating the presence of a hazard. House Wood Products Company, 3 BNA OSHC 1993 (1976). Similarly, Berkmans unsupported opinion is likewise unacceptable to prove a greater hazard. Hurlock Roofing Co., 7 BNA OSHC 1108 ( 1979). Among the other means of protecting the employees working at the tanks from the hazard present was the recommendation by the CO that automation similar to what was already in place in the brass plating room be used; the general response by Be&man that this cannot be accomplished because of lack of space and cost is rejected; no proof of its economic or technological infeasibilty was presented; no investigation of is feasibility was carried out, no outside consultants were sought for an opinion thereof; the unsupported statements of Gerald Be&man, who has no expertise in the engineering field as to the technical and economic aspects of installing automated procedures cannot be given any serious credibility, and is rejected.
Finally, there is a complete failure to comply with third element, the variance factor.
The testimony demonstrated that such variance application was essentially a sham, being sought about one week before trial. To allow such belated use of the variance defense at the time of trial would negate it and allow employers to disregard a standard when they mistakenly believe their work practice is safer than complying with the standard. Thusly, employees would be exposed to a hazard through the entire time up to the final disposition of the enforcement proceedings. On its face this prolongment of the hazard is contrary to the intent of the Act in promoting the safety and health of the nations employees. “Both the Commission and the Courts have habitually looked on such claims with a jaundiced eye when they have been raised for the first time in enforcement proceedings by employers who have made no prior attempt to seek either a variance -- or a modification.” Diebo@ Inc. V.Marsizall, 585 F2d 1327 (6th Cir. 1978). It is clear that Be&man has failed to prove
any of the elements of the greater hazard defense and it is rejected.
The defense of infeasibilty of compliance is likewise found unavailable herein. The
burden of proving that alternative means of compliance were infeasible rests with the employer. The Commission in Dun-Par Engineering Fonm Company, 12 BNA OSHC 1949 (No. 79-2553, 1986) stated: “ the question of whether a means of protection is infeasible must be answered in light of practical realities of the particular workplace.” Reviewing respondent’s operations in light of the evidence of record demonstrates the suggested methods of compliance are practical and realistic. The CO testified that either railing or automation are feasible. In fact the work was carried out with the railings in place, the complaint of the employee notwithstanding; the short trial period as stated previously did not persuasively demonstrate it presented a greater hazard to the worker; additionally, the automatic operation option which was successful in another part of the plant was similarly shown as feasr%le; the allegation of economic and technical infeasibility was not proven in any way, and is nothing more than a self-exculpatory allegation by Be&man. On this record, the respondent did not sustain the burden of proving the means of compliance put forth by the Secretary were infeasible. Accordingly, the standard was violated as alleged.
The Secretary proposed a penalty of $560. The Commission stated in Secretary v.
National Realty & Construction Co., 72 OSAHRC 9/a2, 1 BNA OSHC 1049. 1971-3. CCH OSHD, par. 15,188 (No. 85, 1971) that the elements to be considered in determining the gravity are: (1) the no. of employees exposed to the risk of injury; (2) the duration of exposure; (3) the precautions taken against injury, if any; and (4) the degree of probability of occurrence of injury.
Having considered the evidence in the record relating to those factors, the penalty of $560 proposed by the Secretary is appropriate.
FINDINGS OF FACT
The findings of fact relevant and necessary to a determination of the contested issues have been found specially and appear in the decision. See Rule 52(a) of the Federal Rules of Civil Procedure.
CONCLUSIONS OF LAW
1. The record establishes by a preponderance of the evidence that the Respondent committed a serious violation of 29 CFR 1910.23 (c)(3).
2. A penalty of $560 is appropriate.
Based upon the findings of fact, conclusions. of law, and the entire record, it is ORDERED
1. Citation no. 1, issued February 25, 1991, is AFFIRMED and a penalty
DATED: MAR 2 3 19%
Washington, D.C.
Does this precedent still control your case?
Ezel checks whether it still stands, including any court review since, and applies it to your situation with citations.
Opens in Ezel Pro.
- Checks the law as it stands today, not only this page
- Cites every source it relies on, so you can verify it
- Chat, drafting and research in one workspace