OSHRC Commission decision Docket 87-2007 Decided May 7, 1992 Mixed result

Sal Masonry Contractors, Inc.

Ladder item vacated and guardrail violation made willful

Apply this precedent to your situation

This is citable Commission precedent from 1992, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.

Currency note: this decision dates from 1992
The OSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Decision of the Commission
This is a decision of the Occupational Safety and Health Review Commission, the highest level of agency review, citable as Commission precedent. It may have been appealed to a U.S. Court of Appeals after issuance; check subsequent history before relying on it. The full text below is from the official OSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official OSHRC release. The full text is the Commission's own document.
Read the official release (oshrc.gov)

Plain-English summary

Sal Masonry Contractors was cited for ladder and scaffold violations during masonry work on an academic building at Cornell University. The Commission vacated the scaffold-access item because the testimony conflicted over whether a ladder was present and whether supervisors knew employees were climbing the scaffold, and the former judge had not made credibility findings that resolved the conflict. It left the damaged-plank violation classified as repeated and serious with a $200 penalty, but found that the conflicting evidence did not prove willfulness. The Commission found the missing-guardrail violation willful because the company had prior citations under the same standard, its president had recently acknowledged missing toeboards, and a foreman admitted knowing guardrails were required but had not installed them. It assessed $1,000 for that willful violation. Together with the ALJ's unreviewed dispositions, the case resulted in total penalties of $1,400.

Decision snapshot

  • Cited standard(s): 29 C.F.R. §§ 1926.451(a)(8), 1926.451(a)(13), 1926.451(a)(14), 1926.451(d)(3), 1926.451(d)(10), and 1926.602(c)(1)(vi).
  • Outcome: Scaffold-access item vacated; damaged-plank item affirmed as repeated and serious with $200; guardrail item affirmed as willful with $1,000; unreviewed items left intact.
  • Key point: Prior citations plus a supervisor's admitted knowledge and delay supported willfulness for missing guardrails, while evenly balanced conflicting evidence could not prove the separate access violation.

Full text (OSHRC public release)

Docket No. 87-2007

SECRETARY OF LABOR.

Complainant,

v.

SAL MASONRY CONTRACTORS, INC.,

Respondent.

OSHRC Docket No. 87-2007

DECISION

BEFORE: FOULKE, Chairman; WISEMAN and
MONTOYA, Commissioners.

BY THE COMMISSION:

Sal Masonry was the masonry contractor
for the building of Savage Hall, an academic building at Cornell University in Ithaca, New
York. As a result of an inspection by Ralph Rose, a compliance officer for the
Occupational Safety and Health Administration ("OSHA"), a citation was issued
which, as amended, alleged willful, as well as repeated and serious, violations of the
ladder and scaffolding standards at 29 C.F.R. � 1926.451(a)(8), (a)(13), and (d)(10).
Penalties of $10,000 were proposed for each of the three alleged violations.

Sal Masonry contested the citation and a
hearing was held before former Commission Administrative Law Judge Foster Furcolo. Judge
Furcolo found violations of each cited standard and characterized each violation as
repeated and serious. He assessed penalties of $200 each for the violations of section
1926.451(a)(8) and (13) and $500 for the violation of section 1926.451(d)(10). Review was
directed on the issues of: (1) Whether Sal Masonry violated section 1926.451(a)(13) by
failing to provide an access ladder or "equivalent safe access" to scaffolding,
and, if so, whether that violation was willful; and (2) Whether the judge erred in holding
that Sal Masonry's violations of section 1926.451(a)(8) and (d)(10) were not willful.[[1]]
For the reasons set forth below, we vacate that part of the citation alleging a violation
of section 1926.451(a)(13), find that the violation of section 1926.451(a)(8) was not
willful, and find that the violation of section 1926.451(d)(10) was willful. We assess a
$1000 penalty for the willful violation.

Alleged Violation of Section
1926.451(a)(13): Was A Ladder or Equivalent Safe Access Provided for Scaffolding?

The Secretary alleges that Sal Masonry
violated section 1926.451(a)(13)[[2]] by failing to provide an access ladder or equivalent
safe access to employees who were seen climbing the frames and braces of scaffolding
erected inside an air intake shaft.

To prove a violation of a standard, the
Secretary must establish that: (1) the standard applies to the cited condition; (2) the
employer violated the terms of the standard; (3) its employees were exposed or had access
to the violative conditions; and (4) the employer had actual or constructive knowledge of
the violation. E.g., Trumid Constr. Co. , 14 BNA OSHC 1784, 1788, 1990 CCH OSHD �
29,078, p. 38,859 (No. 86-1139, 1990).

