Is the Arkansas Wind Energy Development Act's April 9, 2025 'under development' exemption deadline constitutional, given that the Act took effect August 5, 2025 with no emergency clause? And does it apply to leases signed between those two dates?

Short answer The Attorney General found the April 9 exemption cutoff constitutional despite the Act's August 5 effective date and the absence of an emergency clause. A project with leases signed after April 9 and before August 5 is not exempt on that basis, but may still qualify if it began the required studies or construction by April 9. Leases signed before rulemaking ends do not themselves create an exemption.
State
Arkansas
Opinion
Opinion No. 2025-054
Issued
December 3, 2025
Issued by
Office of the Arkansas Attorney General
Requested by
State Senator Ronald Caldwell

Apply this to your situation

This page answers the general question as of 2025. Ask about yours and see what current Arkansas law means for your facts, with citations you can check.

Disclaimer: This is an official Arkansas Attorney General opinion. AG opinions are persuasive authority but not binding precedent. This summary is for informational purposes only and is not legal advice. Consult a licensed Arkansas attorney for advice on your specific situation.
About this page: The plain-English summary, reader guidance, and Q&A below were written by Ezel based on the official AG opinion. The original opinion (linked on this page) is the authoritative source for any reliance.

Plain-English summary

The Arkansas Wind Energy Development Act took effect August 5, 2025, but exempts projects already “under development” as of April 9. The Attorney General said that cutoff is constitutional despite the later effective date, the Public Service Commission's later rulemaking deadline, and the absence of an emergency clause. The Act uses past activity to decide which future obligations apply; it does not impose those obligations before its effective date.

A project may meet the “under development” definition through any one of three steps completed by April 9: executed land leases, commencement of necessary state and federal studies related to construction, or commencement of construction. Thus, a lease signed after April 9 but before August 5 does not establish the exemption by itself. PDF footnote 23 makes clear that the project could still qualify if one of the other conditions was met by April 9. Signing a lease before PSC rules are finalized also creates no exemption by itself.

What this means for you

If you develop a wind project

Check what your project had actually done by April 9, 2025. Preserve evidence of any executed leases, necessary studies, or construction begun by then. If none of those occurred, a lease signed between April 9 and August 5 does not qualify the project for the exemption. The opinion says nonexempt projects must comply with the Act from its effective date, regardless of when PSC rulemaking finishes.

If you have a wind lease

A lease executed by April 9 may be one route to the exemption. A later lease does not establish it, though other qualifying project work completed by April 9 might. The opinion does not decide the status of an individual project or interpret your lease terms.

If you administer the Act

Apply the three statutory alternatives separately. Footnote 23 says each is independently sufficient. The April 9 date is the cutoff for the qualifying activity; August 5 is when the Act became effective for nonexempt projects.

Common questions

Do all leases signed before August 5 fail to qualify?
No. Leases executed by April 9 can qualify a project. For a later lease, check whether necessary studies or construction began by April 9.

Does a lease signed after April 9 automatically make the project nonexempt? No. The Attorney General's answer about later leases assumes none of the other qualifying conditions was met before April 9.

Did the lack of an emergency clause invalidate the April 9 cutoff? No. The opinion distinguishes the exemption's reference to past activity from the Act's effective date and finds no requirement for an emergency clause here.

Does signing a lease before the PSC finishes its rules create an exemption? No. The opinion says the Act applies to nonexempt projects from August 5, 2025, regardless of when PSC rules are finalized.

Background and statutory framework

A.C.A. § 23-18-1418 contains the exemption, and A.C.A. § 23-18-1403(15) defines “under development.” The Attorney General describes the exemption as weakly retroactive because it uses April 9 activity to determine future duties. He concludes it does not change the legality of pre-effective-date conduct or impair vested lease rights. The opinion contrasts a prior opinion about an affirmative duty imposed before a law's effective date.

