American Federation of Government Employees, Local 916 and Department of the Air Force, Tinker Air Force Base (Authority decision, January 24, 1990)

Tinker Air Force Base (FLRA 0-AR-1728): Late grievance appeal remains dismissed

Decision type
Authority decision
Docket
0-AR-1728
Decided
January 24, 1990
Outcome
Upheld
Precedential status
Citable Authority precedent
Checked against source
2026-10-04

Apply this precedent to your situation

This is citable Authority precedent from 1990, and it may have been appealed since. Ezel checks how it stands today and answers your situation, with citations.

Currency note: this decision dates from 1990
The federal labor-relations law may have been amended, and later Authority or court decisions may have changed the analysis since then. Treat this page as historical context, not current advice. Verify current law before relying on any specific rule mentioned here.
About this page: The plain-English summary and decision snapshot below were written by Ezel based on the official FLRA release. The full text is the agency's own release.
Read the official release (flra.gov)

Final FLRA decision. The Authority denies the union's exceptions to an arbitration award dismissing a grievance as procedurally nonarbitrable. Under 5 U.S.C. § 7123(a)(1), an order involving an arbitral award is generally excluded from judicial review unless it involves an unfair labor practice under 5 U.S.C. § 7116. This decision does not decide an unfair labor practice.

Plain-English summary

An employee at Tinker Air Force Base grieved a ten-day suspension. The union delivered its next appeal to the commander's office within the contract's ten-day period, but the employee relations division received it after that period. An arbitrator ruled that the agreement required timely receipt by the employee relations division and dismissed the grievance without reaching whether the suspension was justified. The union challenged that interpretation and asserted a legal error. The Authority found that the exceptions only disagreed with the arbitrator's procedural timeliness ruling and denied them.

Decision snapshot

  • Authority: Arbitration exceptions under 5 U.S.C. § 7122(a).
  • Outcome: Union's exceptions denied; dismissal of the suspension grievance stands.
  • Key point: Disagreement with the arbitrator's interpretation of the grievance filing deadline did not establish a deficient award.

Full text (FLRA public release)

[ v34 p551 ]
34:0551(93)AR

The decision of the Authority follows:

34 FLRA No. 93

FEDERAL LABOR RELATIONS
AUTHORITY

WASHINGTON, D.C.

AMERICAN FEDERATION OF GOVERNMENT
EMPLOYEES

AFL-CIO

LOCAL 916

and

DEPARTMENT OF THE AIR
FORCE

TINKER AIR FORCE
BASE

0-AR-1728

DECISION

January 24, 1990

Before Chairman McKee and Members Talkin and
Armendariz.

I. Statement of the Case

This matter is before the Authority on exceptions to the award of Arbitrator Richard F. Dole, Jr. The Arbitrator determined that the appeal of American Federation of Government Employees, AFL-CIO, Local 916 (the Union) to step 3 of the negotiated grievance procedure was untimely and that, consequently, the case was not procedurally arbitrable. Accordingly, the Arbitrator dismissed the grievance.

The Union filed exceptions under section 7122(a) of the Federal Service Labor-Management Relations Statute (the Statute) and part 2425 of the Authority's Rules and Regulations. Tinker Air Force Base (the Activity) did not file an opposition to the Union's exceptions.

For the reasons stated below, we conclude that the Union's exceptions provide no basis for finding the award deficient. Accordingly, we will deny the exceptions.

II. Background and the Arbitrator's
Award

By notice dated January 4, 1988, the Activity notified the grievant of its decision to suspend the grievant for 10 days for "abusive and offensive language, and insolence on 2 September 1987." Arbitrator's Award at 1. On January 5, the grievant filed a grievance protesting the suspension. The Activity denied the grievance at step 2 of the negotiated grievance procedure on February 9 and the decision was received by the Union on February

  1. The Union's appeal of the grievance to step 3 of the negotiated grievance
    procedure was received in the office of the Activity's commander on February 18, but was not received by the employee relations division until February 23.

The grievance was not resolved and was submitted to arbitration on the following issues:

  1. Is the grievance arbitrable?

  2. If so, was the 10-day suspension for just
    cause?

  3. If not, what is the appropriate
    remedy?

Id. at 3.

The Arbitrator concluded that the Union's appeal to step 3 was untimely. The Arbitrator determined that Article 6, Section 6.07(c) of the parties' collective bargaining agreement requires receipt of a Union appeal by the employee relations division within 10 calendar days following the Union's receipt of a step 2 decision in order to be timely. The Arbitrator noted that under section 6.07(c), the Union is entitled to file a copy of the appeal in the commander's office. However, the Arbitrator determined that the filing with the commander does not satisfy the contractual requirement to file with the employee relations division within the 10-day deadline.

The Arbitrator determined that, under the agreement, the commander's office is not required to forward a step 3 appeal. The Arbitrator held that when the commander's office forwards an appeal within the 10-day deadline, the transmittal would satisfy the contractual requirement, but when the commander's office does not forward an appeal within the 10-day deadline, the appeal is untimely and the grievance is not arbitrable.

Because the Union did not file its step 3 appeal with the employee relations division and the commander's office did not transmit the Union's step 3 appeal to the employee relations division within the 10-day deadline of Article 6, Section 6.07(c), the Arbitrator ruled that: (1) the Union's step 3 appeal was untimely; and (2) the grievance was not procedurally arbitrable. Accordingly, the Arbitrator dismissed the grievance.

III. Exceptions

The Union contends that the award is: (1) contrary to and not within the intent of the parties' collective bargaining agreement; and (2) contrary to law.

IV. Discussion

We conclude that the Union has not established that the Arbitrator's award is deficient on any of the grounds set forth in section 7122(a) of the Statute. The Union has failed to establish that the award is contrary to any law, rule, or regulation or that the award is deficient on other grounds similar to those applied by Federal courts in private sector labor relations cases.

The Union's contentions that the award is not within the intent of the parties' collective bargaining agreement and that it is contrary to law provide no basis for finding the award deficient. These contentions constitute nothing more than disagreement with the Arbitrator's ruling on the procedural arbitrability issue of whether the Union's step 3 appeal was timely filed and provide no basis for finding the award deficient. American Federation of Government Employees, Local 1915 and Wm. Jennings Bryan Dorn Veterans Hospital, Columbia, S.C., 32 FLRA 1223 (1988) (denial of exceptions which merely disagree with an arbitrator's determination on a procedural arbitrability question is consistent with the decisions of Federal courts in private sector labor relations cases).

As the Union's exceptions provide no basis for finding the award deficient, we will deny the exceptions.

V. Decision

The Union's exceptions are denied.

FOOTNOTES:
(If blank, the decision does not
have footnotes.)

Does this precedent still control your case?

Ezel checks whether it still stands, including any court review since, and applies it to your situation with citations.

Opens in Ezel Pro.

  • Checks the law as it stands today, not only this page
  • Cites every source it relies on, so you can verify it
  • Chat, drafting and research in one workspace