It is undisputed that the standard is
applicable, and the record is clear that employee exposure was shown. The parties dispute
whether the terms of the standard were violated and whether the employer had knowledge of
the allegedly violative conditions. The evidence on these issues is in direct conflict.

Five of Sal Masonry's employees or
former employees -- Eugene DeLong, Samuel Swan, Dwayne Vorhes, Arthur White, and Gary
Stupke -- testified that there was no ladder present to access the scaffolding. All five
also testified that they sometimes accessed the scaffold by climbing it. Compliance
officer Rose testified that no ladder was present on the first day of the inspection.
However, the next morning, after Rose saw an employee of Sal Masonry climbing the
scaffolding, he asked company foreman Luke Renna why the employee was climbing the
scaffolding. Rose testified that Renna answered, "I don't know. We had a ladder. It
must be somebody took it." The company then sent its employees to look for a ladder,
and they brought one back and positioned it for access to the scaffold.

Company foreman Renna, labor foreman
Craig Zullo, and project manager Don Judge all testified that they had never seen any of
their employees climb the scaffolding. Renna and Zullo also testified that there was a
ladder at the site. Renna testified that the ladder was lying on the ground near the air
intake shaft where the employees worked and that he had taken it down a few days before
the compliance officer inspected the site because he did not want any of the college kids
climbing it and getting hurt falling into the shaft. Zullo testified that the ladder was
lying on the ground outside the air intake shaft, but he stated that it had never been put
up because the employees preferred to access the scaffolding by using stairs and other
scaffolding.

Judge's Decision

The judge concluded that "[t]he
evidence clearly established that there was no ladder" present to access the
scaffold. Instead of specifically stating what that evidence was, however, the judge
merely listed a series of transcript pages that he apparently believed contained testimony
supporting his conclusion. He did not specifically refer to any of the evidence presented
above in framing his conclusions. Instead of separately considering whether the Secretary
proved that Sal Masonry had actual or constructive knowledge that a ladder was not present
to access the scaffolding, the judge resolved the knowledge issue as to all three of the
alleged violations referred to in the direction for review by concluding that
"Respondent knew, or should have known, of all the alleged hazardous conditions. All
were in plain sight or were admitted by supervisory personnel of the Respondent." His
finding was followed by an enumeration of the transcript pages which presumably contained
the evidence to support the finding.

Discussion

To establish that section 1926.451 (a)(
13) was violated, the Secretary must show that no ladder was provided. The Secretary's
evidence demonstrates that there was no ladder and that employees climbed the scaffolding
to access their workplaces. The company's evidence demonstrates that there was a ladder
and that none of the company's supervisors had seen any of their employees climb the
scaffolding.

In order to prove knowledge in this
case, the Secretary must show that the company either knew or, with the exercise of
reasonable diligence, could have known that there was no ladder present to access the
scaffolding. See Daniel Constr. Co. , 10 BNA OSHC 1254, 1256, 1982 CCH OSHD �
25,840, p. 32,328 (No. 80-1224, 1981). The Secretary argues that she proved knowledge by
showing that certain of the company's employees, and one of its supervisors, climbed the
scaffolding and that foreman Renna witnessed one of the employees climbing it. Sal Masonry
argues that there was no testimony that its supervisors knew that the ladder they had
previously placed at the job site had been removed.

With the evidence in conflict, it was
necessary for the judge to make credibility findings that specifically resolved the
conflicting testimony. Generally, this requires a written analysis of the testimony,
including reasons for the finding. See P & Z Co., 6 BNA OSHC 1189, 1192,
1977-78 CCH OSHD � 22,413, p.27,024 (No. 76-431, 1977). See also Asplundh Tree Expert
Co. , 7 BNA OSHC 2074, 2078-79, 1980 CCH OSHD � 24,147, pp.29,346-47 (No. 16162,
1979). The judge failed to make such credibility findings here. This deficiency would
ordinarily result in the Commission remanding the case to the judge for further
consideration and explanation. See C. Kaufman, Inc. , 6 BNA OSHC 1295, 1298,
1977-78 CCH OSHD � 22,481, p. 27,100 (No. 14249, 1978). However, Judge Furcolo is no
longer with the Commission. In light of the Commission's role as the ultimate finder of
fact, Accu-Namics, Inc. v. OSHRC , 515 F.2d 828, 834 (5th Cir. 1975), cert.
denied , 425 U.S. 903 (1976), we will complete the adjudication of matter.