Source

Original opinion text

Opinion No. 2025-054

December 3, 2025

The Honorable Ronald Caldwell
State Senator
120 CR 393
Wynne, Arkansas 72396

Dear Senator Caldwell:

I am writing in response to your request for an opinion on the constitutionality of the retroactive exemption deadline found in Act 945 of 2025, the Arkansas Wind Energy Development Act (the “Act”).1 You state that because the Act lacked an emergency clause, it became effective on August 5, 2025.2 Had the General Assembly included a valid emergency clause under article 5, section 1 of the Arkansas Constitution, the Act could have taken effect immediately.3

You state that the Act exempts wind energy projects “under development” as of April 9, 2025.4 A project qualifies as “under development” if it has (1) executed land leases; (2) begun required state or federal studies related to construction; or (3) started construction.5 Finally, you state that the Act requires the Arkansas Public Service Commission (“PSC”) to develop rules by January 1, 2026.6

1
A.C.A. §§ 23-18-1401 to -1419. Acts 940 and 945 of the 95th General Assembly each added a Subchapter 13 to Title 23, Chapter 18 of the Arkansas Code. Under 945, Subchapter 13 was designated the “Arkansas Wind Energy Development Act.” But under Act 940, the same subchapter was titled, “Retirement of Dispatchable Electric Generation Facilities.” Because these two enactments conflicted, the Arkansas Wind Energy Development Act has been renumbered and now appears as Subchapter 14. 2 See Ark. Const. art. 5, § 1; Fulkerson v. Refunding Bd, 201 Ark. 957, 962, 147 S.W.2d 980, 983 (1941); Ark. Att’y Gen. Op. 2025-032. 3 Ark. Const. art. 5, § 1 (Referendum).
4
A.C.A. § 23-18-1418 (“A wind energy project is exempt from this subchapter if the wind energy facility project is under development as of April 9, 2025.”). 5 Id. § 23-18-1403(15).
6
Id. § 23-18-1419(a).

BOB R. BROOKS JR. JUSTICE BUILDING
101 WEST CAPITOL AVENUE
LITTLE ROCK, ARKANSAS 72201

The Honorable Ronald Caldwell
State Senator
Opinion No. 2025-054
Page 2

Against this background, you ask the following questions:

1. Does the retroactive exemption deadline of April 9, 2025, violate article 5, section 1 of the
  Arkansas Constitution on the grounds that:

       a. It precedes the effective date of the Act;

       b. It precedes the Public Service Commission rulemaking deadline; and

       c. The General Assembly did not include an emergency clause to justify the
          retroactivity?

   Brief response: No. Nothing in Article 5, § 1 of the Arkansas Constitution prohibits
                   retroactive laws.

2. If the answer to Question 1 is no, is the retroactive exemption deadline of April 9, 2025,
  otherwise not applicable to a wind energy project that executed land lease agreements after
  April 9, 2025, (but before the effective date of the Act) in light of Attorney General Opinion
  No. 91-101 and both the fact that:

       a. The exemption date still precedes the effective date of the Act; and

       b. The absence of an emergency clause undermines any claim of necessity for
          retroactive application?

   Brief response: Yes, wind energy projects that executed land leases after April 9, 2025,
                   but before the Act’s effective date of August 5, 2025, do not qualify for
                   the exemption.

3. If the answer is yes to either or both of the foregoing questions, would a wind energy project
  that executes leases prior to the finalization of the PSC’s rulemaking be exempt from the
  Act?

   Brief response: No, executing leases before the PSC rules are finalized does not exempt
                   wind energy projects from the Act’s requirements.

DISCUSSION

The Arkansas Wind Energy Development Act imposes new substantive obligations on wind energy developers. These include, but are not limited to:

The Honorable Ronald Caldwell
State Senator
Opinion No. 2025-054
Page 3

• Setback requirements.7

• Environmental impact assessments by qualified, third-party experts.8

• Acoustic emission limits.9

• Preconstruction noise modeling and enforcement.10

• Developing emergency procedures.11

• Establishing financial security for decommissioning.12

• Insurance requirements.13

The Act exempts wind energy projects deemed “under development” as of April 9, 2025. By implication, all other projects—those not qualifying for the exemption—must comply with the Act once it becomes effective on August 5, 2025. This implicit mandate, rather than the exemption itself, raises constitutional questions addressed below.

