OSHRC Commission decision Docket 79-2090 Decided August 27, 1984 Citations vacated

Rust Engineering Company

Split Commission leaves delayed fall-protection citation vacated

Apply this precedent to your situation

This is citable Commission precedent from 1984, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.

Currency note: this decision dates from 1984
The OSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Decision of the Commission
This is a decision of the Occupational Safety and Health Review Commission, the highest level of agency review, citable as Commission precedent. It may have been appealed to a U.S. Court of Appeals after issuance; check subsequent history before relying on it. The full text below is from the official OSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official OSHRC release. The full text is the Commission's own document.
Read the official release (oshrc.gov)

Plain-English summary

OSHA issued Rust Engineering a fall-protection citation 111 days after its inspection. The judge vacated the citation because the delay was unreasonable and prejudiced Rust's defense, and also found that compliance was impossible and would create greater hazards. Chairman Buckley would have affirmed the reasonable-promptness ruling because the delay lacked a sound justification and harmed Rust's ability to defend itself. Commissioner Cleary would have reversed because delay alone was not enough and Rust had not shown meaningful prejudice. The divided Commission vacated the direction for review. The judge's vacation therefore became the final order but retained only the precedential value of an unreviewed ALJ decision.

Decision snapshot

  • Cited standard(s): 29 U.S.C. § 658(a), 29 C.F.R. § 1926.28(a), and 29 C.F.R. § 1926.105(a)
  • Outcome: Direction for review vacated; fall-protection citation remained vacated.
  • Key point: The Commission did not resolve whether the 111-day citation delay was prejudicial, leaving the judge's case-specific ruling final without Commission-precedent weight.

Full text (OSHRC public release)

Docket No. 79-2090

SECRETARY OF LABOR,

Complainant,

v.

RUST ENGINEERING COMPANY,

Respondent.

OSHRC Docket No. 79-2090

DECISION

Before:  BUCKLEY, Chairman, and CLEARY, Commissioner.

BY THE COMMISSION:

This case is before the Occupational Safety and Health Review Commission
under 29 U.S.C. � 661(i), section 12(j) of the Occupational Safety and Health Act of
1970, 29 U.S.C. �� 651-678 ("the Act").  The Commission is an
adjudicatory agency, independent of the Department of Labor and the Occupational Safety
and Health Administration.  It was established to resolve disputes arising out of
enforcement actions brought by the Secretary of Labor under the Act and has no regulatory
functions.  See section 10(c) of the Act, 29 U.S.C. � 659(c).

A citation issued to Rust Engineering Company alleged violations of the fall
protection standards contained at 29 C.F.R. �� 1926.28(a) and 1926.105(a).  An
administrative law judge vacated the citation based on a finding that it was not issued
with "reasonable promptness" as required by section 9(a) of the Act, 29 U.S.C.
� 658(a).[[1]]  In the judge's view, the delay of 111 days between the inspection
and the issuance of the citation was both prejudicial to the employer's ability to prepare
and present a defense and unreasonable to the point of unconscionability.  The judge
entered alternative findings on the merits of the citation and concluded that the citation
should be vacated because the employer established that compliance with the standards
would be impossible and would expose its employees to greater hazards.

The two participating Commission members are divided on whether the judge's
decision on the issue of reasonable promptness should be affirmed or reversed.[[2]]
 Appellate and Commission, precedent establish that a citation may be vacated on
reasonable promptness grounds upon a showing of prejudice to the employer.  See
Stripe-A-Zone, Inc ., 82 OSAHRC 31/E13, 10 BNA OSHC 1694, 1982 CCH OSHD � 26,069
(No. 79-2380, 1982)(citing appellate and Commission decisions); Todd Shipyards Corp. v .
Secretary of Labor , 566 F.2d 1327, 1330 (9th Cir. 1977).  Chairman Buckley
would affirm the judge's decision because the reasons advanced by the Secretary for the
111 day delay were not reasonable, and because, as the judge found, the failure of the
inspecting compliance officer to inform Rust Engineering Company during this 111 day
period that a citation might issue seriously prejudiced Rust's ability to properly defend
against the charge.[[3]]

Commissioner Cleary would reverse the judge's reasonable promptness ruling.  Contrary
to the judge's decision, a delay in issuing a citation is not per se a ground under
Commission precedent to vacate the citation.[[4]]  Instead, the Commission has
required employers claiming that a citation was issued without reasonable promptness to
show that the delay prejudiced the employer's ability to prepare and present a
defense.[[5]]  The courts or appeals have agreed with this approach.  The Ninth
Circuit has stated:

Even if we were not bound to yield to the Secretary and the Commission a
relatively broad discretion in interpreting the Act, The Budd Co. v. OSHRC ,
513 F.2d 201, 204-205 (3rd Cir. 1975), we would still be compelled to recognize the merit
of this approach. It is very much in keeping with the remedial purpose of the Act . . . .
To vacate a citation because of delay that is less than prejudicial would clearly run
counter to the concern for safe working conditions that led to the enactment of OSHA.