The Secretary is required to prove each
element of her case by a preponderance of the evidence. See Regina Constr. Co.,
15 BNA OSHC 1044, 1046, 1991 CCH OSHD � 29,354, p. 39,465 (No. 87-1309, 1991). The judge
failed to provide us with credibility findings, and the record does not help us resolve
the conflicts in the testimony. We thus have no sufficient basis for crediting the
testimony of one set of witnesses over the other. The result is that the evidence as to
whether a ladder was present and whether there was knowledge is basically in balance as
between the two parties. The Secretary has therefore failed to meet her burden of proving
by a preponderance of the evidence that the terms of the standard were violated and that
there was employer knowledge. In light of her failure to establish her prima facie case,
we vacate the citation insofar as it alleges that Sal Masonry violated section
1926.451(a)(13).[[3]]

Alleged Willful Violation of
Section 1926.451(a)(8): Split Planks on Scaffolding

Judge Furcolo found that Sal Masonry
violated section 1926.451(a)(8)[[4]] by failing to immediately repair or replace damaged
scaffold planks on which company employees worked. He characterized the violation as
repeated and serious, and he assessed a $200 penalty. In finding that the Secretary failed
to establish that the violation was willful as alleged, the judge concluded that Sal
Masonry "did not act in utter disregard of the safety of its employees, and the
Respondent did not intentionally violate any cited standard." He supported those
conclusions by referring to: uncontradicted testimony that Sal Masonry painted its damaged
planks so that they would not be confused with planks in good condition; and testimony
from compliance officer Rose that a representative of the company told him that Sal
Masonry had an "average" safety program.

The Secretary argues that the judge used
the wrong test for willfulness. She contends that the judge apparently concluded that if
an employer can point to anything that it has done that has a beneficial effect on
employee safety, then the violation is not willful.[[5]] The Secretary contends that the
judge's approach virtually writes willfulness out of the Act, since most employers would
be able to point to some step they have taken to improve employee safety. She also argues
that she proved willfulness on the basis of the entire record.

To prove that a violation was willful,
the Secretary must show that the violation "was committed voluntarily with either an
intentional disregard for the requirements of the Act or with plain indifference to
employee safety." A.C. Dellovade, Inc., 13 BNA OSHC 1017, 1019, 1986-87 CCH
OSHD � 27,786 (No. 83-1189,1987). To show intentional disregard of a standard, there must
be evidence that the employer knew of the applicable standard prohibiting the condition
and that it consciously disregarded it. E.g., Williams Enterp., Inc. , 13 BNA OSHC
1249, 1257, 1986-87 CCH OSHD � 27,893, p. 36,589 (No. 85-355, 1987). We agree with the
Secretary that the judge used the wrong test for willfulness by requiring the Secretary to
establish that Sal Masonry acted in "utter disregard of the safety of its
employees." As the quotation from the Dellovade case shows, the Secretary's
burden of proving willfulness is not so heavy. Moreover, the evidence relied on by the
judge, Sal Masonry's painting of certain of its damaged planks and its "average"
safety program, sheds little light on the question of whether the company's violation of
section 1926.451(a)(8) was willful.

To prove willfulness, the Secretary
relies on a settlement agreement affirming a violation of section 1926.451(a)(8) by the
company, evidence of the use of damaged planks by the company's employees, and knowledge
of that use by company supervisors. Although we find that the company did have knowledge
of the requirements of the standard, our review of the record fails to establish that Sal
Masonry's failure to immediately repair or replace damaged planks was willful.

Foreman Renna testified that the
company's procedure with respect to split or damaged planks was to use them as mud sills,
if possible, but otherwise to either spray paint them or throw them out. Labor foreman
Zullo testified that the company paid close attention to cracked planks. He stated that
planks that were not considered to be in good condition did not go on the scaffolding
because an employee could fall through them and be killed. He also stated that if split
planks were found, they would be painted and put in a separate pile from the good planks.
Project manager Judge testified that he was on the scaffolding every day and examined the
planks for cracks and defects, but he did not discover any problems. He also testified, as
did Renna, that if split planks were found they would be used as mud sills or put aside
and spray painted. Compliance officer Rose testified that company president Sal Fresina
"may have" indicated to him that if split planks were found, they were utilized
as mud sills and not as scaffold planking.

The testimony of company officials was
corroborated by employee Stupke, who testified that Sal Masonry instructed employees who
saw a cracked plank to tell a supervisor so that the plank could be replaced. Employee
White testified that Sal Masonry informed its employees that if they saw a cracked plank,
it would be replaced immediately. White also testified that Sal Masonry would correct any
safety violations he brought to their attention.

