Could the New Orleans convention center waive a bidder's missing builder's risk insurance proof?

Short answer No. The AG said this project's bid form and instructions made proof of every required insurance coverage mandatory, including builder's risk; omitting it was a substantive bid deviation the owner could not waive.
State
Louisiana
Opinion
La. Atty. Gen. Op. 03-0401
Issued
October 29, 2003
Issued by
Richard P. Ieyoub, Attorney General of Louisiana
Requested by
Lambert C. Boissiere, Jr., Louisiana State Senator

Apply this to your situation

This page answers the general question as of 2003. Ask about yours and see what current Louisiana law means for your facts, with citations you can check.

Disclaimer: This is a historical Louisiana Attorney General opinion. AG opinions are advisory and are not binding court precedent. This page is informational and is not legal advice.
About this page: The plain-English summary, reader guidance, and Q&A below were written by Ezel based on the official AG opinion. The original opinion (linked on this page as an official web page) is the authoritative source for any reliance.
View original AG opinion (official page)

Plain-English summary

For the New Orleans Convention Center's Phase IV construction bid, the bid form required bidders to attach insurance certificates or statements of insurability. In Opinion 03-0401, the Louisiana AG said those documents were mandatory for all insurance coverages required by the project's supplementary conditions, including builder's risk coverage.

The AG concluded that a bidder's failure to supply the builder's risk certificate or statement was a substantive departure from the bid documents. The owner could not waive that missing proof as a minor informality. The opinion applied the public bid law and the particular wording of this project's bid form and instructions.

Currency note

This opinion was issued in 2003. Subsequent statutory amendments, court decisions, or later AG opinions may have changed the analysis. Treat this page as historical context, not current legal advice. Verify current law before relying on any specific rule, deadline, or remedy mentioned here.

What the opinion meant at issuance

Convention center procurement officials

The AG read Exhibit No. 2 of the bid form and Article 14.1 of the instructions as requiring certificates or statements of insurability with bids for every coverage in Article 11. It said the owner could not excuse a missing builder's risk document as an informality for one bidder.

Construction bidders

For this project, the AG said a bidder had to attach proof for all specified insurance coverages when submitting a bid. The project documents required a certificate or a statement of insurability; the opinion did not say a bidder had to attach an issued policy itself.

Common questions

Could the convention center waive missing builder's risk insurance proof?

No. The AG called that omission a substantive deviation from the construction documents that could not be waived.

Was the insurance-document requirement limited to one type of coverage?

No. The AG interpreted the bid form and instructions to cover all insurance listed in Article 11 of the supplementary conditions.

Did a bidder have to submit an insurance certificate rather than a statement of insurability?

The project documents, as quoted in the opinion, allowed certificates of insurance or statements of insurability acceptable to the owner.

Why did the AG treat the omission as substantive?

The bid form and instructions used mandatory language, and the AG read the public bid law as barring waiver of substantive requirements imposed on all bidders.

Background and statutory framework

Senator Lambert C. Boissiere, Jr. asked about the Phase IV bids for the Ernest N. Morial New Orleans Convention Center. The bid form and Article 14.1 of the instructions required insurance certificates or acceptable statements of insurability with each bid. The supplementary conditions listed the coverages, including builder's risk.

The AG relied on La. R.S.38:2212 and its quoted nonwaiver provision, La. R.S.38:2212A(1)(b). It read the bid documents as mandatory and said the owner could not waive a missing certificate or statement for builder's risk coverage. The letter tied that result to common standards and equal treatment in public bidding.

Citations and references

  • La. R.S.38:2212: Louisiana public bidding statute discussed in the opinion.
  • La. R.S.38:2212A(1)(b): provision quoted on nonwaiver of bid requirements.

Source

Original opinion text

One American Place
301 Main Street, Suite 600
DEPARTMENT OF JUSTICE
P.O. Box 94005
CIVIl. DIVISION
TEL.: (225) 342-7013
BATON ROUGE
FAX: (225) 342-2090

RICHARD P. IEYOUB
70804-9005
ATTORNEY GENERAL

October 29, 2003
OPINION NUMBER 03-0401

90-A-1 Public Funds and Contracts
La. R.S. 38:2212
Honorable Lambert C. Boissiere, Jr.
State Senator
Emest N. Morial New Orleans Convention
6305 Elysian Fields Avenue
Center
New Orleans, LA 70122-4245

Dear Senator Boissiere:

You have requested an opinion of this office relative to the receipt of bids by the Ernest N. Morial New Orleans Hall Authority, for the project known as "Phase IV" of the Convention Center.