Todd Shipyards Corp. v. Secretary of Labor , 566 F.2d 1327, 1330 (9th
Cir. 1977).  See also Brennan v. Chicago Bridge and Iron Co .,
514 F.2d 1082 (7th Cir. 1975).  Commissioner Cleary also finds that Rust did not show
that the delay was prejudicial.  He would observe first that a delay of 111 days is
hardly apt to be prejudicial.  Because long statutes of limitations are common in
legal jurisprudence, lawsuits are frequently filed years after alleged wrongs occurred.
  Lawyers are able to and are accustomed to then locating witnesses and documents.
 Reconstruction of events and conditions after several years does not normally
present a serious obstacle to litigation of cases.  Viewed in this light, a delay of
111 days is negligible.  Though it is a significant fraction of the Act's six-month
limitations period, it is too short to pose a serious prospect of prejudice in all but the
most unusual case.  Yet, this case is hardly unusual.  Rust had located its
witnesses and they were prepared to testify.  In other respects, this record shows
nothing more than the usual amount of difficulty that any defense lawyer can expect to
encounter in preparing a defense.  See Havens Steel Co. v. OSHRC ,
No. 82-2261 (10th Cir. July 9, 1984)(slip op. at 5-7).

In view of the impasse as to the issue before the Commission for review,
Chairman Buckley and Commissioner Cleary have agreed to vacate the direction for review.
  E.g ., Texaco, Inc. , 80 OSAHRC 74/B1, 8 BNA OSHC 1758, 1980 CCH OSHD

� 24,634 (Nos. 77-3040 & 77-3542, 1980).  The Commission members have discretion
under the Act and the Commission's Rules of Procedure to direct review of a judge's
decision.  Section 12(j), 29 U.S.C. � 661(i); 29 C.F.R. � 2200.92.  In the
absence of a direction for review, the judge's decision becomes a final order of the
Commission and can be appealed by an aggrieved party to a United States court of appeals.
  Sections 10(c), 11(a) and (b) and 12(j), 29 U.S.C. �� 659(c), 660(a) and (b),
661(i).  The judge's decision in this case therefore becomes the appealable final
order of the Commission, but is accorded the precedential value of an unreviewed judge's
decision.

FOR THE COMMISSION

Ray H. Darling, Jr.

Executive Secretary

DATED: AUG 27 1984

The Administrative Law Judge decision in this matter is unavailable in this
format.  To obtain a copy of this document, please request one from our Public
Information Office by e-mail ( [email protected]
), telephone (202-606-5398), fax (202-606-5050), or TTY (202-606-5386).

FOOTNOTES:

[[1]] Section 9(a) provides in part:

If, upon inspection or investigation, the Secretary or his authorized
representative believes that an employer has violated a requirement of section 5 of this
Act, of any standard, rule or order promulgated pursuant to section 6 of this Act, or of
any regulations prescribed pursuant to this Act, he shall with reasonable promptness issue
a citation to the employer.

[[2]] As established by the Act, the Commission is composed of three members.
  Section 12(a), 29 U.S.C. � 661(a).  Under section 12(f) of the Act, 29 U.S.C.
� 661(e), official action can be taken by the Commission with the affirmative vote of at
least two members.  Currently, the Commission is composed of two members, due to a
vacancy.

[[3]] In Chairman Buckley's view, citations issued after "patently
unreasonable, unnecessary and unjustified" delays should be vacated to fully
implement the statutory requirement that citations be issued with reasonable
promptness.  See Stripe-A-Zone , 10 BNA OSHC at 1696, 1982 CCH OSHD at
p. 32,782 (concurring opinion).  Vacation of citations issued after such delays will
promote the prompt issuance of citations and ultimately advance the Act's objectives of
rapid abatement to protect employees following prompt adjudication of contested
cases.  Atlas Roofing Co. v. OSHRC , 430 U.S. 442, 461 (1977); Gilbert Manufacturing
Co ., 79 OSAHRC 68/A2, 7 BNA OSHC 1611, 1613, 1979 CCH OSHD � 23,782, p. 28,846 (No.
76-4719, 1979).  Here the administrative law judge correctly found that the reasons
offered by the Secretary for the delay were meritless.

[[4]] See , in addition to Stripe-A-Zone , National Industrial
Constructors, Inc ., 81 OSAHRC 94/A2, 10 BNA OSHC 1081, 1981 CCH OSHD � 25,743 (No.
76-4507, 1981), and Stearns-Roger, Inc. , 80 OSAHRC 103/A2, 8 BNA OSHC 2180, 1980
CCH OSHD � 24,870 (No. 76-819, 1980).

[[5]] Id .