The Secretary contends, however, that
employees Swan, Vorhes, White, and Stupke all testified that they worked on cracked or
notched planks on the air intake shaft scaffolding. Although these employees did testify
that they worked on damaged planks, we find that their testimony cannot be relied upon to
support the Secretary's willful allegation because the same employees provided testimony
that tends to disprove willfulness. Employees Swan and White testified that they never
notified a supervisor of the cracked or damaged planks. Employee Vorhes also testified
that he never told anyone from Sal Masonry about the cracked planks and also testified
that he never saw a supervisor view a split plank. Although employee Stupke testified at
the hearing that he did not think he had been told to notify a supervisor of the
existence of split planks, he also testified to the truth of a pre-hearing statement he
gave that employees were in fact instructed to notify a supervisor if they saw cracked
planks, so that the planks could be replaced and work could be resumed.

The Secretary further relies on evidence
that shows Sal Masonry's supervisors knew about the damaged planks. She claims that
employee DeLong testified that labor foreman Zullo told him to work on scaffolding where
there were damaged planks and worked with him in such areas. DeLong also testified, the
Secretary points out, that he complained to project manager Judge about damaged planks,
but that nothing was ever done about them.

Sal Masonry attacks the credibility of
employee DeLong because DeLong had been fired by labor foreman Zullo. Zullo testified that
he had never been told of any split planks and that he had never told DeLong to work where
there were split planks. Project manager Judge testified that he had never seen split
planks at the Cornell jobsite before the inspection by compliance officer Rose. Foreman
Renna testified that he did not recall any employees telling him there were split planks
on the scaffolding and that he did not see any split planks other than the one pointed out
to him by the compliance officer in an area where Renna had not been. Because the judge
did not specifically resolve the conflicting testimony of DeLong and the company's
supervisors, we have no particular basis for crediting either DeLong or the supervisors.
Thus, we cannot conclude that DeLong's testimony establishes that Sal Masonry's
supervisors knew of the cracked planks.

The Secretary also points to compliance
officer Rose's testimony that foreman Renna told him that damaged and cracked planks had
been thrown off scaffolding at another site and used as scaffolding at the Cornell site.
Foreman Renna denied making the statement, however, and the judge did not resolve the
conflict in the testimony between Rose and Renna. Once again, we have no basis for
resolving the conflicting testimony. Therefore, we cannot say whose testimony is more
persuasive, and we must find that compliance officer Rose's contradicted testimony
provides no support for the Secretary's allegation of willfulness.

We also reject the Secretary's
contention that the violation was willful because the company had previously been cited
for violating the same standard. Under Potlatch Corp. , 7 BNA OSHC 1061, 1063,
1979 CCH OSHD � 23,294, p.28,171 (No. 16183, 1979), the Secretary makes out a prima facie
showing that a violation is repeated by establishing that there was a Commission final
order against the same employer for a substantially similar violation. Substantial
similarity can be shown by demonstrating that both violations are of the same standard.
However, such a showing, standing alone, is not sufficient to establish a willful
violation. In D.A. & L. Caruso, Inc ., 11 BNA OSHC 2138, 2142, 1984-85 CCH
OSHD � 26,985, p.34,694 (No. 79-5676, 1984), the case relied on by the Secretary, there
was ample additional evidence which compelled the finding of a willful violation. In this
case, however, as outlined above, the testimony supporting a willful determination is in
conflict. Because the judge failed to resolve the conflicts, we are unable to choose from
the conflicting versions of testimony, and we conclude that the violation was not proven
to be willful.

Alleged Willful Violation of Section 1926.451(d)(10): Scaffolding Without
Guardrails or Toeboards

The judge found that Sal Masonry committed a repeated, serious violation of section
1926.451(d)(10) [[6]] by failing to provide standard guardrails and toeboards for tubular
welded frame scaffolding on which employees worked. He assessed a $500 penalty. The judge
concluded that the violation was not willful without providing any specific reasons for
his conclusion, stating only that the company painted damaged planks and that the
compliance officer rated its safety program "average." The judge relied on this
same evidence in finding that the violation discussed above was not willful. Therefore,
his decision provides us with virtually no insight into whether Sal Masonry willfully
violated section 1926.451(d)(10).

However, our own review of the record
indicates that the Secretary did establish a willful violation of section 1926.451(d)(10).
The evidence clearly demonstrates that Sal  Masonry knew of the cited standard. It
had received three prior citations alleging violations of the same standard in January,
August, and December of 1985. The company's attorney conceded that Sal Masonry failed to
contest two of the citations, and that it had settled the guardrail portion of the third
citation by agreeing that it be affirmed. [[7]] Further evidence that Sal Masonry knew of
the standard's requirements is provided by a letter written by company president Fresina
to OSHA less than two weeks before the violations involved here occurred, acknowledging
that "toeboards were not in place" on scaffolding at the Savage Hall
construction site.