Your request specifically asks for an answer to the following questions:

1. Are the requirements set forth in the Bid Forms Exhibit #2 and Article 14.1 of Instructions to Bidders mandatory?

Does Exhibit #2 and Article 14 of Instructions to Bidders mandate the attachment of certificates or statement of insurability as to subpart 11.3 of "Article 11 Insurance and Bonds" as well as other subparts of Article 11 ?

If evidence of Builders Risk Insurance is required, but not furnished with the bid, is the requirement ($275,000,000 property damage coverage) subject to waiver as an informality?

Perhaps a discussion of the meaning and purpose of the Louisiana bid process would be in order before answering the above stated questions. The public bid process in Louisiana is governed by La. R.S.38:2212. The purpose of that statute is to insure fundamental fairness to the bidders in the process by setting forth specific requirements for particular bids. By requiring advertising in the obtaining of competitive bids, the tax paying citizens are protected against the awarding of public contracts through favoritism, fraud and possibly exorbitant and excessive prices. See Mickey O’Conner General Contractor, Inc. v. City of lVest Wego, 804 So.2d 128 (La. App. 5th Cir. 2001). It is a prohibitory law and its purpose is to prevent public officials from awarding contracts on the basis of favoritism.


Page 2

Senato~ Lambert C. Boissiere
OPINION 03-0401
Page2 of 5

This process is carried out through an agency requesting bids on a particular job by promulgating requirements or instructions for the particular bid. These instructions provide and instruct the bidders on the job and the special requirements for the job. The instructions are contained in the construction documents and are termed the "Instructions to Bidders".

The bid form is the actual document which describes and depicts the requirements for the job. Bidders are required to fill out and to present their Bid Form Proposals by a certain date. The law then requires the entity to open the documents and to award the contract to the lowest responsible bidder. In the case of the Convention Center, the bidders were given bid documents which included, among other things, the Instructions to Bidders, Bid Forms, and the Supplementary Conditions. These documents have the force and effect of law between the entity requesting the bid and the bidders. These instructions are contained in the construction documents and are termed the "Instructions to Bidders." By enacting the Public Bid Law, the Legislature balanced the competing policy interest, as is their role, and found that it is in the best interest of the taxpayers of Louisiana to award contracts in favor of a bidder who had complied with the bidding requirements in all respects. Such a policy prevents fraud and favoritism which is, after all, the ultimate goal of the public bidding system and encourages fair and equal competition.

In answer to question #1 we must consider that the provisions of the statutes requiring competitive bidding in the letting of municipal contracts are for the purpose of inviting competition, to guard against favoritism, fraud and corruption, and to secure the best work or supplies at the lowest price practicable. They were enacted for the benefit of property holders and taxpayers, and should be administered as to accomplish such purpose fairly and reasonably with sole reference to the public interest. These provisions are strictly construed by the courts and will not be extended beyond their reasonable purpose. Competitive bidding provisions must be read in light of the reason for their enactment, or they could be applied in such a way as to deny a municipality or public authority the ability to deal with problems in a sensible, practical way.

Inherent in the bidding process is the requirement that the public body shall prescribe a common standard on all matters that are material to the proposals. To that end the interested person may bid intelligently and will be induced to bid by the promise of impartiality. No scheme or device, which imposes limitations, not applicable to all bidders alike, should be tolerated. A public entity cannot waive deviations that are substantive in nature when awarding a public contract to the lowest responsible bidder. Bob Brothers Construction Co., L.L.C. v. Department of Transportation and Development, 698 So.2d 675 (La. App. 1 ~t Cir. 1997).

La. R.S.38:2212A(1)(b) provides:

The provisions and requirements of this Section, those stated in the advertisement for bids, and those required on the Bid Form shall not


Page 3

Senate" Lambert C. Boissiere
OPINION 03-0401
Page 3 of 5

be considered as informalities and shall not be waived by any public entity. (emphasis added).

In this case, the Bid Form stated that, "bidders shall attach insurance certificates or statement of insurability from bidders insurer to this page"¯ The substance of this requirement is set out in Art. 14 of the "Instructions to bidders: Section 14.1 of that document which provides:

14.1 Bidders shall deliver Certificates of Insurance or statement of insurability acceptable to the Owner with their bids, to demonstrate compliance with Article 11 of the Supplementary Conditions.

Section 14.2 of the article provides:

14.2 Failure of the Successful Bidder to deliver said Certificates of statement of insurability with the Bid may result in the Bid being deemed incomplete and non-responsive. In the event of such failure, the Owner reserves the right to offer the Contract to the next lowest responsive Bidder or re-advertise the project to request a corrq~letely new set of bids."

