Westinghouse Electric Corporation (Commission decision, December 11, 1980)

A spray room may be established by sufficient separation rather than exclusive use, so the case returns for evidence on how separate the operation was

Decision type
Commission decision
Docket
13955
Decided
December 11, 1980
Outcome
Remanded
Precedential status
Citable Commission precedent
Checked against source
2026-09-11
Cited standards

Apply this precedent to your situation

This is citable Commission precedent from 1980, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.

Currency note: this decision dates from 1980
The OSHA standards may have been amended, penalty amounts have been adjusted, and later Commission or court decisions may have changed the analysis since then. Treat this page as historical context, not current compliance advice. Verify the current standard before relying on any specific rule, threshold, or penalty mentioned here.
Decision of the Commission
This interlocutory remand order sent the case back to the judge for evidence and a new determination about whether the spray operation was sufficiently separated. That issue remained unresolved, so the order did not finally dispose of the case. The full text below is from the official OSHRC release.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official OSHRC release. The full text is the agency's own release.
Read the official release (oshrc.gov)

Plain-English summary

A short order carrying out a court of appeals remand. Nothing is decided on the merits.

The standard at 29 C.F.R. § 1910.94(c)(2) requires that spray booths or spray rooms enclose or confine all spray finishing operations. Westinghouse was not using a spray booth, so the case turned entirely on whether it had a spray room, defined at § 1910.94(c)(1)(iii) as a room in which spray finishing operations not conducted in a spray booth are performed separately from other areas.

In 1979 a divided Commission found noncompliance. The majority held the operation was not adequately confined because there was no spatial or physical separation between the spray finishing room and other production activities. Commissioner Barnako dissented on a narrower point: the definition does not say whether separation requires any minimum distance, the Secretary offered neither evidence nor argument about what "performed separately from" demands in terms of proximity, and on that record the Secretary had not carried the burden.

The Seventh Circuit vacated. It held that § 1910.94(c)(2) does not necessarily require spray finishing to happen in a room where nothing else takes place; a sufficient spatial or physical separation between the spray finishing and other activities might satisfy the standard. The court observed that under that reading the majority and the dissent could possibly be reconciled, and that the record had not been developed for the question and could not support a determination either way. Westinghouse Electric Corp. v. OSHRC, 617 F.2d 497 (7th Cir. 1980).

The Commission therefore returns the case to Administrative Law Judge Sidney J. Goldstein, who heard it originally, so the parties can put on additional evidence and argument about how separate the spray finishing operation was from the rest of the facility, and so he can decide whether it was performed in a spray room within the meaning of § 1910.94(c)(1)(iii).

Decision snapshot

  • Cited standard(s): 29 C.F.R. § 1910.94(c)(2), spray finishing confined
    to a booth or room
  • Outcome: Remanded to the judge who first heard the case, for further
    evidence and a new determination.
  • Key point: A spray room is defined by separation, not by exclusive use.
    Because separation is a matter of degree and the standard sets no distance, the Secretary has to develop evidence on it rather than rely on the presence of other activities nearby.

Full text (OSHRC public release)

Johnson, Dawn Adair
Normal
OChair
2
155
2018-01-09T19:14:00Z
2018-01-09T19:14:00Z
1
515
2941
24
6
3450
16.00

false
false
false

EN-US
X-NONE
X-NONE

UNITED STATES OF AMERICA

OCCUPATIONAL SAFETY AND HEALTH REVIEW COMMISSION

SECRETARY
OF LABOR,

Complainant,

v.

OSHRC
DOCKET NO. 13955

WESTINGHOUSE
ELECTRIC CORPORATION,

Respondent.

December 11, 1980

ORDER

Before CLEARY, Chairman; BARNAKO and COTTINE,
Commissioners.

BY THE COMMISSION:

In
our prior decision in this case, a divided Commission concluded that Respondent failed to comply with the standard at 29 C.F.R. 1910.94(c)(2), which requires that spray booths or spray rooms be used to enclose or confine all spray finishing operations. Westinghouse Electric Corp., 79 OSAHRC 28/B8, 7 BNA OSHC 1318, 1979 CCH OSHD 23,542 (No. 13955, 1979). The majority based its conclusion that Respondent�s spray finishing operation was not adequately confined on its finding that there was no spatial or physical separation of the spray finishing room from other production activities. Id., 7 BNA OSHC at 1323, 1979 CCH OSHD at 28,521. [*] In dissent, Commissioner Barnako stated:

The definition of a spray room does not
state whether or not �separation� requires a certain minimum distance and the Secretary offered no evidence or argument from which it can be concluded that
�performed separately from� does or does not contemplate any particular proximity. In such circumstances I would conclude that the Secretary failed to establish that Respondent�s operations were not performed separately from other areas. (Footnote omitted).

Id., 7 BNA OSHC at 1324�25,
1979 CCH OSHD at 28,522.

On
appeal, the United States Court of Appeals for the Seventh Circuit concluded that section 1910.94(c)(2) does not necessarily require spray-finishing operations to be conducted in a room in which no other activities take place but might be satisfied by a sufficient spatial or physical separation between the spray finishing operation and other activities. Westinghouse Electric Corp. v. OSHRC, 617 F.2d 497 (7th Cir. 1980). The court noted that the Commission�s majority and dissenting opinions possibly could be reconciled under the court�s interpretation. The court further concluded that �[t]he record was not developed for the purpose and is not sufficient to support a determination of whether or not the location of the Westinghouse spray painting is sufficiently separated from other activities in the particular circumstances so as to qualify as being conducted in a spray room.� Id. at 503. Accordingly, the court vacated our prior decision and remanded to us �for further proceedings consistent with this opinion to determine whether or not the spray painting is being conducted in a spray room.� Id. at 503.

The
court�s decision requires that the parties be afforded an opportunity to present further evidence relevant to the separation of Respondent�s spray-finishing operation from other activities in its facility. Accordingly, the case is remanded to Administrative Law Judge Sidney J. Goldstein, who heard the case in the first instance, to afford the parties the opportunity to present additional evidence and argument on this point and to determine whether Respondent�s spray painting operation was performed in a spray room within the meaning of 29 C.F.R.  1910.94(c)(1)(iii).

SO ORDERD.

FOR THE COMMISSION:

RAY H. DARLING, JR.

EXECUTIVE SECRETARY

BY: Gloria W. White

Acting Executive Secretary

DATED:
DEC 11, 1980

[*] The record
establishes that Respondent�s spray finishing operation was not performed in a spray booth. The dispute in this case centers over whether the operation was performed in a spray room, which is defined as �a room in which spray-finishing operations not conducted in a spray booth are performed separately from other areas.� 29 C.F.R. 1910.94(c)(1)(iii).

Does this precedent still control your case?

Ezel checks whether it still stands, including any court review since, and applies it to your situation with citations.

Opens in Ezel Pro.

  • Checks the law as it stands today, not only this page
  • Cites every source it relies on, so you can verify it
  • Chat, drafting and research in one workspace