Stop-Notice - North Dakota
NORTH DAKOTA CONSTRUCTION-LIEN CLAIM NOTICE AND OWNER-WITHHOLDING REQUEST
Use limitation: This document does not itself create, perfect, extend,
enforce, release, or bond off a construction lien. It does not impose a
mandatory payment freeze. Complete it only after North Dakota counsel
classifies the claimant and confirms the current statutory sequence.
1. Purpose and use selection
Select every intended use:
☐ Pre-recording notice under N.D.C.C. § 35-27-02(4). Counsel has confirmed
that written notice stating that a lien will be claimed must be sent to the
legal or equitable owner by certified mail at least ten days before recording.
☐ Claim notice under N.D.C.C. § 35-27-09. Counsel has confirmed that the
claimant has a lien under the contractor, the contractor is liable for the
claim, and the notice may be served on the owner.
☐ Itemized and verified account requested by the owner under N.D.C.C.
§ 35-27-09. Attach the completed account and use the verification selected
by counsel.
☐ Informational payment request only. No representation is made that a
statutory lien or withholding condition has been satisfied.
Do not use this packet as:
- a direction to a construction lender or unrelated disbursing agent;
- a substitute for the recorded lien required to perfect a claim;
-
a demand for a percentage reserve, segregated account, injunction, bond,
interest, attorney fees, indemnity, or damages; or -
an agreement by the owner, contractor, or any recipient.
2. Current-law and deadline gate
| Issue | Counsel's conclusion | Official authority or instruction | Checked |
|---|---|---|---|
| Claimant is within § 35-27-02 and not excluded | [________________________________] | [________________________________] | [__/__/____] |
| Correct legal or equitable owner identified | [________________________________] | [________________________________] | [__/__/____] |
| Contractor tier and person liable identified | [________________________________] | [________________________________] | [__/__/____] |
| Contract price paid and remaining balance investigated | [________________________________] | [________________________________] | [__/__/____] |
| Required pre-recording notice and certified-mail date | [________________________________] | [________________________________] | [__/__/____] |
| County recorder, property description, and recording requirements | [________________________________] | [________________________________] | [__/__/____] |
| First and last contribution dates | [________________________________] | [________________________________] | [__/__/____] |
| Any owner demand under § 35-27-25 located and calendared | [________________________________] | [________________________________] | [__/__/____] |
| Enforcement-notice, suit, and lis-pendens dates | [________________________________] | [________________________________] | [__/__/____] |
| Bankruptcy, public-project, bond, leasehold, lender, or priority issue | [________________________________] | [________________________________] | [__/__/____] |
3. Claimant and project information
Claimant
- Legal name: [________________________________]
- Entity or individual status: [________________________________]
- Address: [________________________________]
- Email and telephone: [________________________________]
- North Dakota license information, if applicable: [________________________________]
Project
- Street address: [________________________________]
- County: [________________________________]
- Complete legal description: [________________________________]
- Legal or equitable owner: [________________________________]
- Owner's last-known address: [________________________________]
- Person who contracted with claimant: [________________________________]
- Claimant's tier: ☐ Direct contractor ☐ Subcontractor ☐ Supplier
☐ Laborer ☐ Design or professional service ☐ Other: [________________]
Contribution
- Contract or order date: [__/__/____]
- First contribution date: [__/__/____]
- Last contribution date: [__/__/____]
-
Labor, skill, services, equipment, or materials furnished:
[____________________________________________________________] -
Property or improvement receiving the contribution:
[____________________________________________________________]
4. Itemized claim
| Invoice or item | Date | Description | Original amount | Credits or payments | Claimed balance |
|---|---|---|---|---|---|
| [____________] | [__/__/____] | [________________] | $[________] | $[________] | $[________] |
| [____________] | [__/__/____] | [________________] | $[________] | $[________] | $[________] |
| [____________] | [__/__/____] | [________________] | $[________] | $[________] | $[________] |
| Totals | $[________] | $[________] | $[________] |
Disputed items, offsets, retainage, change orders, or payment defenses known to
claimant: [____________________________________________________________]
Amount attributed to lienable contribution after counsel review:
$[________________]
Do not add a fixed percentage for interest, costs, or fees. State each claimed
component separately and identify its contract or current-law basis.
5. Notice to owner
Date: [__/__/____]
To: [LEGAL OR EQUITABLE OWNER NAME AND ADDRESS]
From: [CLAIMANT NAME AND ADDRESS]
Project: [PROJECT ADDRESS AND LEGAL DESCRIPTION]
Person with whom claimant contracted: [NAME]
Claimed amount: $[________________]
The claimant states that it furnished the contribution identified in this
packet and that the stated balance remains claimed after the listed credits and
payments.
If the pre-recording-notice box in Section 1 is selected, claimant gives written
notice that a construction lien will be claimed. Counsel must arrange certified
mail early enough to satisfy N.D.C.C. § 35-27-02(4); this sentence does not cure
late or defective delivery.
If the § 35-27-09 claim-notice box in Section 1 is selected, claimant serves
notice of its claim on the owner. Claimant requests that the owner evaluate the
owner's option under N.D.C.C. § 35-27-09 to withhold from the owner's contractor
so much of the contract price as may be necessary to meet qualifying lien
demands for which that contractor is liable.
This is a request for evaluation, not a representation that withholding is
mandatory. It is not directed to a lender and creates no private default,
segregated-account duty, liability cap, indemnity, bond amount, or fee right.
Please direct factual questions or payment communications to:
- Contact: [________________________________]
- Address or email: [________________________________]
- Requested response date, if any: [__/__/____]
The requested response date is an administrative request and does not alter any
statutory deadline or remedy.