Thus, the documents which set out the requirements for the phase IV of the Convention Center required all of the bidders to attach certificates of insurance or statements of insurability to the bid.

The word "shall" as used in statutes, contracts, or the like, is generally imperative or mandatory. In common or ordinary parlance, the term "shall" is a word of command, and one which must be given a compulsory meaning. It has the significance of excluding the idea of discretion, and operates to impose a duty which must be enforced, particularly when used in cases involving public policy or the public interest. Given the use of the term "shall" in these documents, it is our opinion that as a matter of law, the requirements set forth in the Bid Form Exhibit No. 2 and Art. 14.1 of the Instructions to Bidders are mandatory.

A review of the relevant documents indicates that the answer to question #2 must be in the affirmative. Specifically, Exhibit No. 2 provides that the bidder shall attach the insurance certificate or statements of insurability from bidder’s insured to this page, and Art. 14 of the Instructions to Bidders provides that the bidders shall deliver certificates of insurance or statement of insurability acceptable to the owner with their bids to demonstrate compliance with Art. 11 of the Supplementary Conditions. This sentence clearly indicates that the bidder is required to deliver the certificates of insurance or statement of insurability with regard to all of the particular insurances listed in Art. 11 of the Supplementary Conditions. This also requires the attachment of all certificates of


Page 4

Senator Lambert C. Boissiere
OPINION 03-0401
Page 4 of 5

insurance or statemems of insurability for all of the insurance coverage required and the Supplementary Conditions found in Art. 11. Art. 14 also would require a particular type of coverage to the extent that subpart 11.3 provides that there should be a particular type of coverage.

In answer to question #3 we must point out that Louisiana law provides that a public entity may waive deviations that are not substantive in nature; however, it may not treat substantive requirements of the Bid Law, the advertisement for bid, and the Bid Forms as mere informalities in order to justify its decision to waive a deviation in a bid. In this case, the Bid Form and the Construction Documents both contain the word "shall". When reading these documents they must be given the interpretation that best conforms to the purpose of the law and the public interest. Clearly, the wording of these provisions connotes that the inclusion of the certificates of insurance or the statements of insurability in compliance with all of Art. 11 is mandatory. The bidders are not provided with a choice as to which insurance to provide, but instead are instructed to demonstrate compliance with "Art. 11 of the Supplementary Condition." Indeed, the bidders are reminded in section 14.2 of article 14 that the failure of the successful bidder to deliver said certificates or statements of insurability with the bid may result in the bid being deemed incomplete and non-responsive. That section further provides that in the event of such failure, the owner reserves the right to offer the contract to the next lowest responsive bidder or re-advertise the project to request a completely new set of bids. This section does not provide the entity with the ability to waive a particular bidder’s failure to provide any one of the insurance coverages listed in Art. 11. This would include a prohibition on the entity from waiving a bidder’s failure to provide the coverage enumerated in section 11.3 of Art. ll. Consequently, the failure of a bidder to fiLrnish a certificate of insurance or statement of insurability with regard to section 11.3 of Art. 11 is a substantive deviation from the requirements of the construction documents which cannot be waived by the terms of the documents. See La. R.S.38:2211 et seq. and Wallace Drennan, Inc. v. Sewage and Water Board ofNew Orleans, 798 So.2d 1167 (La. App. 4t~ Cir. 2001).

This conclusion is also consistent with section 4 of the Instructions to Bidders. That section entitled "Interpretation or Correction of Bid Documents provides at section 4.5, that should there be any discrepancy in the information contained in these documents, the more stringent requirements shall cover it." This section mandates the inclusion of all of the insurances set out in section 11. Accordingly, failure to submit the certificate of insurance or the statement of insurability for Builders Risk Insurance cannot be waived by the board. When this section is interpreted in light of the purpose of the statute to provide protection to the tax paying public it clearly leads to the conclusion that the bidders on this particular job were required to produce copies of all insurances enumerated in the subparts of Art. 11 of the Supplementary Conditions.


Page 5

Senato~ Lambert C. Boissi~e
OPINION 03-0401
Page 5 of 5

We trust that we have sufficiently answered the questions contained in your opinion request.

Very truly yours,

RICHARD P. IEYOUB
Attorney General

RPl:mmn

What does Louisiana law say today, for your facts?

This opinion is from 2003. Ezel checks the current Louisiana statutes and case law, applies them to your situation, and cites what it relies on.

Opens in Ezel Pro.

  • Checks the law as it stands today, not only this page
  • Cites every source it relies on, so you can verify it
  • Chat, drafting and research in one workspace