In addition, the evidence shows Sal
Masonry consciously disregarded the standard. Compliance officer Rose testified that when
he arrived at the jobsite, he observed employees, including foreman Renna, working on
unguarded scaffolding. Rose testified that when he asked Renna why guardrails were missing
from the scaffold, Renna responded, "he [Renna] had been told that there should be
guardrails put on the scaffold; that he [Renna] just hadn't gotten around to doing it.
[[8]]

Sal Masonry contends that compliance
officer Rose is not a credible witness and that he is biased against it. The company
further argues that because it has called the compliance officer's credibility into
question, the judge's. credibility findings should be given deference. Thus, it claims
that the judge's finding that the compliance officer's characterization of the company's
safety program as "average" was more compelling than the compliance officer's
testimony on willfulness. We conclude that there is no merit in either argument. First, on
the matter of credibility, the judge did not make any credibility finding with respect to
the compliance officer's testimony that he gave an "average" rating to the
company's safety program. The judge simply referred to the testimony, in the absence of
any direct testimony that the company's safety program should have been given some
different rating, to help him justify his determination that the violation was not
willful. Second, on the matter of alleged bias, compliance officer Rose testified on at
least two occasions during the hearing that foreman Renna told him that he knew guardrails
were required on the scaffolding, but that he just "hadn't gotten around" to
installing them. Foreman Renna never contradicted this testimony. Nor has the company
claimed that the testimony was inaccurate. Therefore, even if we were to conclude that the
company's allegation of bias against the compliance officer has some merit to it -- and we
do not so conclude -- it would not affect the alleged willfulness of the violation of
section 1926.451(d)(10). Moreover, as we have already noted, that a company's safety
program is average is not dispositive of the willfulness of a violation.

The company also argues that the
violation was not willful because it had hired an employee specifically to construct
guardrails for the scaffolding on the site. In light of the failure of the company's
supervisors to have the guardrails installed, however, this argument is without merit. We
similarly reject the company's argument that guardrails were removed temporarily in order
to bring material up to the scaffold. The unrebutted testimony of compliance officer Rose
is that when he asked foreman Renna if the company was in the process of erecting or
dismantling the scaffold, Renna responded in the negative. Further, foreman Renna's
statement that he had not gotten around to putting up guardrails refutes any suggestion
that all absent guardrails might have been taken down so that material could be brought up
to the scaffold, as opposed to their never having been put up in the first place. We,
therefore, conclude that the violation of section 1926.451(d)(10) was willful.

Penalty

Based on the penalty factors enumerated
in section 17(j), 29 U.S.C. � 666(j), of the Occupational Safety and Health Act, we
assess a penalty of $1000 for the willful violation of section 1926.451(d)(10). Sal
Masonry had a prior history of violating this and other OSHA standards, and the gravity of
this violation was high as an employee could fall from 36 to 42 feet to his death from the
unguarded scaffolding.

Order

Accordingly, we vacate the citation
insofar as it alleges that Sal Masonry violated section 1926.451(a)(13). We find that the
repeated, serious violation of section 1926.451(a)(8) was not willful and leave intact the
judge's $200 penalty assessment for the violation. Lastly, we affirm the repeated, serious
violation of section 1926.451(d)(10) as a willful violation and assess a $1000 penalty.

Edwin G. Foulke, Jr.,

Chairman

Donald G. Wiseman,

Commissioner

Velma Montoya,

Commissioner

Dated: May 7, 1992

SECRETARY OF LABOR.

Complainant,

v.

SAL MASONRY CONTRACTORS, INC.,

Respondent.

OSHRC Docket No. 87-2007

DECISION

This case arose under 29 USC, � 651, et
seq. of the Occupational Safety and Health Act of 1970 (the Act). As a result of an
inspection by the Occupational Safety and Health Administration (OSHA), of the
Respondent's premises on or about May 27, 1987 to November 24, 1987, Citations were issued
on or about November 24, 1987, charging [as amended] that the Respondent violated sec.
5(a)(2) of the Act by the serious violation of the standard at 1926.451(d)(3);
the serious, willful, and repeated violation of the standard at 1926.451(a)(8); the
serious, willful, and repeated violation of the standard at 1926.451(a)(13);
the serious, willful, and repeated violation of the standard at 1926.451(d)(10);
the serious and repeated violation of the standard at 1926.451(a)(14) and the
other than serious violation of the standard at 1926.602(c)(1) (VI) - respectively, Item 1
of Citation 1; Item 1 of Citation 2; Item 2 of Citation 2; Item 3 of Citation 2; Item 1 of
Citation 3; and Item 1 of Citation 4.

On or about December 1, 1987, the
Respondent filed Notice of Contest to said items of the Citations and the penalties
proposed therefor.