6. Optional itemized and verified account
Complete this section only if the owner made a timely written request under
N.D.C.C. § 35-27-09 and counsel confirms this packet supplies the requested
information.
- Date the underlying contract was completed: [__/__/____]
- Date owner delivered the request: [__/__/____]
- Claim amount: $[________________]
-
Claimant name and address:
[____________________________________________________________] -
Attached itemized account identifier: [________________________________]
Counsel-selected verification
I, [NAME], state that I am authorized to verify the attached account; that I
reviewed the account and supporting records; and that the account is true and
correct to the extent stated, subject to the disclosed credits, offsets, and
disputes.
Signature: ______________________________
Date: [__/__/____]
Notary, oath, declaration, and signer language:
[____________________________________________________________]
7. Deadline worksheet
These entries are screening prompts, not automatic deadline calculations.
| Event | Current rule reflected in fetched Chapter 35-27 | Case-specific date |
|---|---|---|
| Pre-recording owner notice | Certified mail at least 10 days before recording under § 35-27-02(4) | [__/__/____] |
| Ordinary perfection period | Record within 90 days after all of claimant's contribution is done under § 35-27-13 | [__/__/____] |
| Outside filing limit | A lien may not be filed more than 3 years after the first item of material is furnished under § 35-27-14 | [__/__/____] |
| Pre-enforcement notice | Personal service at least 10 days before suit, or registered mail at least 20 days before suit, under § 35-27-24 | [__/__/____] |
| Owner's suit demand | Suit and lis pendens within 30 days after delivery when a compliant § 35-27-25 demand was delivered and filed | [__/__/____] |
| Outside enforcement limit | Action and lis pendens within 3 years after recording under § 35-27-25 | [__/__/____] |
Counsel must reconcile these rules with the actual claimant, contribution,
recording date, payment history, owner demand, project type, and any controlling
order or proceeding. Section 35-27-14 also describes consequences of filing
after ninety days; do not summarize those consequences without applying the
actual purchaser, encumbrancer, owner-payment, and recording facts.
8. Delivery and record log
| Recipient | Role | Address | Method | Sent | Delivered | Evidence retained |
|---|---|---|---|---|---|---|
| [____________] | Legal or equitable owner | [____________] | [____________] | [__/__/____] | [__/__/____] | [____________] |
| [____________] | Contractor | [____________] | Informational copy only | [__/__/____] | [__/__/____] | [____________] |
| [____________] | Other | [____________] | Informational copy only | [__/__/____] | [__/__/____] | [____________] |
☐ Certified-mail receipt and tracking retained if § 35-27-02(4) was selected
☐ Complete signed packet and every attachment retained
☐ Recorded-lien copy and recorder receipt added separately, if applicable
☐ Enforcement notice, service proof, complaint, and lis pendens tracked
separately, if applicable
9. Claimant signature
I authorize delivery of this packet for the use or uses selected in Section 1.
I understand that it is not the recorded construction lien and that recipients
do not become bound merely by receiving it.
| Claimant | |
|---|---|
| Legal name | [________________________________] |
| By | ______________________________ |
| Printed name and title | [________________________________] |
| Date | [__/__/____] |
10. Recipient acknowledgment — optional
Receipt acknowledged only; no validity, amount, priority, withholding duty,
payment promise, waiver, or agreement is admitted.
| Recipient | |
|---|---|
| Name and role | [________________________________] |
| Signature | ______________________________ |
| Date received | [__/__/____] |
Sources and References
About this template
- Last updated
- August 27, 2026
- Citations checked
- August 27, 2026
- Jurisdiction
- North Dakota
- Category
- Real Estate
Legal authority
- N.D.C.C. § 35-27-02
- N.D.C.C. § 35-27-09
- N.D.C.C. § 35-27-13
- N.D.C.C. § 35-27-14
- N.D.C.C. § 35-27-24
- N.D.C.C. § 35-27-24.1
- N.D.C.C. § 35-27-25
Real estate documents transfer ownership, define who can use a property, and record agreements between buyers, sellers, landlords, and tenants. Deeds, purchase agreements, leases, and easements have to be drafted to meet state recording requirements, and mistakes show up at closing or years later in title disputes. Good real estate paperwork moves transactions forward quickly and avoids the kind of problems that only surface when it is time to sell or refinance.
Not legal advice
This template is provided for informational purposes. We recommend having an attorney review any legal document before signing, especially for high-value or complex matters.
Checked against the law it cites
A reviewer verified this template's legal citations against the official source on August 27, 2026.
N.D.C.C. § 35-27-02(4) (checked August 27, 2026): "Written notice a lien will be claimed must be given to the legal or equitable owner of the real estate by certified mail at least ten days before the recording of the construction lien."
N.D.C.C. § 35-27-09 (checked August 27, 2026): "The owner may withhold from the owner's contractor so much of the contract price as may be necessary to meet the demands of all persons, other than such contractor, having a lien upon the premises for labor, skill, or material furnished for the improvement, and for which the contractor is liable."
N.D.C.C. § 35-27-13 (checked August 27, 2026): "Every person desiring to perfect the person's lien shall record with the recorder of the county in which the property to be charged with the lien is situated, within ninety days after all the person's contribution is done."
N.D.C.C. § 35-27-14 (checked August 27, 2026): "A lien may not be filed more than three years after the date of the first item of material is furnished."
Draft your Stop-Notice in the editor
Answer a few questions, let the AI editor draft each section from your answers, review it, and download Word and PDF. $99 one time, or $249 per month for every document and every Ezel app.