N. Picco & Sons Contracting Co., Inc.
Scaffold and housekeeping violations affirmed
Apply this to your situation
This order from 2003 bound only the parties to this case; it isn't precedent. Ezel answers your situation under the current OSHA standards and Commission precedent, with citations.
Plain-English summary
N. Picco & Sons was constructing a three-story addition to a school in Bronxville, New York. OSHA observed two employees working 36 and 42 feet above ground on a scaffold with improper fall-arrest anchorage, incomplete planking, an excessive gap from the building, and no suitable access. The judge rejected Picco's employee-misconduct defense because the company did not establish preventive work rules, communication, monitoring, and effective enforcement. He affirmed all four scaffold items as serious and assessed a grouped $5,000 penalty. A debris-housekeeping item was affirmed as other-than-serious with no penalty.
Decision snapshot
- Cited standard(s): 29 C.F.R. §§ 1926.502(d)(15)(ii), 1926.451(b)(1), 1926.451(b)(3), 1926.451(e)(1), and 1926.25(a)
- Outcome: Four serious scaffold violations and one other-than-serious housekeeping violation were affirmed; $5,000 was assessed.
- Key point: An employee-misconduct defense requires proof of established rules, communication, monitoring, and enforcement, not only a claim that employees worked in the wrong location.
Full text (OSHRC public release)
SECRETARY OF LABOR,
Complainant,
v. OSHRC DOCKET NO. 02-2200
N.PICCO & SONS CONTRACTING
COMPANY, INC.,
Respondent.
Appearances:
Margaret A. Temple, Esquire Rowland A. Riccardi
U.S. Department of Labor N. Picco & Sons Contracting
Office of the Solicitor Company, Inc.
New York, New York Mamaroneck, New York
For the Complainant. For the Respondent, pro se.
Before: Irving Sommer
Chief Judge
DECISION AND ORDER
This proceeding is before the Occupational Safety and Health Review Commission (“the
Commission”) pursuant to section 10(c) of the Occupational Safety and Health Act of 1970, 29
U.S.C. § 651 et seq. The Occupational Safety and Health Administration (“OSHA”) conducted an
inspection of Respondent’s work site, located in Bronxville, New York, on October 9, 2002; the
work at the site involved the construction of a three-story addition to an existing school building, and
OSHA had received a complaint about the scaffolding being used at the site. As a result of the
inspection, OSHA issued to Respondent a Citation and Notification of Penalty (“Citation”) on
October 25, 2002, alleging various violations of OSHA’s construction standards; the four alleged
serious violations were grouped and proposed a total penalty of $5,000.00, and the one alleged
“other” violation did not propose a penalty. Respondent timely contested the Citation, and this case
was designated for E-Z Trial pursuant to Commission Rule 203(a).
2
After notice to both parties, a hearing in this matter was held on June 3, 2003. Although the
Secretary’s counsel appeared with her witness for the hearing, no one appeared on behalf of
Respondent; as a consequence, the Secretary’s motion for a default judgment was granted in a
decision and order issued on June 11, 2003. On June 27, 2003, the Commission received a letter
from Respondent indicating that it had not received notice of the June 3 hearing and requesting that
another hearing be scheduled. The undersigned issued an order vacating and setting aside the June
11 decision and order and scheduling another hearing for July 30, 2003. A representative of
Respondent appeared at the July 30 hearing, and the Secretary and her witness also appeared.
The OSHA Compliance Officer’s Testimony
Angelo Signorile, the OSHA compliance officer (“CO”) who conducted the inspection,
testified that upon arriving at the site, he held an opening conference with Rowland Riccardi, the
project manager for Respondent (“Picco”), and Robert Phelan, Picco’s job site superintendent; also
present were the carpentry and masonry shop stewards.1 The CO then began his inspection,
accompanied by Mr. Riccardi and the two shop stewards. On the south side of the building, the CO
observed two employees who were standing on tubular welded frame scaffolding in order to put
insulation on the building under construction; one employee was on the sixth level of the scaffolding,
about 36 feet from the ground, and the other employee was on the seventh level, about 42 feet from
the ground.2 The CO noted that the employees wore harnesses and that their lanyards were tied off
to the frame of the scaffolding, as shown in photo G-1; he further noted that the employees also tied
off to the cross bracing as they moved to other parts of the scaffold to work. When the CO asked if
he was familiar with anchorage points for fall arrest systems on scaffolds, Mr. Riccardi indicated that
he was not, even though he had told the CO that he was the qualified person at the site and knew the
OSHA regulations. The CO testified that the condition was hazardous; Mr. Riccardi could not tell
him if the scaffold could withstand the weight of a falling person, and, if an employee had fallen, the
scaffold could have collapsed. (Tr. 9-20).