Question 1: Does the retroactive exemption deadline of April 9, 2025, violate article 5, section 1 of the Arkansas Constitution on the grounds that: a. It precedes the effective date of the Act; b. It precedes the PSC rulemaking deadline; and c. The General Assembly did not include an emergency clause to justify the retroactivity?

No, the retroactive exemption in A.C.A. § 23-18-1418 does not violate Article 5, § 1 or any other provision of the Arkansas Constitution. A retroactive provision may precede a legislative act’s effective date and remain valid —without an emergency clause—so long as it does not unlawfully

7
A.C.A. § 28-18-1406(a)(1)–(2).
8
A.C.A. § 28-18-1406(b)(1).
9
A.C.A. § 18-18-1406(c)(1).
10
A.C.A. § 23-18-1406(c)(2).
11
A.C.A. § 23-18-1407(b)(4).
12
A.C.A. §23-18-1408.
13
A.C.A. § 23-18-1409.

The Honorable Ronald Caldwell
State Senator
Opinion No. 2025-054
Page 4

impair vested rights, interfere with contractual obligations, or impose new substantive duties.14 Likewise, nothing in the Arkansas Constitution prohibits a retroactive provision from preceding a rulemaking deadline.

1.1 Retroactivity and constitutional limits. Retroactive provisions are not inherently unconstitutional.15 The federal and the Arkansas Constitutions prohibit only specific types of retroactive laws, including bills of attainder, ex post facto laws, and laws that impair contracts or violate the Due Process Clause, Takings Clause, or principles of separation of powers.16 The Arkansas Constitution provides equivalent protections in each of these areas.17 A retroactive law is unconstitutional if it falls within one of the prohibited categories—such as impairing contracts or violating due process.18

1.2 Retroactivity analysis. The exemption in A.C.A. § 23-18-1418 is retroactive because it impliedly alters the legal consequences of a past action or event.19 It does so by requiring any wind energy projects that fail to qualify as “under development” under A.C.A. § 23-18-1403(15) by April 9, 2025, to comply with the Act’s requirements, even though the Act is not effective until August 5, 2025. But there are different types of retroactivity, a distinction that helps clarify how the Act operates.

A law can be retroactive in two ways, which are sometimes called “strong” or “weak.”20 A law is strongly retroactive if it alters the past legal consequences of a past action or event in the past. A

14
2 Norman J. Singer & Shambie Singer, Sutherland Statutory Construction § 41:2 (8th ed., 2024); Hardin v. Fort Smith Couch & Bedding Co., 202 Ark. 814, 152 S.W.2d 1015, 1017–18 (1941); Archer v. Sisters of Mercy Health Sys., St. Louis, Inc., 375 Ark. 523, 294 S.W.3d 414 (2009). 15 Sutherland, § 41:1.
16
Id.
17
See, e.g., Ark. Const. art. 2, § 17 (Attainder—Ex post facto laws—Impairment of contract); Ark. Const. art. 2, § 8 (Criminal procedure—Double jeopardy—Right against self-incrimination—Due process); Ark. Const. art. 4, §§ 1 (Division of governmental authority), 2 (Separation of powers). 18 Sutherland, § 41:1.
19
See Landgraf v. USI Film Prods., 511 U.S. 244, 269–70, 280 (1994) (requiring courts to assess whether a statute is retroactive by “ask[ing] whether the new provision attaches new legal consequences to events completed before its enactment” and requiring courts to “first … determine whether [the legislature] prescribed the statute’s proper reach”). 20 While numerous courts and scholars have recognized and applied this distinction, they often use different labels for the two kinds of retroactivity: E.D. Ark.: St. Bernard’s Hosp., Inc. v. Sullivan, 781 F. Supp. 576, 590–91 (E.D. Ark. 1991); D.C. Cir.: Nat’l. Cable & Telecomms. Assn. v. FCC, 567 F.3d 659, 670 (D.C. Cir. 2009); 5th Cir.: FDIC. v. Faulkner, 991 F.2d 262, 266 (5th Cir. 1993); 9th Cir.: Nat’l Med. Enters., Inc. v. Sullivan, 957 F.2d 644, 671 (9th Cir. 1992); Calif.: 20th Century Ins. Co. v. Garamendi, 878 P.2d 566, 607 (Cal. 1994) (en banc); New Jersey: Harris v. Branin Transp., Inc., 711 A.2d 311, 337 (N.J. 1998) (“A pure retroactive statute changes what the law was in the past. Bowen v. Georgetown Univ. Hosp., 488 U.S. 204, 220 (1988) (Scalia, J., concurring). A law or rule that has