The pertinent sections of the Act and
the standards are appended to this decision under appropriate titles.

CITATION 1, ITEM 1

[451 (d) (3)]

The Respondent's labor foreman [Zullo]
and the Complainant's Compliance Officer [Rose], were the main witnesses concerning
whether the scaffolding was properly braced. Although Zullo said the scaffolding was
properly braced, his testimony was weakened by his concession that the bracing wire was
"a little loose" and had "a sag in it"... Tr.II, 275-277. Rose
testified that the scaffold was not properly braced and that it was easily moved
...Tr.144, II-17, 19, 275, 276. I find that the scaffold in question was not properly
braced.

CITATION 2, ITEM 1

[451 (a) (8)]

The uncontradicted evidence established
that the scaffolding had several planks that had been damaged by dry rot and cracks or
splits ...Tr.33, 34, 40, 43, 111, 124-128, 160. I find that some scaffolds so damaged or
weakened had not been immediately repaired or replaced.

CITATION 2, ITEM 2

[451 (a) (13)]

The evidence clearly established that
there was no ladder at the place in question ... Tr. 15, 46, 67, 85, 113, 117, 179.
However, the Respondent contended that there was an "equivalent safe access"
provided by a longer route that made use of a stairwell, scaffolding, and flooring
...Tr.II-207-221, 302-308.

Assuming that the route so described was
an "equivalent safe access" [as indicated at Tr.II-127], that defense would
still be rejected. There is nothing to establish that employees were trained or instructed
to use it to the exclusion of other less safe means of access. Moreover, where [as here]
there are two or more paths of access available to employees, it is unreasonable for an
employer to assume that employees would always use the longer or more inconvenient way.

I find there was no ladder and an
equivalent safe access was not provided.

CITATION 2, ITEM 3

[451 (d) (10)]

The uncontradicted evidence established
that some scaffolds did not have guardrails at all open sides and ends. The Compliance
Officer [Rose] testified that the Respondent's foreman [Renna] conceded the point ...
Tr.47, 48, 208, 225.

I find that some scaffolds did not have
guardrails at all open sides and ends.

CITATION 3, ITEM 1

[451 (a) (14)]

There was no contradiction of the
evidence that established that some scaffold planks extended over their end supports less
than 6 inches or more than

12 inches...Tr.233-240 and Exh. C-33 and C-34.

I find that some scaffold planks
extended over their end supports less than 6 inches or more than 12 inches.

CITATION 4, ITEM 1

[1926.602 (c) (1) (V)]

The Compliance Officer [Rose] testified
that the emergency brake on the vehicle in question was inoperable and that its driver
said it wasn't working properly and should be fixed...Tr.244, II-6, 8, 310. That testimony
was not contradicted.

I find that the vehicle did not meet the
ANSI requirements.

KNOWLEDGE

The Respondent knew, or should have
known, of all the alleged hazardous conditions. All were in plain sight or were admitted
by supervisory personnel of the Respondent ... Tr.15, 109, II-46, 48, 69, 75-78, 327.

HAZARD

Except for the violation alleged in Item
1 of Citation 4 [29 CFR 1926.602 (c)(1)(VI), the hazard consisted of broken bones or death
caused by a fall of 25 feet ... Tr.155,162,181.

DEGREE OF VIOLATION

Four of the citations that alleged
serious violations were amended to include repeated misconduct by the Respondent; and
three of the four were amended to also include its willful misconduct. Was there
justification for "repeated" or "willful" citations?

The POTLATCH case [7 OSHC 1061]
and the FOTI case [10 OSHC 1937] point out that a violation may be characterized as
"repeated" if it is based on the same standard or the same hazard or is
factually substantially similar to an earlier violation. Here, the citations alleged to be
"repeated" were based on the same standard, the same hazard, and substantially
similar facts. I find that the four citations in question were properly characterized as
"repeated" ...Exh.C-8. 13, 21 , 30-32, 35.

To establish that the citations were
willful, the Complainant basically relied on two elements of proof: 1) the earlier
violation of the same standard ... Exh.C-8-10, 13, 21, 30-32, 35 and, 2) testimony that
tended to establish that the Respondent's foreman [Renna] knew that damaged planks from
another jobsite were transported for use in the scaffolds at the jobsite in question ...
Tr.168, II-106, 107.

However, there was also uncontradicted
testimony by supervisory personnel of the Respondent that damaged planks were identified
by paint so they would not be used as regular planks ...Tr.II 311. Distinguishing the
damaged planks in that way would seem to indicate that the Respondent had some regard for
the safety of its employees. Certainly such conduct on the part of the Respondent is
inconsistent with a willful violation.