1
Mr. Riccardi also told the CO that he was the general superintendent on the site. (Tr. 12).
2
Mr. Riccardi informed the CO that the workers were Picco employees. (Tr. 18-19).
3
The CO testified about three other conditions on the scaffold that were a hazard. First, the
scaffold was not fully planked to provide a safe work platform; the areas where the employees were
working had only two planks, as shown in photo G-2, and, if a worker had misstepped or lost his
balance, he could have fallen from the scaffold. Second, the planks the employees used as work
platforms were more than 14 inches from the face of the building, as shown in photo G-3, exposing
the workers to falls between the planks and the building. 3 Third, the CO did not see a ladder to
access the scaffold. Mr. Riccardi took him inside the building and up to the third floor, where they
saw the employees coming down from the scaffold; to do so, the employees jumped from the
scaffold into an opening in the wall and then jumped over a cable and onto the third floor. The CO
said that the condition exposed the workers to falls and serious injury. The CO indicated that Mr.
Riccardi agreed with all of his determinations with respect to the scaffold and that he abated the
hazards by having the employees come down; Mr. Riccardi also agreed to install safety lines so that
each employee could be independently attached to a safety line, and he and the CO discussed how
to abate the access ladder violation. (Tr. 20-28).
The final condition that the CO observed was debris, shown in photos G-5-7, that was
scattered underneath the scaffold on which the employees were working. The CO stated that the
debris consisted of bricks and insulation that could have exacerbated injuries if employees had fallen
from the scaffold; the debris could also have caused the employees to trip and fall. The CO further
stated that Mr. Riccardi told him the materials belonged to Picco and that he (Mr. Riccardi) had the
employees begin picking up the materials. (Tr. 29-30; 33-34).
Serious Citation 1
Item 1a of Citation 1 alleges a violation of 29 C.F.R. 1926.502(d)(15)(ii), which requires
anchorages for attachment of personal fall arrest equipment to be under the supervision of a qualified
person. Item 1b of Citation 1 alleges a violation of 29 C.F.R. 1926.451(b)(1), which requires
platforms on working levels of scaffolds to be fully planked or decked. Item 1c of Citation 1 alleges
a violation of 29 C.F.R. 1926.451(b)(3), which requires the front edge of all scaffold platforms to
not be more than 14 inches from the face of the work. Item 1d of Citation 1 alleges a violation of 29
3
The CO indicated that he measured the distance between various planks and the face of the
building at the ground level and determined that the distance, on average, was 18 inches. (Tr. 23).
4
C.F.R. 1926.451(e)(1), which requires ladders or other suitable means of access to be used when
scaffold platforms are more than 2 feet above or below a point of access.
The testimony of the CO, set out above, establishes a prima facie violation of each of the
foregoing cited standards. At the hearing, however, Mr. Riccardi testified that the scaffolding the CO
observed was under erection and that the two employees should not have been working there. He
also testified that the masonry shop steward asked the job site foreman what the employees were
doing there, and the foreman replied that the employees were supposed to be working on a scaffold
on the north side of the building. Mr. Riccardi said that after the employees came down from the
scaffold, he called Edward Cooke, the delegate for Carpenters Local 11. Mr. Cooke interviewed the
employees and talked to them about employee misconduct; he also asked them who instructed them
to work on the scaffold, and they told him that they had just wanted to finish that one area and that
they had thought it was a critical area. It was Mr. Riccardi’s understanding that the employees had
been sent to additional OSHA training offered by Carpenters Local 11. (Tr. 35-39).
Mr. Riccardi said he had discussed the above with OSHA in a phone conference after the
citation was issued. He also said he had a letter documenting the employee misconduct that he had
sent Mr. Cooke. Mr. Riccardi did not have the letter with him at the hearing, but he was advised that
he could submit a copy of the letter to the Secretary and to my office after the hearing. (Tr. 38-41).