The Honorable Ronald Caldwell
State Senator
Opinion No. 2025-054
Page 5

law is weakly retroactive when it alters the past legal consequences of a past action or event only at and after the act’s effective date.

The Act’s exemption is weakly retroactive. It does not alter the legal status of actions taken before the Act’s effective date. Instead, it uses a past date (April 9, 2025) to determine which projects are exempt from future obligations. In doing so, the Act does not impose new duties or penalties on completed actions but merely references those actions to establish future compliance requirements.

Importantly, the Act does not retroactively impair vested rights as it does not revoke any rights legally acquired before its effective date. For instance, entering into a land use lease after April 9, 2025, but before August 5, 2025, does not create a vested right to avoid future regulation.21

Finally, the Act does not interfere with existing contractual obligations. It does not invalidate or alter the terms of leases or agreements executed before the Act’s effective date. The Act’s obligations—such as setback requirements, environmental assessments, and insurance mandates— apply only prospectively.

One might contend that, although the Act’s requirements are technically prospective, they function in practice as of April 10, 2025, because any wind energy project that does not qualify for the exemption must ultimately comply with the Act once it takes effect. For example, a non-exempt developer might construct a wind turbine after April 9, 2025, in a location that does not meet the Act’s setback requirements, only to be required to relocate the turbine after the Act becomes effective.

Even in that scenario, the Act operates prospectively because the obligation to comply arises only upon the Act’s effective date. While this may raise fairness concerns, the mere possibility of unfairness does not override the legislature’s intent, as discussed above in section 1.1. Thus, projects that do not qualify for the exemption must comply with the Act’s requirements after the Act becomes legally effective, not before.

With the general constitutional validity of the retroactive exemption addressed, the analysis next addresses article 5, section 1 of the Arkansas Constitution to explain why the exemption in A.C.A.
§ 23-18-1418 does not violate it.

1.3 Constitutional analysis. Nothing in article 5, section 1 of the Arkansas Constitution prevents the retroactive exemption in A.C.A. § 23-18-1418 from preceding the Act’s effective date. Article 5, section 1 is chiefly concerned with protecting the initiative and referendum power reserved to

exclusively future effects, but that affects past transactions is ‘secondarily retroactive.’ Ibid. A secondarily retroactive law is valid so long as it is not arbitrary or capricious. Ibid.”). See also Daniel E. Troy, Toward a Definition and Critique of Retroactivity, 51 Ala. L. Rev. 1329, 1334–35 (2000). 21 See, e.g., United States v. Locke, 471 U.S. 84, 104 (1985) (holding that the regulation of property rights does not amount to a taking when individuals can still realize their investment-backed expectations by complying with reasonable regulations and that individuals do not have a vested right to be free from regulation).

The Honorable Ronald Caldwell
State Senator
Opinion No. 2025-054
Page 6

the people of this state. The retroactive exemption does not affect the people’s right to petition for a referendum or make the Act immediately effective. Instead, it applies the Act’s rules to events or actions that were complete before the Act’s effective date, but that application is only on and after the Act’s effective date, as explained above.

Likewise, article 5, section 1 of the Arkansas Constitution does not reference rulemaking deadlines, nor does it imply that rulemaking must precede a law’s effective date for it to be constitutional. The Act does not require enforcement before the Arkansas Public Service Commission promulgates its rules. In fact, the retroactive exemption reduces the need for immediate enforcement, since projects under development as of April 9, 2025, are exempt from the Act.