There is also the testimony of the
Compliance Officer [Rose] that he had rated the Respondent's safety and health program as
average ... Tr.II-172. That certainly is inconsistent with willful violations.

I find that the Respondent did not act
in utter disregard of the safety of its employees, and the Respondent did not
intentionally violate any cited standard.

FINDINGS OF FACT

Having heard the testimony, observed the
witnesses, and examined the exhibits, the following Findings of Fact are made:

  1. At all times concerned, the
    Respondent regularly received, handled or worked with goods which had moved across state
    lines.

  2. As concerns Item 1 of Citation 1, some scaffolding was not properly braced but was
    loose and easily movable.

  3. As concerns Item 1 of Citation 2, some planks had become damaged or weakened but
    had not been immediately repaired or replaced.

  4. As concerns Item 2 of Citation 2, there was no ladder or equivalent safe access.

  5. As concerns Item 3 of Citation 2, some scaffolds had no guardrails.

  6. As concerns Item 1 of Citation 3, some scaffold planks extended over the end
    supports less than 6 inches or more than 12 inches.

  7. As concerns Item 1 of Citation 4, the vehicle's emergency brake was inoperable;
    and the vehicle did not meet the ANSI requirements.

  8. The conditions described in Item 1 of Citation 4 exposed the Respondent's
    employees to sustaining harm because of the hazard of brake not holding.

  9. The conditions described in each Item of Citations 1, 2, and 3 exposed the
    Respondent's employees to sustaining serious or fatal harm because of the hazard of a fall
    of 25 feet.

  10. One or more officers or supervisory personnel of the Respondent knew of the
    hazardous conditions described herein and knew that employees were exposed to such hazard.

CONCLUSIONS OF LAW

  1. At all times concerned, the
    Respondent was an employer engaged in a business affecting commerce within the meaning of
    the Act; and the Occupational Safety & Health Review Commission has jurisdiction over
    the subject matter, and the parties.

  2. At all times concerned, the Respondent knew, or with the exercise of due diligence
    should have known, of the alleged violations.

  3. On the date in question, the Respondent was not in compliance with the standards
    at 29 CFR 1926.451 (a)(8), (a)(13), (a)(14), (d)(3), (d)(10), and 1926.602(c)(1) and the
    Complainant has sustained the burden of proving the Respondent violated sec. 5(a)(2) of
    the Act (sec. 654).

ORDER

The whole record having been considered,
and due consideration having been given to 29 U.S.C. sec. 666(j),

it is ordered:

  1. Item 1 of Citation 1 is affirmed as a serious violation, and a penalty of $100 assessed
    therefor.

  2. Item 1 of Citation 2 is affirmed as a serious and repeated violation, and a
    penalty of $200 assessed therefor.

  3. Item 2 of Citation 2 is affirmed as a serious and repeated violation, and a
    penalty of $200 assessed therefor.

  4. Item 3 of Citation 2 is affirmed as a serious and repeated violation, and a
    penalty of $500 assessed therefor.

  5. Item 1 of Citation 3 is affirmed as a serious and repeated violation, and a
    penalty of $100 assessed therefor.

  6. Item 1 of Citation 4 is affirmed as an other than serious violation, and a penalty
    of zero assessed therefor.

So ordered.

FOSTER FURCOLO

Judge, OSHRC

Dated: October 27, 1988

Boston, Massachusetts

APPENDIX

THE ACT

1.
Section 654
[section 5(a)(2)] Employer
"...shall comply with

occupational safety and health standards..."

2.
Section 666
[section 17(a)] " ... employer
who willfully or

repeatedly violates...this Act ...may be assessed

a civil penalty of not more than $10,000 for each

violation."

3.
Section 666
[section 17(b)] "...employer
who has received a

citation for a serious violation ... of this Act ...

shall be assessed a civil penalty of up to $1,000

for each such violation.

4.
Section 666
[section 17(b)] "...employer
who has received a

citation for a serious violation ... of this Act

...shall be assessed a civil penalty of up to

$1,000 for each such violation."

5.
Section 666
[section 17(c)] "...employer
who has received a

citation for a violation of ...this Act ...

specifically determined not to be of a serious

nature, may be assessed a civil penalty of up

to $1,000 for each such violation."

6.
Section 666
[section 17(j)] "...assess all
civil penalties ...

giving due consideration to...the size of the

business ... gravity of the violation, the good

faith of the employer, and the history of

previous violations."

7.
Section 666
[section 17(k)] "...a serious
violation shall

be deemed to exist...if there is a substantial

probability that death or serious physical harm

could result ... unless the employer did not,

and could not ...know of the presence of the

violation."

STANDARDS

29 CFR 1926.451(a)(8): "Any scaffold including
accessories ...

damaged or weakened from any cause shall be immediately repaired or replaced."