Mr. Riccardi did in fact provide the letter, and it has been received in evidence as R-1. The letter is
dated August 16, 2002, it is addressed to Edward Cooke at the Empire State Regional Council of
Carpenters, Local 11, and it is essentially consistent with Mr. Riccardi’s testimony.
Notwithstanding Mr. Riccardi’s testimony and R-1, I conclude that Picco has not rebutted
the Secretary’s prima facie case, for the following reasons. First, the CO testified that Mr. Riccardi
said nothing to him during the inspection about the scaffold on the south side being under erection.
He said that he and Mr. Riccardi had walked by the west side of the building, where scaffold erection
was taking place, and that he had talked to Mr. Riccardi about how employees should tie off during
scaffold erection; however, as the employees were working on the first frame, he did not address that
scaffold. The CO also said he had asked Mr. Riccardi to indicate to him the area in question and that
Mr. Riccardi had told him it was the scaffold on the south side. (Tr. 32-33; 41-42). I observed the
demeanor of the CO as he testified, and I found him to be a sincere and credible witness.
5
Second, even assuming that all of the events that Mr. Riccardi described occurred, albeit after
the inspection had taken place, there is no basis for vacating the citation items. To prove that a
violation was the result of unpreventable employee misconduct, the employer must show that it has
established work rules designed to prevent the violation, that it has adequately communicated the
rules to its employees, that it has taken steps to discover violations, and that it has effectively
enforced the rules when violations have been discovered. Jensen Constr. Co., 7 BNA OSHC 1477,
1479 (No. 76-1538, 1979). Picco has not met its burden of demonstrating that the violations in this
case were due to unpreventable employee misconduct.
Based on the foregoing, Picco was in violation of the cited standards, and Items 1a through
1d of Citation 1 are accordingly affirmed as serious violations. As noted supra, these four items were
grouped for penalty purposes, and a total penalty of $5,000.00 has been proposed. The CO discussed
how his office arrived at the proposed penalty, and, in view of his testimony and the record as a
whole, I conclude that a penalty of $5,000.00 is appropriate. (Tr. 28-29). The proposed penalty is
therefore assessed.
“Other” Citation 2
Item 1 of Citation 2 alleges a violation of 29 C.F.R. 1926.25(a), which requires debris to be
kept cleared from work areas and in and around buildings or other structures. The CO’s testimony
set out above establishes a prima violation of the cited standard. Mr. Riccardi testified that the brick
under the scaffolding belonged to Picco but that the other materials belonged to other contractors at
the site. (Tr. 36). However, as indicated supra, the CO testified that Mr. Riccardi told him that the
materials under the scaffolding were Picco’s, and he denied that Mr. Riccardi told him that only the
bricks belonged to Picco; the CO also testified that Mr. Riccardi had his employees start picking up
the materials. (Tr. 30; 33-34). Based on the record as a whole and my credibility determination
supra, I find that Picco was in violation of the cited standard. Item 1 of Citation 2 is affirmed as an
“other” violation. No penalty was proposed, and none is assessed.
6
Conclusions of Law
1. Respondent was in serious violation of 29 C.F.R. §§ 1926.502(d)(15)(ii), 1926.451(b)(1),
1926.451(b)(3) and 1926.451(e)(1), as set out in Items 1a through 1d, respectively, of Citation 1.
2. Respondent was in “other” violation of 29 C.F.R. § 1926.25(a), as set out in Item 1 of
Citation 2.
Order
Based upon the foregoing Findings of Fact and Conclusions of Law, it is ordered that:
1. Items 1a through 1d of Citation 1 are AFFIRMED as serious violations, and a total penalty
of $5,000.00 is assessed for these items.
2. Item 1 of Citation 2 is AFFIRMED as an “other” violation, and no penalty is assessed for
this item.
/S/
Irving Sommer
Chief Judge
Date: October 2, 2003
Washington, D.C.
Get today's answer for your situation
You just read what one judge decided for one employer in 2003, and it binds only those parties. Ezel checks the current OSHA standards and Commission precedent and answers your specific situation, with citations.
Opens in Ezel Pro. Every answer cites the authority it relies on.