Moreover, the Arkansas Administrative Procedures Act, codified in A.C.A. § 25-15-201 et seq., governs the rulemaking process in Arkansas. Arkansas Code § 25-15-204 requires agencies, like the Arkansas Public Service Commission, to follow notice-and-comment procedures for rulemaking, a process that could not occur before legislation is enacted. It is common for regulatory statutes, such as the Arkansas Wind Energy Development Act, to become effective before the rulemaking process is complete.

Finally, the General Assembly is not required to include an emergency clause to justify a retroactive exemption. As explained above, retroactive provisions are not inherently unconstitutional.22

Question 2: If the answer to Question 1 is no, is the retroactive exemption deadline of April 9, 2025, otherwise not applicable to a wind energy project that executed land lease agreements after April 9, 2025, (but before the effective date of the Act) in light of Attorney General Opinion No. 91-101 and both the fact that: a. The exemption date still precedes the effective date of the Act; and b. The absence of an emergency clause undermines any claim of necessity for retroactive application?
Yes, the retroactive exemption is not applicable to wind energy projects that executed land lease agreements after April 9, 2025, but before the Act’s effective date of August 5, 2025, assuming none of the other conditions for qualifying for the exemption have been met before April 9, 2025.23

22
State v. Kline, 23 Ark. 587, 588 (1861) (“The proposition that a statute is void merely because its terms are retroactive, cannot be maintained.”). 23 A wind energy project qualifies as “under development” if it has “(1) [e]xecuted land leases; (2) [c]ommenced necessary state and federal studies related to construction of a wind energy facility; or (3) [c]ommenced construction of a wind energy facility[.]” See A.C.A. § 23-18-1403(15). Because this list is disjunctive, each condition is independently sufficient for qualifying for the exemption. See Antonin Scalia & Bryan A. Garner, Reading Law: The Interpretation of Legal Texts 116 (2012).

The Honorable Ronald Caldwell
State Senator
Opinion No. 2025-054
Page 7

As explained above, a retroactive provision may precede an effective date. The inclusion of a retroactive provision does not make a legislative act immediately effective. Thus, the absence of an emergency clause does not invalidate a retroactive provision.

Your question references Attorney General Opinion No. 91-101. That opinion addressed Act 860 of 1991, which required taxpayers to assess their tangible personal property before the law’s effective date.24 My predecessor concluded that, absent an emergency clause, the requirement to assess tangible personal property before the effective date could not be enforced.25

The retroactive exemption found in A.C.A. § 23-18-1418 differs significantly. Act 860 imposed an affirmative obligation—requiring taxpayers to assess tangible personal property before the law became effective. In contrast, the retroactive exemption in the Wind Energy Development Act operates passively: it relieves qualifying wind energy projects from future compliance without requiring any action before the Act takes effect. Here, no action is required before the effective date, and the exemption merely identifies which projects will be subject to future obligations. Therefore, projects that executed land lease agreements after April 9, 2025, but before August 5, 2025, do not qualify for the exemption and must comply with the Act. While the Act does not impose any legal obligations before August 5, 2025, non-exempt developers who intend to begin projects before that date need to prepare for compliance in advance to avoid delays, disruptions, or violations once the Act becomes effective and the PSC rulemaking is complete.

Question 3: If the answer is yes to either or both of the foregoing questions, would a wind energy project that executes leases prior to the finalization of the PSC’s rulemaking be exempt from the Act?

Wind energy projects are not exempt from the requirements of the Act merely because they execute a lease before the Arkansas Public Service Commission finalizes its rulemaking. As discussed above in section 1.3, the Act became effective on August 5, 2025, and it applies to all nonexempt projects from that date forward, regardless of when the PSC completes its rulemaking.

Assistant Attorney General Justin Hughes prepared this opinion, which I hereby approve.

Sincerely,

TIM GRIFFIN
Attorney General

24
Ark. Att’y Gen. Op. 91-101.
25
Id.

What does Arkansas law say today, for your facts?

This opinion is from 2025. Ezel checks the current Arkansas statutes and case law, applies them to your situation, and cites what it relies on.

Opens in Ezel Pro.

  • Checks the law as it stands today, not only this page
  • Cites every source it relies on, so you can verify it
  • Chat, drafting and research in one workspace