1926.451(a)(13): "An access ladder or equivalent
safe access shall be provided."

1926.451(a)(14): "Scaffold planks shall extend
over their end supports not less than 6 inches nor more than 12 inches."

1926.451(d)(3): "Scaffolds shall be properly
braced...

so that that erected scaffold is always plumb, square, and rigid..."

1926.451(d)(10): "Guardrails shall be installed
at all open sides and ends."

29 CFR 1926.602(c)(1)(Vl): "All industrial
trucks in use shall meet the applicable requirements of...maintenance, and operation, as
defined" in ANSI B 56.1-1969.

FOOTNOTES:

[[1]] The direction for review specified only these
issues. Ordinarily, the Commission does not decide issues that are not directed for
review. 29 C.F.R. �� 2200.92(c), .93(a). We observe that policy here. Therefore, we do
not review those parts of the judge's decision affirming serious and repeated violations
of section 1926.451(a)(8) and section 1926.451(d)(10) in our consideration of whether the
judge erred in not finding those violations willful. See Tampa Shipyards,
Inc., 15 BNA OSHC 1533,1535 n.4,1992 CCH OSHD � 29,617, p. 40,097 n.4 (No.
86-469,1992).

[[2]] Section 1926.451(a)(13) provides:

� 1926.451 Scaffolding.

(a) General requirements.

....

(13) An access ladder or equivalent safe access shall
be provided.

[[3]] Sal Masonry could have complied with the plain
terms of the cited standard by providing its employees with either (1) a ladder
to access the scaffolding or (2) equivalent safe access to the scaffolding. Since the
company's evidence demonstrates that it did provide a ladder and the Secretary has failed
to carry her burden of proving that the company did not provide a ladder, we need not
inquire into whether the alternative, equivalent safe access, was provided.

[[4]] Section 1926.451(a)(8) provides:

� 1926.451 Scaffolding.

(a) General requirements.

....

(8) Any scaffold including accessories such as
braces, brackets, trusses, screw legs, ladders, etc. damaged or weakened from any cause
shall be immediately repaired or replaced.

[[5]] The Secretary provides the following examples
of cases where the Commission found willful violations even though the cited employers had
taken pertinent steps in behalf of employee safety: Ensign-Bickford Co. v. OSHRC ,
717 F.2d 1419 (D.C. Cir. 1983), cert. denied , 466 U.S. 937 (1984); A . Schonbek
& Co. v. Donovan, 646 F.2d 799 (2d Cir. 1981); and Empire-Detroit Steel Div.,
Detroit Steel Corp. v. OSHRC , 579 F.2d 378 (6th Cir. 1978).

[[6 ]] Section 1926.451(d)(10) provides:

� 1926.451 Scaffolding.

....

(d) Tubular welded frame scaffolds.

....

(10) Guardrails made of lumber, not less than 2 x 4 inches (or other material providing
equivalent protection), and approximately 42 inches high, with a midrail of 1 x 6 inch
lumber (or other material providing equivalent protection), and toeboard, shall be
installed at all open sides and ends on all scaffolds more than 10 feet above the ground
or floor. Toeboards shall be a minimum of 4 inches in height. Wire mesh shall be installed
in accordance with paragraph (a)(6) of this section.

[[7]] Sal Masonry's argument that the evidence of its
three prior violations of the cited standard may not be used against the company because
such evidence constitutes unsubstantiated hearsay is rejected. As we noted above, evidence
of prior violations may be used as partial support for a finding of willfulness. See
D.A. & L. Caruso, Inc., 11 BNA OSHC 2138, 1984-85 CCH OSHD � 26,985 (No.
79-5676, 1984). We also note that the company's attorney assented to the existence of all
three violations.

[[8 ]] The Secretary also argues that a willful
violation was established by statements from employees. She relies on employee DeLong's
testimony that he was unable to erect scaffold guardrails bemuse the company did not
provide sufficient material to build them. She further notes that DeLong testified that he
apprised supervisors Zullo and Judge about this and that he was told to do the best he
could. The Secretary also points out employee Swan's testimony that he worked on scaffolds
without guardrails, and that he complained to both the labor foreman and supervisor about
the lack of guardrails, without receiving any response until after the compliance officer
began his inspection. We do not rely on this evidence in finding a willful violation here.
The evidence was essentially contradicted by the testimony of Sal Masonry's supervisory
officials, and the judge failed to resolve the conflict in the testimony.

Get today's answer for your situation

You just read Commission precedent from 1992. Ezel checks whether it still stands, including any court review since, and answers your specific situation, with citations.

Opens in Ezel Pro. Every answer cites the authority it relies on.